XOX Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order Wait time 15.6 Inspection time 0.8 Process time 1.6 Move time 0.7 Queue time 3.9 Compute the delivery cycle time in days. Percentage of manufacturing cycle time spent on non-value-added activities.
Q: A hospital emergency room (ER) Is currently organized so thất all patients register through an…
A: Here now we assume a stable system. IT shows that average inflows equal average outflow at every…
Q: The following data pertain to operations at Quick Incorporated: Throughput time…
A: Throughput time is the total time taken to produce the product in the manufacturing process of…
Q: Help ! Choice Bank receives credit card applications that need to be reviewed for a decision.…
A: Utilization is the work done in a given specified time, that is how much did the employee utilize…
Q: Judy’s Cake Shop makes fresh cakes to customer orders. After receiving the order by Judy’s…
A: a) Process capacity is the possible output of the production line. We can identify the process…
Q: The Holt Million Corporation’s plant manufactures two different products: X and Y. The plant has…
A:
Q: Calculate the total number of machine-hours
A: Total machine hour is calculated as below:
Q: Apples are prepared in a process with two resources. The first resource has a capacity of 2.1 apples…
A: The concept used here is cycle times and bottleneck resource identification.
Q: 1000 workers are currently working in Sigma Manufacturing Industry. This industry is paying the…
A: Below is the solution:-
Q: A 30,000-seat college football stadium is used 20 times for games, concerts, and graduation…
A: Utilization explains to us how well a particular resource is used and is utilized to its maximum…
Q: Clients are served in a process with two resources. The first resource has a capacity of 14 clients…
A: Given data: Capacity for the first resource = 14 client/hour Capacity for the second resource = 15…
Q: CodeDeskInc matches programmers with freelance jobs. It has 30 employees who staffits online chat…
A: Active chat sessions=Average request per hour×Chat session timeMinutes per hour=240×560=20
Q: Which of the following product flow types are characterized by high skill level? Continuous O Job…
A: Job shop uses general-purpose equipment and depends on the knowledge and skill of the workers. So,…
Q: Given this set of daily service operation, assuming a processing order of A-B-C-D-E; Determined the…
A: If four cycles are used, then the inventory size of the operation can be minimized and be more…
Q: Claims received by Healthwise Insurance Company are en-tered into the database at one station, and…
A: Solution Applying Johnsons rule, we get - Johnson's rule is: Pick the one with the shortest…
Q: The boss at the Precision Machine Shop needs to de-finish the personnel policy,which minimises all…
A: Given that: For junior attendant: λ = 8 μ = 10 For junior attendant: λ = 8 μ = 16
Q: It is election day and 1800 voters vote in their precinct’s library during the 10 hours thepolls are…
A: Inventory or stock is the products and materials that a business holds for a definitive objective of…
Q: CodeDesk Inc matches programmers with freelance jobs. They have 34 employees who staff their online…
A: Given data Flow rate = 235 chats per hour =23560=3.92 request per minutes Flow time = 3 minutes…
Q: A Printed Circuit Board (PCB) machine installs integrated circuits onto a board. Before starting to…
A: Given: Setup time = 16min Processing time = 0.19min/board
Q: Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken,…
A: Following formula can be used to calculate implied utilization rate: Firstly, the workload needs to…
Q: In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 16.65…
A: Given, Flow time in minutes = 16.65 hours * 60 minutes = 999 minutes Value added time = 1 minute +…
Q: The Holt Million Corporation’s plant manufactures two different products: X and Y. The plant has…
A:
Q: Kitty Wonderland (KW) makes toys for cats. KW’s managers have recently learned that they can…
A: Solution of the above problem is as follows:
Q: The site is scheduled to run from 8:00 am to 5:00 pm and has 9,000 citations today. You can start…
A: given, scheduled run = 8.00am to 5.00 pm citation = 9000 arriving rate = 1250 per hour
Q: Digos Mineral Inc. is in water refilling. The following information pertains to its operations…
A: Given data is Processing time = 40 minutes Inspection time = 7.5 minutes Waiting time = 7.5 minutes…
Q: Mack’s guitar fabrication shop produces low-cost, highly durable guitars for beginners. Typically,…
A:
Q: Which service process structure typically involves work flows with steps that vary from one customer…
A: Service process structure is a type of structure that determines how inputs and output of a process…
Q: Rajesh, a Junior System Administrator with the MIS department, clocked in 4 minutes and 27 seconds…
A: Business ethics describes the morals and principles an organization approved in its whole…
Q: Recall "Tommy's Dresses to go" case. Three years after, this company still rents designer dresses to…
A: Tenants request residences for periods ranging from one month to a year, and in some cases even…
Q: Why is it important to view a batch-process operation as a network of interconnected queues?
A: Batch process operation is a type of operation in which a fixed no. inputs are loaded into the…
Q: Loans are evaluated in a process with two resources. The first resource has a capacity of 30 loans…
A: Given, First resource capacity = 30 loans / hour Second resource capacity = 38 loans / hour Demand =…
Q: Suppose Panini employs 1 worker at each step. a) Does Panini have enough capacity to fulfill the…
A: Given Details Grilled Vegetables Grilled Chicken Pastrami Demand per hour 25 9 12 Step…
Q: Work-in-process inventories are raw materials and supplies waiting to be processed.; True or False
A: Manufacturing is the process of conversion of raw materials into final goods after carrying out…
Q: Given this set of daily service operations, and assuming a processing order of A-B-C-D-E:a. Give one…
A: a. If four cycles are used, the inventory size can be minimized and it will be more flexible. If two…
Q: Dell uses a strategy by aiming to shrink the time needed to fill orders of their computers and…
A: Processing time is the time when the products are manufactured, packed and filled in containers and…
Q: 30,000-seat college football stadium is used 18 times for games, concerts, and graduation…
A: It is given that the stadium has been used 18 times. So, the Resource used = 18 times
Q: Which of the following inefficiencies in a grocery store’s operations results frominflexibility?a.…
A: Generally stores operate from 7am to 10 pm or 8am to 10 pm. and there is no flexibility in work…
Q: Cycle-Time Analysis Variability is often considered to be the enemy of efficient and effective…
A:
Q: In a one-page paper, list the advantages and disadvantages of using part-time employees to help meet…
A: There is nothing more exciting than a small business that is growing faster than you can keep up…
Q: A veterinary office with three processes (examination, greeting, and checkout) has two types of…
A: Below is the solution:-
Q: Which among the following is a feature of a Manufacturing Enterprise a. Less Infrastructure…
A: Here, Question has asked about the feature of a Manufacturing Enterprise, every manufacturing…
Q: WIP is an abbreviation for O a. work-in-process O b. waiting inventory potential Oc waiting…
A: An abbreviation refers to the short form of a word/phrase/saying that is shortened to make an…
Q: The product–process matrix is a convenient way of characterizing the relationship between product…
A: It is a tool to analyze the fit between a chosen product positioning and fabricating measure. The…
Q: Define Process Flow Time Reduction with example?
A: Flow-Time Reduction is getting each product, job, and process project completed sooner and faster in…
Q: A work system has five stages with processing times of of 6, 4, 2, 8, and 10 mins/unit. A product…
A: Given- A work system has five stages - Processing times for stages are 6, 4, 2, 8, and 10 mins/unit
Q: In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 14.35…
A:
Q: Sherwood Store is a retail grocery store chain with a central distribution center and 14 retail…
A: Management Informations Systems are the tools and techniques deployed to efficiently running and…
Q: What is the total idle time of the process assuming unlimited demand?
A: Idle time is the time measured minus the total process time by the total cycle time.
Q: Required: Which segment is more efficient in terms of manufacturing efficiency? How can management…
A: Throughput time is the total time incurred in the production process to manufacture a product.
XOX Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order
Wait time 15.6
Inspection time 0.8
Process time 1.6
Move time 0.7
Queue time 3.9
- Compute the delivery cycle time in days.
-
Percentage of manufacturing cycle time spent on non-value-added activities.
Step by step
Solved in 2 steps
- XYZ is famous for homemade pizzas which are crisp with thin crust and varied toppings giving the pizzas fabulous tastes. XYZ· is revamping its order processing and pizza-making process. In order to deliver fresh pizza fast, six work elements must be completed as shown in the table below :Element Description Precedence Time (in min)A Receive order - 2·0B Shape dough A 1·0C Prepare toppings A 2·0D Assemble pizza B, C 3·0E Bake pizza D 3·0F Deliver pizza E 3·0Construct a precedence diagram for the process.If the demand is 120 pizzas per night (5:00pm to 1:00am), compute the cycle time for the process. Compute the lead time for the process.What is the theoretical minimum number of workstations needed to achieve the required production?How will you balance the production line to produce and deliver 120 pizzas per night? What is the actual minimum number of workstations needed?SpikLock makes several lines of metal items. The most recent order has been for 1200 door lock units for an apartment complex developer. The sales and production departments must work together to determine delivery schedules. Each lock unit consists of three components: the knob and faceplate, the actual lock itself, and a set of two keys. Although the processes used in the manufacture of the three components vary, there are three areas where the production manager is concerned about the availability of resources. These three areas, their usage by the three components, and their availability are detailed in the table. Resource Knob and Plate Lock Key (each) Available Brass Alloy 12 5 1 15000 units Machining 18 20 10 36000 minutes Finishing 15 5 1 12000 minutes A quick look at the amounts available confirms that SpikLock does not have the resources to fill this contract. A subcontractor, who can make an unlimited number of each…Up, Up, and Away is a producer of kites and wind socks.Relevant data on a bottleneck operation in the shop for theupcoming fiscal year are given in the following table:Item Kites Wind SocksDemand forecast 30,000 units/year 12,000 units/yearLot size 20 units 70 unitsStandard processing time 0.3 hour/unit 1.0 hour/unitStandard setup time 3.0 hours/lot 4.0 hours/lotThe shop works two shifts per day, 8 hours per shift, 200 daysper year. Currently, the company operates four machines,and desires a 25 percent capacity cushion. How many ma-chines should be purchased to meet the upcoming year’s de-mand without resorting to any short-term capacity solutions?
- A furniture factory makes two types of wooden tables,large and small. See the flowchart below.SetupTime,MinutesRun Timeper Piece,MinutesCapacity,Piecesper HourWood cutting 30 5 15Make four legs 60 10 10Make tops 60 12 8Finish the wood 20 8 12Assemble and ship 20 17 14 Small tables are made in batches of 100, and large tables are made in batches of 50. A batch includes a fixed setup time for the entire batch at each process step and a run time for each piece in the batch. Both large and small tables have the same processing times. The capacities of each process step are given, and apply to production of either type of table, as shown in the flowchart.a. What is the capacity of the system, and what is the bottleneck?b. What are the throughput times for batches of large and small tables?c. When producing at a rate of six small tables per hour on average, how many tables will be in the system?XYZ Company is a multinational company which exports ladies dresses to European countries. For the month of January, the total ordered quantity amounts to 14,400 pieces and lead time of 5 days is given to the company to finish the goods. Based on the time study conducted by the Senior Industrial Engineer, the standard time for this particular style of ladies dress is 5.0 mins/piece. Being an Industrial Engineer of the same plant, you were given the task to provide your superior of the following information given the additional data below: Salary per person = 400.00/day Working time = 7.5 hours/day Material Cost = 10,000.00 Miscellaneous Cost = 5,000.00 REQUIRED: Compute for the Production Cost 2. GIVEN: WARRANTY COST = P 30,000.00 DEVELOPMENT COST = 40,000.00 PRODUCTION COST = 60,000.00 COMPUTE FOR TOTAL COSTTailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwindshoe, which sells for $210, contains both gas- and liquid-filled compartments to provide morestability and better protection against knee, foot, and back injuries. Manufacturing the shoesrequires 10 separate tasks. There are 400 minutes available for manufacturing the shoes inthe plant each day. Daily demand is 60. The information for the tasks is as follows: Task Performance Time (In minutes) Task Must Follow This task A 1 ___ B 3 A C 2 B D 4 B E 1 C.D F 3 A G 2 F H 5 G I 1 E,H J 3/25 I 1. What is the theoretical minimum number of work stations required to satisfy this output rate? 2. Allocate the tasks to work stations taking into consideration the precedence requirements and usingthe LOT rule to break ties between feasible tasks.
- Using a flowchart, prepare the high-level process of the following:1. Procure to Pay2. Order to Cash3. Record to ReportDell uses a time-based strategy with the aim of reducing the delivery time needed to fill orders of computers this is an example of manufacturing time reduction : True or False?Please dont answer in image ormat,Do type. Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day, or…
- Discuss each statement given below whether its true or false and explain briefly (a) If cycle time is increased number of workers should also be increased to respond to related change. (b) Manual operation time in part production capacity sheet includes both walking and manual processing times (c) There is no diffrence between part production capacity sheets and standard operations routine (d) If operations are simple then order of process and the operations routine are similar to each otherXYZ company provides labor and space for the manufacturing and assembly operations and stocking various inventory items for production such as wire, cables, some electronic components, etc. XYZ company orders a variety of components and raw materials by contract. The company recently hired 100 part-time employees working four to six-hour shifts. Skilled employees must do several raw material conversions for packaging—there are currently three (3) such employees. The plant layout is a typical process layout - machines of similar types are located together. Each machine and employee must be scheduled over the day and the standard time period for planning is one (1) hour. Material handling is mainly done manually, although the company would like to consider conveyors or other automation to aid in automating their processes. XYZ company forecasts planned production for two (2) years on a rolling quarterly basis. Often, the customer changes the forecast, and these changes can occur as…What does process planning entail? How would processplanning differ for batch and continuous processes