WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000 45000 2.04 Communications 30000 30000 30000 2.05 Tech. Manuals 42000 42000 48000 2.06 Spares 40000 35000 42000 2.07 Training 80000 80000 86000 Project Total 342000 316000 324000 Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX) Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX? Select one: a. The project is $26,000 under budget. b. The project is $8,000 over budget. c. The project is $18,000 over budget. d. The project is on budget.
WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000 45000 2.04 Communications 30000 30000 30000 2.05 Tech. Manuals 42000 42000 48000 2.06 Spares 40000 35000 42000 2.07 Training 80000 80000 86000 Project Total 342000 316000 324000 Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX) Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX? Select one: a. The project is $26,000 under budget. b. The project is $8,000 over budget. c. The project is $18,000 over budget. d. The project is on budget.
Pkg Acc Infor Systems MS VISIO CD
10th Edition
ISBN:9781133935940
Author:Ulric J. Gelinas
Publisher:Ulric J. Gelinas
Chapter15: Integrated Production Processes (ipps)
Section: Chapter Questions
Problem 1SP
Related questions
Question
WBS Element
|
Planned Value
(PV) |
Earned Value
(EV) |
Actual Cost
(AC) |
2.01 Airframe |
48000
|
48000
|
50000
|
2.02 Engines |
22000
|
21000
|
23000
|
2.03 Avionics |
80000
|
60000
|
45000
|
2.04 Communications |
30000
|
30000
|
30000
|
2.05 Tech. Manuals |
42000
|
42000
|
48000
|
2.06 Spares |
40000
|
35000
|
42000
|
2.07 Training |
80000
|
80000
|
86000
|
Project Total |
342000
|
316000
|
324000
|
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report
(October 31, 20XX)
(October 31, 20XX)
Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX?
Select one:
a. The project is $26,000 under budget.
b. The project is $8,000 over budget.
c. The project is $18,000 over budget.
d. The project is on budget.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Recommended textbooks for you
Pkg Acc Infor Systems MS VISIO CD
Finance
ISBN:
9781133935940
Author:
Ulric J. Gelinas
Publisher:
CENGAGE L
Accounting Information Systems
Finance
ISBN:
9781337552127
Author:
Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:
Cengage Learning
Pkg Acc Infor Systems MS VISIO CD
Finance
ISBN:
9781133935940
Author:
Ulric J. Gelinas
Publisher:
CENGAGE L
Accounting Information Systems
Finance
ISBN:
9781337552127
Author:
Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:
Cengage Learning