Question
Building materials
A crew consisting of two carpenters and one
helper can fix 10 m² of a slab form work in 8
hours and the hourly labour rate of a carpenter
is Rs. 85 and for a helper is Rs. 69.50. An
average hourly rate per worker of the crew will
be nearly
Transcribed Image Text:A crew consisting of two carpenters and one helper can fix 10 m² of a slab form work in 8 hours and the hourly labour rate of a carpenter is Rs. 85 and for a helper is Rs. 69.50. An average hourly rate per worker of the crew will be nearly
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Pricing subcontractor's work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,