Question
Don’t solve in excel please . Question number (3).
A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks
to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01,2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B,
C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed.
Such that Task A does not need any predecessors; task B requires task A to be completed. To start task Cand task D, each
require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task Dand task E to be
completed. Finally, task G can start only once task Fis completed.Given we apply the most remaining tasks rule for balancing
the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation
are
О a. В. С, and D
O b. Donly
Oc. Eonly
O d. Dand F
O e. None is the correct answer
Transcribed Image Text:A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01,2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task Dand task E to be completed. Finally, task G can start only once task Fis completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation are О a. В. С, and D O b. Donly Oc. Eonly O d. Dand F O e. None is the correct answer
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Process strategy
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,