29' 9" ation. 34' 0" Bucket Wall Plan Excavator Information 2.3 ft³ Ift=12in 27ft = lyd Continuous concrete footing 1'9 36 Section of wall plan

Construction Materials, Methods and Techniques (MindTap Course List)
4th Edition
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:William P. Spence, Eva Kultermann
Chapter25: Bonding Agents, Sealers, And Sealants
Section: Chapter Questions
Problem 12RQ
icon
Related questions
Question
Give correct answer and show all steps. Subject is construction engineering
Given the wall plan and wall section drawings and a mini excavator specifications, estimate hours required for
footing excavation.
11"
29' 9"
34' 0"
Wall Plan
Excavator Information
Bucket
Cycle of Operation
Efficiency
2.3 ft3
40 second per cycle
40 mins per hour
73
Ift=12in
27ft = lyd
Continuous concrete
footing
26
1'9
36
Section of wall plan
Transcribed Image Text:Given the wall plan and wall section drawings and a mini excavator specifications, estimate hours required for footing excavation. 11" 29' 9" 34' 0" Wall Plan Excavator Information Bucket Cycle of Operation Efficiency 2.3 ft3 40 second per cycle 40 mins per hour 73 Ift=12in 27ft = lyd Continuous concrete footing 26 1'9 36 Section of wall plan
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Historic projects
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning