Use a graphical approach such as Critical Path Method (CPM) ■ Captures the activities and their inter- relationships using a graph (network of precedence relationships) Code ■ Data take-of ■ Lines are used to represent the activities ■ Nodes are used to represent the start and stop of activities USED IN: the jobs repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience. Adding time dimension . The forward pass ■ calculate the earliest start dates of the activities Earliest start date ■ To calculate the project completion date . The backward pass calculate the latest start dates for activities identify the critical path from the graph 1 Program test 3 6 7 Event Number Latest start date Slack (a measure on how late an event may be without affecting the end date of the project) + Id A B C D E F G H I Activity Name Design the project 4 framework Contract with sponsors and partners Identify and contract with startup businesses and collaborators Acquiring a location Designing and maintaining the shipping containers Acquiring materials and the required infrastructure Review application of startups that focus on providing good services Providing incubation Duration(Weeks) Precedents support (mentorship) Sales and Marketing 4 4 6 16 6 4 6 4 A A B D D.E G F

Oh no! Our experts couldn't answer your question.

Don't worry! We won't leave you hanging. Plus, we're giving you back one question for the inconvenience.

Submit your question and receive a step-by-step explanation from our experts in as fast as 30 minutes.
You have no more questions left.
Message from our expert:
Our experts are unable to provide you with a solution at this time. Try rewording your question, and make sure to submit one question at a time. We've credited a question to your account.
Your Question:
Need a CPM for it “I attached summary picture for CPM information”
Use a graphical approach such as Critical Path
Method (CPM)
■ Captures the activities and their inter-
relationships using a graph (network of
precedence relationships)
Code
■
Data take-of
■ Lines are used to represent the activities
■ Nodes are used to represent the start and stop
of activities
USED IN: the jobs repetitive in nature where the activity time estimates can be
predicted with considerable certainty due to the existence of past experience.
Adding time dimension
. The forward pass
■ calculate the earliest start dates of the
activities
Earliest start
date
■ To calculate the project completion date
. The backward pass
calculate the latest start dates for activities
identify the critical path from the graph
1
Program test
3
6
7
Event Number
Latest start
date
Slack
(a measure on how late an event
may be without affecting the end
date of the project)
Transcribed Image Text:Use a graphical approach such as Critical Path Method (CPM) ■ Captures the activities and their inter- relationships using a graph (network of precedence relationships) Code ■ Data take-of ■ Lines are used to represent the activities ■ Nodes are used to represent the start and stop of activities USED IN: the jobs repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience. Adding time dimension . The forward pass ■ calculate the earliest start dates of the activities Earliest start date ■ To calculate the project completion date . The backward pass calculate the latest start dates for activities identify the critical path from the graph 1 Program test 3 6 7 Event Number Latest start date Slack (a measure on how late an event may be without affecting the end date of the project)
+
Id
A
B
C
D
E
F
G
H
I
Activity Name
Design the project 4
framework
Contract with
sponsors and
partners
Identify and
contract with
startup businesses
and collaborators
Acquiring a
location
Designing and
maintaining the
shipping
containers
Acquiring
materials and the
required
infrastructure
Review
application of
startups that focus
on providing good
services
Providing
incubation
Duration(Weeks) Precedents
support
(mentorship)
Sales and
Marketing
4
4
6
16
6
4
6
4
A
A
B
D
D.E
G
F
Transcribed Image Text:+ Id A B C D E F G H I Activity Name Design the project 4 framework Contract with sponsors and partners Identify and contract with startup businesses and collaborators Acquiring a location Designing and maintaining the shipping containers Acquiring materials and the required infrastructure Review application of startups that focus on providing good services Providing incubation Duration(Weeks) Precedents support (mentorship) Sales and Marketing 4 4 6 16 6 4 6 4 A A B D D.E G F
Recommended textbooks for you
Computer Networking: A Top-Down Approach (7th Edi…
Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON
Computer Organization and Design MIPS Edition, Fi…
Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science
Network+ Guide to Networks (MindTap Course List)
Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning
Concepts of Database Management
Concepts of Database Management
Computer Engineering
ISBN:
9781337093422
Author:
Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:
Cengage Learning
Prelude to Programming
Prelude to Programming
Computer Engineering
ISBN:
9780133750423
Author:
VENIT, Stewart
Publisher:
Pearson Education
Sc Business Data Communications and Networking, T…
Sc Business Data Communications and Networking, T…
Computer Engineering
ISBN:
9781119368830
Author:
FITZGERALD
Publisher:
WILEY