Work Study Is One of the Common Techniques That Can Be Used to Evaluate and Improve Productivity in Construction Operations. Describe the Two Major Branches of Work Study and How These Can Be Used to Improve Productivity.

Decent Essays

Work Study Definition: Work study can defined as the analysis of a task for the best optimal method and optimal time to perform. There for this method investigate two branches one is Method of work should carry out and the best timing to perform that task. So it focus on not only high production the efficiency of the production so called productivity. Influence of Work Study in Improving Productivity In order to recognize the function of work study, need to classify method study and that of time study. Method study is typically used to improve the method of performing work. It is applicable for new and existing task , method study focus to find more efficient and effective methods of doing the jobs that are cost-effective and safe, involve …show more content…

Step 3: Analysis of present method and develop alternatives. Using the expert and practices knowledge the root causes of delays are identified. The mitigation action are proposed to eliminate inefficiency of existing system. The new work study conduct and re arrange the working method as follows
 8 people divide in to two groups as excavation and shoring group and backfilling and road reinstatement group
 4 people in excavation group , one person helping to shoring work and keep alignment of trench, one people shaping the trench wall manually , two people are
Work Study
Method Study
Time Study
Provide improved planning and control for better use of Recourses
Providing standard time for task and incentive scheme for high production in given time frame
3
preparing the pipe and pipe bed. Excavator is continues excavation is carrying unlike before. The 4 men are selected by observing their skill and safe work behavior with machine and inside trench.
 Other 4 people work for backfilling, three people engage in material backfill , level, watering works and other person should handle the compactor. This person has good skill of handling machine and he understand maintain of equipment. Once a day he have to cut the asphalt trench also during the morning and evening.
 Excavation trench right with , compaction passes , control over exaction by simple calibrated stick, fixed tea breaks, provide free tea to site also