18. Consider projects S and L. Both have normal cash flows and the projects have the same risk, hence both are evaluated with the same cost of capital, 10%. However, S has a higher IRR than L. Which of the following statements is CORRECT? A. If project S has a positive NPV, Project L must also have a positive NPV. B. If the cost of capital increases, each project's IRR will decrease. C. If the cost of capital fails, each project's IRR will increase. D. If Projects S and L have the same NPV at the current cost of capital, 10%, then Project L, the one with the lower IRR, would have a higher NPV if the cost of capital used to evaluate the projects decline.

Intermediate Financial Management (MindTap Course List)
13th Edition
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Eugene F. Brigham, Phillip R. Daves
Chapter12: Capital Budgeting: Decision Criteria
Section: Chapter Questions
Problem 13P
icon
Related questions
Question
18. Consider projects S and L. Both have normal cash flows and the projects
have the same risk, hence both are evaluated with the same cost of capital,
10%. However, S has a higher IRR than L. Which of the following statements is
CORRECT?
A. If project S has a positive NPV, Project L must also have a positive NPV.
B. If the cost of capital increases, each project's IRR will decrease.
C. If the cost of capital fails, each project's IRR will increase.
D. If Projects S and L have the same NPV at the current cost of capital,
10%, then Project L, the one with the lower IRR, would have a
higher NPV if the cost of capital used to evaluate the projects
decline.
Transcribed Image Text:18. Consider projects S and L. Both have normal cash flows and the projects have the same risk, hence both are evaluated with the same cost of capital, 10%. However, S has a higher IRR than L. Which of the following statements is CORRECT? A. If project S has a positive NPV, Project L must also have a positive NPV. B. If the cost of capital increases, each project's IRR will decrease. C. If the cost of capital fails, each project's IRR will increase. D. If Projects S and L have the same NPV at the current cost of capital, 10%, then Project L, the one with the lower IRR, would have a higher NPV if the cost of capital used to evaluate the projects decline.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Corporate Fin Focused Approach
Corporate Fin Focused Approach
Finance
ISBN:
9781285660516
Author:
EHRHARDT
Publisher:
Cengage