Two projects have an identical "Net Present Value' of $9,000. Are both projects equal in desirability?
Q: For the following projects, which project would you select, based on the Equivalent Uniform Amount…
A: Let CFn be the cashflow in year n. r = MARR = 15% Let's calculate NPV of both projects first.
Q: Consider two mutually exclusive projects – Project X and Project Y with identical initial outlays of…
A: Net present value (NPV):The net present value is a technique used for making the investment…
Q: McKnight Company is considering two different, mutually exclusive capital expenditure proposals.…
A: The NPV method is used for the feasibility analysis of a project. It incorporates the time value of…
Q: Assume a $200,000 investment and the following cash flows for two alternative capital projects: Year…
A: Pay Back period is that length of time in which the initial investment of project is recovered in…
Q: Your division is considering two projects. Its WACC is 10%, and the projects’ after-tax cash flows…
A: “Hi There, thanks for posting the question. But as per Q&A guidelines, we must answer the first…
Q: Tamarisk Company is considering two different, mutually exclusive capital expenditure proposals.…
A: Net Present Value :— It is the sum of all present value of future cash flows. NPV is used for…
Q: Use the following information for problems 1 to 5. Assume that the projects are mutually exclusive.…
A: Since you have posted a question with multiple sub-parts, we will solve first three subparts for…
Q: Consider two mutually exclusive projects – Project X and Project Y with identical initial outlays of…
A: Payback period of a project is the total time period in which the initial investment amount is…
Q: A company is considering two projects. The discount rate is 10 percent, and the projects’ cash flows…
A: Using NPV and IRR function in excel
Q: Central Energy is considering two mutually exclusive projects, Project Red and Project The projects…
A: To find the weighted average cost of capital at which both the projects would have the same net…
Q: Consider two mutually exclusive projects – Project X and Project Y with identical initial outlays of…
A: Capital budgeting means taking decisions related to investments. Capital investments involve the…
Q: HH Companies has identified two mutually exclusive projects. Project A has cash flows of −$40,000,…
A: Given, The project A and project B.
Q: A project has an estimated cost of $200,000 with an estimated revenue of $400,000. What is the BCR?
A: Benefit-cost ratio (BCR): It is a ratio that shows the relationship between the relative costs and…
Q: A company is considering two mutually exclusive projects. Both require an initial investment of…
A: The question is related to Capital Budgeting. Capital budgeting is the process by which a…
Q: Two mutually exclusive projects are under consideration. The cash flow diagrams below depict the…
A: We need to calculate Internal rate of return(IRR) of both projects. The decision criteria for…
Q: A company is considering two mutually exclusive projects. Both require an initial investment of…
A: Initial investment (I) = $10800 Project X life = 2 years Project Y life = 4 years Assuming…
Q: Consider two mutually exclusive projects – Project X and Project Y with identical initial outlays of…
A: Payback period is the required time to recovered the initial investment of the asset or a project…
Q: What is the IRR for a project that has a net investment of $14,600 and a single net cash flow of…
A: Working note:
Q: Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year…
A: Hello. Since your question has multiple sub-parts, we will solve the first three sub-parts for you.…
Q: Assume two mutually exclusive projects have the estimated net incremental after-tax cash flows shown…
A: NPV is the net current worth of cash flows that have occurred in the past or present. It is computed…
Q: Explain whether two competing, alternate capital projects are equally desireable if they both…
A: Net Present Value (NPV) which is determined with difference in the cash outflows PV (Present Value)…
Q: Central Energy is considering two mutually exclusive projects, Project Red and Project The projects…
A: At what weighted average cost of capital would the two projects have the same net present value can…
Q: Using the net present value method, the present value of cash inflows for Project A is P44,000 and…
A: Present value (PV) of cash inflows Divided:- Initial investment = Present value of index
Q: Carla Vista Company is considering two different, mutually exclusive capital expenditure proposals.…
A: Net present value = Present value of cash inflow-Present value of cash outflow Profitablity index =…
Q: Suppose Project A and Project B are mutually exclusive. Project A requires an initial cash outlay of…
A: Crossover rate is the cost of capital where two projects have the same net present values (NPV). We…
Q: Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year…
A: Given information: Project S: Cash outflow $10,000 Cash inflows $3,000 for 5 years Project L: Cash…
Q: Consider a project with inflows of $20,000 and outflows of $13,000. If the tax rate is 33%, and if…
A: Annual inflow (A) = $20000 Annual outflow (O) = $13000 Tax rate (T) = 33% Let D = Depreciation
Q: A company is considering two projects. The discount rate is 10 percent, and the projects' cash flows…
A: Using the NPV and IRR function in Excel
Q: What is the IRR for the following project if its initial after tax cost is $5,000,000 and it is…
A: Information Provided: Initial cash outflow = $5,000,000 Operatin Cash inflows Year 1 = $1,800,000…
Q: Project X and Y have the Following End of Year Cash Flows: Years 1 2. Project X -200 130 80 30…
A: Net Present Value (NPV) is a capital budgeting technique which uses a discount rate to bring all the…
Q: Consider two mutually exclusive projects – Project X and Project Y with identical initial outlays of…
A: To open the "IRR function" window - MS-Excel --> Formulas --> Financials --> IRR.
Q: Connor Corporation is considering two projects (see below). For your analysis, assume these projects…
A: An investment appraisal is a capital budgeting technique that helps to determine a capital project's…
Q: (a) Calculate the net present value for each project
A: Information Provided: Cost of capital = 15% Initial Outlay = RM 90,000 Project X free cash flow = RM…
Q: Three mutually exclusive projects, A, B, and C, each require $100,000, S62,500, and $75,000 initial…
A: Internal Rate of Return (IRR) of a project is the rate at which the present value of all the cash…
Q: Proposals L and K each cost $500,000, have 6-year lives, and have expected total cash flows of…
A: Payback period is the amount of period taken by original invesment to be recovered in terms of…
Q: You are considering two mutually exclusive projects with the following cash flows. Which project(s)…
A: YEAR PROJECT A PROJECT B 0 -$275,000 -$202,000 1 0 113,600 2 0 81,900 3 360,000 47,000
Q: Two projects being considered are mutually exclusive and have the following projected cash flows:…
A: Using the what if analysis function in excel
Q: Wildhorse Company is considering two different, mutually exclusive capital expenditure proposals.…
A: Net present value is the difference between the current worth of cash inflows and withdrawals over a…
Q: You are considering two mutually exclusive projects, A and B. Project A costs $90,000 and generates…
A: given, project A: cost = $90,000 annual cashflow = $15,000 years = 8 project B: cost =$100,000…
Q: Consider two mutually exclusive projects, A and B, whose costs and cash flows are shown in the…
A: Cross over rate is the rate at which NPV of two projects is equal or graphically, NPV of two…
Q: Project S has a cost of $9,000 and is expected to produce benefits (cash flows) of $2,700 per year…
A: NPV is the sum of present value of future cashflow less initial investment
Q: There are three potential projects . All with initial cost of 1,900,000. Which project should quark…
A: The NPV of the projects can be calculated as follows : Results obtained :
Q: A certain project with annual benefit of P 50,000 at the end of each year for a period of 6 years.…
A: Note: All the Given Options are wrong, so we are solving the correct one for you as per the figures…
Q: . What is the net present value $ of project A? 2. what is the profitability index for project A?…
A: Net Present Value: It represents a measure of the profitability of a project or investment in…
Two projects have an identical "
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects’ NPVs, IRRs, MIRRs, and PIs, assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?Project A has a required return of 9.2 percent and cash flows of -$87,000, $32,600, $35,900, and $43,400 for Years 0 to 3, respectively. Project B has a required return of 12.7 percent and cash flows of -$85,000, $14,700, $21,200, and $89,800 for Years 0 to 3, respectively. Which project(s) should you accept based on net present value if the projects are mutually exclusive? Select one: A. Accept either one, but not both B. Accept both projects C. Accept Project A and reject Project B D. Reject Project A and accept Project B E. Reject both projectsA company is considering two projects. The discount rate is 10 percent, and the projects’ cash flows would be: Years 0 1 2 3 Project A -$700 $500 $300 $100 Project B -$700 $100 $300 $600 Calculate the projects’ NPVs and IRRs. If the two projects are independent, which project(s) should be chosen? If the two projects are mutually exclusive, which project should be chosen?
- A company is considering two projects. The discount rate is 10 percent, and the projects’ cash flows would be: Years 0 1 2 3 Project A -$700 $500 $300 $100 Project B -$700 $100 $300 $600 Calculate the projects’ NPVs. If the two projects are independent, which project(s) should be chosen? If the two projects are mutually exclusive, which project should be chosen?Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects’ NPVs, IRRs, assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?Given the net present value (NPV) of Project A is -$500,000, Project B is $200,000 and Project C is $250,000. Which of the project(s) can be accepted?
- Using the net present value method, the present value of cash inflows for Project A is P44,000 and the present value of cash inflows of Project B is P24,000. If Project A and Project B require initial investments of P40,000 and P20,000, respectively, and have the same useful life, what is the project that should be accepted assuming the projects are mutually exclusive projects?Consider two mutually exclusive projects – Project X and Project Y with identical initial outlays of RM90,000 and depreciable lives of 5 years. Project X is expected to produce free cash flows of RM32,787 each year. Project Y is expected to generate a single after-tax net cash flow of RM223,880 in year 5. The cost of capital is 15 percent. Required:(a) Calculate the net present value for each projectConsider two mutually exclusive projects – Project X and Project Y with identical initial outlays of RM90,000 and depreciable lives of 5 years. Project X is expected to produce free cash flows of RM32,787 each year. Project Y is expected to generate a single after-tax net cash flow of RM223,880 in year 5. The cost of capital is 15 percent. Required:(a) Calculate the net present value for each project (b) Determine the internal rate of return for each project.(c) Compute the payback period for each project. (d) In a situation where there is capital rationing, calculate the profitability index (PI) for both projects and rank them accordingly. Based on your PI calculations above, identify the problems you foresee in selecting one of the projects. Select the best project based on Capital Budgeting Valuation Techniques above.
- Consider two mutually exclusive projects – Project X and Project Y with identical initial outlays of RM90,000 and depreciable lives of 5 years. Project X is expected to produce free cash flows of RM32,787 each year. Project Y is expected to generate a single after-tax net cash flow of RM223,880 in year 5. The cost of capital is 15 percent.Required:1) Determine the internal rate of return for each project.Explain whether two competing, alternate capital projects are equally desireable if they both generate a positive NPV of $2,000, when using the the Net Present Value method to evaluate the projects.A firm whose cost of capital is 10% is considering two mutually exclusive projects X and Y, the details of which are: Year Project X Project Y Cost X 70 000 Y 70 000 Cash inflows 1 10 000 50 000 2 20 000 40 000 3 30 000 20 000 4 45 000 10 000 5 60 000 10 000 Calculate the following: Net Present Value at 10% for both projects Profitability Index for both projects Internal Rate of Return of the two project