1. Applied Digital Solutions is expanding its operations to include a new product line for manufacturing bioelectronic computer chip. The project for manufacturing this computer chip has a high visibility. The following table lists the activities along with various probabilistic times and the dependencies: Times Activity Optimistic Most Likely Pessimistic Immediate Predecessor Activities A 2 3 4 В 6 7 9 13 20 1 3 4 5 1 E 10 11 12 1 F 4 4 G 11 13 15 4

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

*(e) Draw manually the appropriate network diagram (using PDM) and then find (and also provide as a table) for each of the activities by d: early start (ES), early finish (EF), late start (LS), late finish (LF) and total floats and total slacks and provide them in a table form.

Answer:

1. Applied Digital Solutions is expanding its operations to include a new product line for
manufacturing bioelectronic computer chip. The project for manufacturing this computer chip
has a high visibility. The following table lists the activities along with various probabilistic times
and the dependencies:
Times
Activity
Optimistic
Most Likely
Pessimistic
Immediate
Predecessor
Activities
А
2
3
4
В
6
7
8
C
13
20
1
3
4
1
E
10
11
12
1
F
4
8
4
G
11
13
15
4
H
5
7
4
3,6
2, 5, 8
7,9, 10
(Note that in the above table the predecessors are marked as A =1, B = 2, C = 3, D=4, etc.)
I
5
7
J
5
6
7
K
4
9.
Transcribed Image Text:1. Applied Digital Solutions is expanding its operations to include a new product line for manufacturing bioelectronic computer chip. The project for manufacturing this computer chip has a high visibility. The following table lists the activities along with various probabilistic times and the dependencies: Times Activity Optimistic Most Likely Pessimistic Immediate Predecessor Activities А 2 3 4 В 6 7 8 C 13 20 1 3 4 1 E 10 11 12 1 F 4 8 4 G 11 13 15 4 H 5 7 4 3,6 2, 5, 8 7,9, 10 (Note that in the above table the predecessors are marked as A =1, B = 2, C = 3, D=4, etc.) I 5 7 J 5 6 7 K 4 9.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.