The critical path for the network shown is: A. 1-3-6-7. B. 1-2-4-7. C. 1-4-7. D. 1-3-4-7. E. 1-2-5-7.
Q: What are stakeholders and three examples?
A: For this Q, I would determine the term stakeholders. let's proceed with three examples, all the…
Q: Describe two Qualitative and Quantitative Risk Analysis Techniques
A: Risk analysis is an essential component of project and organizational management. Qualitative and…
Q: A gift shop expects to sell 400 wind chimes during the next year. It cost $4 to store one wind chime…
A: To minimize inventory costs, a business must balance the cost of holding inventory with the cost of…
Q: You are the new Chief Design Officer (CDO) of a start-up, DTUI Inc. The project is to design a…
A: Management Strategy for Creating a Pottery Selling System: Analysis of Requirements (4 weeks): This…
Q: 1. Construct an AON network diagram from the data given 2. Construct an AOA network diagram from the…
A: A network diagram is a graphical representation of project which helps to identify the activity…
Q: A shirt manufacturer buys cloth by the 100-yard roll from a supplier. For setting up a control chart…
A: C-chart is a model of control chart which considering the countable model of irregularities. The…
Q: What lessons do you learn from the entrepreneurial journey of Innotech Oman
A: Innotech Oman is a forward-thinking Omani tech startup that specialises in digital transformation…
Q: The DSDM stands for a set of values and ideals; could you summarise them for me? When working on…
A: DSDM was developed in 1994 by a collaboration of UK software development experts and has now become…
Q: Do you happen to be able to think of any way to increase the machine's production while…
A: Production is the combination of the inputs to have the required output. It includes various tools,…
Q: Recognize field traits. Differentiate project management and software development.
A: In an Organizational area, specifically in the domain of project management and software…
Q: Recently, the ABC company hired Filis Diax as president. She is charged with making the necessary…
A: Business management is the process of managing the activities of a business in such a way that helps…
Q: A manager states that her process is really working well. Out of 1,500 parts, 1,477 were produced…
A: Performance management includes all those activities that are important for achieving the goals of…
Q: Note: In problems 1, 2, and 3, the constraints are the same. This means the feasible regions are the…
A: Here, Constraints are mentioned below, 2X1+4X2≤146X1+2X2≤12X1 and X2≥0 These constraints are same…
Q: You work for the Treasury Department. GDP is $20T right now, and 100M workers make $8T in wages. You…
A: Forecasting methods are those methods that are used by the business organization for determining the…
Q: What exactly has happened between manufacturers and buyers? Give an example of where it may be found…
A: The buyer-manufacturer relationship refers to the interaction and interdependence between companies…
Q: A firm is attempting to minimize its shipping costs. The firm has 3 factories and must supply the…
A:
Q: (c) What is the total profit contribution Kelson can earn with the given production quantities? $…
A:
Q: Which of the following regarding the impact of batch size is WRONG? a. A large batch size…
A: There is a clear correlation between batch size, risk, and cycle time. Each element aids in the…
Q: Use the ER Diagram shown on Figure 2 to anewer questions 6 and 7: 6. According to the ER diagram on…
A: Business management is the process of managing the activities of a business in such a way that it…
Q: How can I Evaluate 2 quality-management tools or strategies used in the healthcare industry? Include…
A: The procedures or methods used to improve the quality of healthcare services and patient outcomes…
Q: This raises the question of whether or not engineers have an obligation to create code that can be…
A: Business ethics are the rules, regulations, and values that guide the behavior of an individual in…
Q: Which of the following industries/sectors would not use supply chain management principles and…
A: Supply chain management (SCM) is a set of principles, practices, and techniques used to manage the…
Q: It's possible that poor software project management was to blame for the catastrophic baggage system…
A: The failure related to the baggage system at Denver International Airport happened due to…
Q: Provide two rework cost-cutting methods. Both strategies need incremental delivery.
A: Rework cost-cutting methods aim to reduce the expenses related to correcting defects or errors in a…
Q: Which of the following is the single most critical factor in assuring the long-term survival of…
A: Advanced real-time systems are complex and sophisticated software systems that are designed to…
Q: ple: Kings Apple Apple's fiscal third quarter P&L results were impressive. But one balance sheet…
A: Apple Inc., a global technology giant, is known for its innovative products and excellent supply…
Q: Can you help me to solve this question? The case study is in image. Supply chain network: For a…
A: The supply chain for perishable and short-shelf-life food goods such as bread needs a one-of-a-kind…
Q: What exactly is ISO, and why should a systems developer care about it?
A: It stands for standards. A standard is simply a collection of guidelines for performing a certain…
Q: Customers arrive at Rich Dunn's Styling Shop at a rate of 3 per hour, distributed in a Poisson…
A: Arrival Rate (λ) = 3 per hourService Rate (μ) = 8 per hour
Q: Part 1. (A) Describe at least 2 benefits of an organization outsourcing its production…
A: Outsourcing is the practice of hiring an external company or individual to perform tasks or provide…
Q: An operations manager has compiled the information below for four manufacturing alternatives (A, B,…
A:
Q: Argument is best defined as a means of convincing your audience to think, feel, or act in a certain…
A: Arguments are omnipresent in today's world, from political disputes to social media discussions. But…
Q: How can communication affect project delivery in project management?
A: Project management is dependent on effective communication. It can have a considerable effect on a…
Q: • Will configure-to-order and postponed production work elsewhere? If not, why not?
A: Customers may use configure-to-order to personalize their purchases based on their individual needs…
Q: A popular, local coffeeshop in one of the suburbs of New York City (NYC) estimates they use 3,000…
A: Economic order quantity helps the company in deciding what should be ordered by an inventory manager…
Q: A company must choose whether to manufacture a component product in-house or to outsource the work…
A: Deciding whether to produce a component product internally or contract the labor to a third party…
Q: Use the following data and table to calculate the correlation coefficient and interpret the result.
A: First of all, the line items per order are to be calculated: Day Line items Orders Line items per…
Q: What does it imply when someone says they have a "operation call"
A: A scheduled meeting or conference call focused on discussing and directing the execution of a…
Q: When choosing a project management approach, do you prefer the tried-and-true waterfall technique or…
A: There are numerous approaches to project management to consider. Two common choices are the…
Q: xplain in only five words what Lean Development is and why it is beneficial by offering two…
A: Lean Development is a methodology for developing products or processes that focus on maximizing…
Q: What is the purpose of six sigma?
A: To be determined: what is the purpose of six sigma? Six Sigma is a technique that provides…
Q: Establishing a comparable-worth plan should include all of the following except: A Adopt a single…
A: Establishing a comparable-worth plan is a strategy used to ensure that jobs that are different but…
Q: How possible is it for MCDO to jump on the plant-based food train? Would it be sustainable business…
A: Sustainability is becoming increasingly important in today's world, as human activities continue to…
Q: Consider a case of TWO sisters fighting over an orange and as a way to end the quarrel, they decide…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements…
A: Cost is the amount that is incurred by the company on producing goods and services by using raw…
Q: State and explain how an organization treat its environment in the context of domain of managerial…
A: The collection of external circumstances and factors that have the ability to have an impact on any…
Q: An investor has at most $10,000 to invest in government bonds, mutual funds, and money market funds.…
A: Let the amount invested in Government bonds be G, mutual funds be M and Money market funds be K. The…
Q: Explain the postal rule in detail.
A: Postal Rule Postal rule is a contract law principle. The postal acceptance rule is also known as…
Q: What is next step?
A: Previously, the LPP has been formulated. Now, it has to be solved to find the optimal amount of…
Q: Communication in organizations Mention and explain in your own words the determining factors in…
A: Effective communication is critical in organisations because it fosters collaboration, coordination,…
A project is represented by the following diagram:
2. The critical path for the network shown is:
A. 1-3-6-7.
B. 1-2-4-7.
C. 1-4-7.
D. 1-3-4-7.
E. 1-2-5-7.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- For data given below draw an AON diagram and calculate ES, EF, LS, LF and Slack? Activity Duration Immediate Predecessor A 2 - B 3 - C 5 A D 9 B E 5 C,D F 5 D G 2 EHumber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 33 B Develop Client Prospectus ― 21 C Perform Design Analysis ― 35 D Program Back End A, B, C 47 E Program Front End A 13 F Project Consolidation D, E 11 (a) For the given project, fill in the nodes of the network diagram below. A E 33 13 Start B D F Finish Time 21 47 11 Time C 35 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…This was a three part question. Bartelby helped me get A and B. The picture for Part A is the network diagram and Part B's answer is below for the critical path. My question I need to answer is Part C which is in the second picture. Part B There are the following paths in the project network. A –> B –> D –> G –> J = 2 + 4 + 2 + 3 + 7 = 18 A –> B –> E –> G – >J = 2 + 4 + 1 + 3 + 7 = 17 A –> B –> F –> H –> J = 2 + 4 + 8 + 5 + 7 = 25 A –> C –> F –> H –> J = 2 + 5 + 8 + 5 + 7 = 27 A –> C –> F –> I –> J = 2 + 5 + 8 + 4 + 7 = 26 The longest path in all the possible paths of the project network is A –> C –> F –> H –> J with the longest time. Therefore, the project duration is 27 days.
- A. Create the NETWORK DIAGRAM B. Theprocesses that are included in the critical path are: for example A-B-C-D C.The total number of days to finish the project is within how many days?The conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity. a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?9.2. Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack for each activity:Activity Activity Predecessor Time (Weeks)1 — 32 — 73 1 24 2 55 2 66 4 17 5 4 Present a Gantt Chart that shows the timeline from start to end. This calls for drawing an A-O-N network diagram using the information given in the Table. Present a Table of Activity versus Slack (wks) and state which specific activities are on the Critical path.
- Construction of a building is based on the followingCPM network:a. Draw the network for this project and label theactivities.b. What are the normal project completion time and normal cost?c. Identify the critical path.d. How much will it cost to crash the project completion by one day? by two days?e. What is the minimum time for project completion?(a) The critical path for the network activities shown below is? (b) What is the completion time in weeks? Refer attached image Activity Preceding Time A - 8 B - 10 C A , B 5 D B 8 E C , D 6The following represents a project that should be scheduled using CPM a. Complete the table b. Draw the Network Diagram c. What is the critical path? d. What is the expected project completion time?' e. What is the probability of completing this project within 16 days?
- The VOXN Cinema is installing a new system to enhance the quality of movies shown. Assume that the following table provides information on the immediate predecessor relation and time estimated for each event. a.List the possible eight events which you think essential in expanding a Cinema.b. Draw a network diagramc.find the total time required to complete the project d. List the critical events of the project. Activity immediate predecessor Time (weeks) A - 3 B - 4 C A 6 D B 2 E A 5 F C 2 G D , E 4 H F , G 5Given the following table, construct a network diagram, either AOA or AON. Times are in days.a. Determine the expected duration of the project.b. Compute the probability that the project will take at least 18 days.Path Activity Time EstimatesA 4-5-6Top B 7-8-10C 3-5-9D 7-8-11Bottom E 2-3-4F 1-4-6The Advanced Tech Company has a project to design anintegrated information database for a major bank. Datafor the project are given in Table 7.6. Indirect project costsamount to $300 per day. The company will incur a $150 perday penalty for each day the project lasts beyond day 14.a. What is the project’s duration if only normal times are used?b. What is the minimum-cost schedule?c. What is the critical path for the minimum-cost schedule?