A Canadian firm is evaluating an investment in Indonesia. The project costs 580 billion Indonesian rupiah and it is expected to produce an income of 280 billion Indonesian rupiah a year in real terms for each of the next 3 years. The expected inflation rate in Indonesia is 11% per year and the firm estimates that an appropriate discount rate for the project would be about 5% above the risk-free rate of interest. Calculate the net present value of the project in dollars Assume a spot exchange rate of $.000112/Rupiah. The interest rate is about 15% in Indonesia and 4% in Canada (Round your enswer to 2 decimal pleces. Enter your answer in millions of Canedian dollors.) NPV of the project willion

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter11: Capital Budgeting And Risk
Section: Chapter Questions
Problem 20P
icon
Related questions
icon
Concept explainers
Question
A Canadian firm is evaluating an investment in Indonesia. The project costs 580 billion Indonesian rupiah and it is expected to produce
an income of 280 billion Indonesian ruplah a year in real terms for each of the next 3 years. The expected inflation rate in Indonesia is
11% per year and the firm estimates that an appropriate discount rate for the project would be about 5% above the risk-free rate of
interest. Calculate the net present value of the project in dollars. Assume a spot exchange rate of $.000112/Rupiah. The interest rate is
about 15% in Indonesia and 4% in Canada (Round your answer to 2 decimal places. Enter your answer in millions of Canadian
dollers.)
NPV of the project
Transcribed Image Text:A Canadian firm is evaluating an investment in Indonesia. The project costs 580 billion Indonesian rupiah and it is expected to produce an income of 280 billion Indonesian ruplah a year in real terms for each of the next 3 years. The expected inflation rate in Indonesia is 11% per year and the firm estimates that an appropriate discount rate for the project would be about 5% above the risk-free rate of interest. Calculate the net present value of the project in dollars. Assume a spot exchange rate of $.000112/Rupiah. The interest rate is about 15% in Indonesia and 4% in Canada (Round your answer to 2 decimal places. Enter your answer in millions of Canadian dollers.) NPV of the project
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Cost of Capital
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
International Financial Management
International Financial Management
Finance
ISBN:
9780357130698
Author:
Madura
Publisher:
Cengage