You are given the processing time (hour) in the following table:
Jobs
Machine A
Machine B
Machine C
1
3
3
2
8
4
8.
3
7
2
10
1
7
5
6.
i) Find out optimum sequence
ii) Find out total elapsed time
iii) Find out idle time for each machine