The Engineering Solutions Company Limited (ESCL) ha for, and won a contract to design and build a computerize warning system in Trinidad and Tobago. Consider the ac durations, and predecessor relationships to roll out this the following network, shown in Table 7 below. Draw the and ans wer the questions that follow

Fundamentals of Information Systems
8th Edition
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Ralph Stair, George Reynolds
Chapter8: Systems Development
Section: Chapter Questions
Problem 3DQ
icon
Related questions
Question
The Engineering Solutions Company Limited (ESCL) has tendered
for, and won a contract to design and build a computerized flood-
warning system in Trinidad and Tobago. Consider the activities,
durations, and predecessor relationships to roll out this project, in
the following network, shown in Table 7 below. Draw the network
and answer the questions that follow.
ESCL Computerized Flood-Warning System Project
Immediate
Activity
Description Predecessor(s)
Time
Optimistic Most Likely Pessimistic
(Weeks)
(Weeks)
(Weeks)
A
4
1
4
7
---
C
A.
2
2
2
D
В
1
7
10
D
4
F
E
1
2
3
G
C
17
H
D, G
3
7
11
I
D
8
10
J
F, H
4
5
K
I
1
1
1
a) Using a network, what is the earliest expected time of
completion of the whole
project?
c) Using the information from Table 7, what is the probability that
the project can be completed in 28
days?
d) Using the information from Table 7, if the project manager
wants at least a 98% probability that the project will be
completed on or before the due date, what is the shortest
project due date that will satisfy the project
manager?
Transcribed Image Text:The Engineering Solutions Company Limited (ESCL) has tendered for, and won a contract to design and build a computerized flood- warning system in Trinidad and Tobago. Consider the activities, durations, and predecessor relationships to roll out this project, in the following network, shown in Table 7 below. Draw the network and answer the questions that follow. ESCL Computerized Flood-Warning System Project Immediate Activity Description Predecessor(s) Time Optimistic Most Likely Pessimistic (Weeks) (Weeks) (Weeks) A 4 1 4 7 --- C A. 2 2 2 D В 1 7 10 D 4 F E 1 2 3 G C 17 H D, G 3 7 11 I D 8 10 J F, H 4 5 K I 1 1 1 a) Using a network, what is the earliest expected time of completion of the whole project? c) Using the information from Table 7, what is the probability that the project can be completed in 28 days? d) Using the information from Table 7, if the project manager wants at least a 98% probability that the project will be completed on or before the due date, what is the shortest project due date that will satisfy the project manager?
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Software Development Approaches
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Fundamentals of Information Systems
Fundamentals of Information Systems
Computer Science
ISBN:
9781305082168
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning
Principles of Information Systems (MindTap Course…
Principles of Information Systems (MindTap Course…
Computer Science
ISBN:
9781305971776
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning
Principles of Information Systems (MindTap Course…
Principles of Information Systems (MindTap Course…
Computer Science
ISBN:
9781285867168
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning