5. In connection with surfacing a new highway, a contractor has a choice of two sites on which to set up the mixing plant equipment. The contractor estimates that it will cost P51.75 per cubic meter per kilometer to haul the asphalt paving material from the mixing plant to the job site. If site B is selected, there will be an added charge of P600 per day for a flagman and it needs 2 flagman. The job requires 50,000 cubic meters of mixed asphalt paving material. It is estimated that four months (17 weeks of five working days per week) will be required for the job Cost Factors Site A Site B 4.3 km Average hauling distance 6 km Monthly rental of site P45,000 P225,000 Cost to setup and remove equipment P675,000 Hauling expense P51.75 / Cu.m/km P1,125,000 P51.75 / Cu.m/km

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter9: Capital Budgeting And Cash Flow Analysis
Section: Chapter Questions
Problem 4P
icon
Related questions
Question

a) Compare the two sites in terms of their fixed, variable, and total costs.

Fixed Costs
Monthly rental of site
Cost to setup and remove
equipment
Flagman wage
Total Fixed Costs
Variable Costs
Hauling expense
Total Costs
Fixed + Variable
What site is better?
(solution to a)
Site A
Site A
Site A
Site B
Site B
Site B
Transcribed Image Text:Fixed Costs Monthly rental of site Cost to setup and remove equipment Flagman wage Total Fixed Costs Variable Costs Hauling expense Total Costs Fixed + Variable What site is better? (solution to a) Site A Site A Site A Site B Site B Site B
5. In connection with surfacing a new highway, a
contractor has a choice of two sites on which to
set up the mixing plant equipment.
The contractor estimates that it will cost P51.75
per cubic meter per kilometer to haul the asphalt
paving material from the mixing plant to the job
site.
If site B is selected, there will be an added
charge of P600 per day for a flagman and it needs 2 flagman.
The job requires 50,000 cubic meters of mixed
asphalt paving material. It is estimated that four
months (17 weeks of five working days per
week) will be required for the job
Cost Factors
Site A
Site B
4.3 km
Average hauling distance
6 km
Monthly rental of site
P45,000
P225,000
Cost to setup and
remove equipment
P675,000
Hauling expense
P51.75/Cu.m/km
P1,125,000
P51.75 / Cu.m/km
Transcribed Image Text:5. In connection with surfacing a new highway, a contractor has a choice of two sites on which to set up the mixing plant equipment. The contractor estimates that it will cost P51.75 per cubic meter per kilometer to haul the asphalt paving material from the mixing plant to the job site. If site B is selected, there will be an added charge of P600 per day for a flagman and it needs 2 flagman. The job requires 50,000 cubic meters of mixed asphalt paving material. It is estimated that four months (17 weeks of five working days per week) will be required for the job Cost Factors Site A Site B 4.3 km Average hauling distance 6 km Monthly rental of site P45,000 P225,000 Cost to setup and remove equipment P675,000 Hauling expense P51.75/Cu.m/km P1,125,000 P51.75 / Cu.m/km
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Cost classification
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning