A flooring subcontractor must install three types of flooring in an existing building. The subcontractor is given 10 days to finish all the work. Assume he has crews to start all three jobs concurrently. Four days after the start of the work, he discovers the following: Туре Quantity (m3 Unit Price Total Price Installed (m) Actual Cost Carpet 2600 2.30 5980 1600 3150 Vinyl tile 1200 2.95 3540 800 2488 Ceramic tile 3330 4.95 16484 750 3638 Total 7130 26004 What is the Cost Performance Index (CPI) value for Ceramic tile Select one: О а.0.38 O b. 1.67 O c. 1.54 O d. 0.56

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter4: Mechanical Processes
Section: Chapter Questions
Problem 4.12P
icon
Related questions
Question
Find the two question,Thanx.
A flooring subcontractor must install three types of flooring in an existing building. The subcontractor is given 10 days to finish
all the work. Assume he has crews to start all three jobs concurrently. Four days after the start of the work, he discovers the
following:
Туре
Quantity
(m)
Unit Price
Total Price Installed (m)
Actual Cost
Carpet
2600
2.30
5980
1600
3150
Vinyl tile
1200
2.95
3540
800
2488
Ceramic tile
3330
4.95
16484
750
3638
Total
7130
26004
What is the Cost Performance Index (CPI) value for Ceramic tile
Select one:
О а. 0.38
O b. 1.67
O C. 1.54
Od. 0.56
1242 AM
ENG
Transcribed Image Text:A flooring subcontractor must install three types of flooring in an existing building. The subcontractor is given 10 days to finish all the work. Assume he has crews to start all three jobs concurrently. Four days after the start of the work, he discovers the following: Туре Quantity (m) Unit Price Total Price Installed (m) Actual Cost Carpet 2600 2.30 5980 1600 3150 Vinyl tile 1200 2.95 3540 800 2488 Ceramic tile 3330 4.95 16484 750 3638 Total 7130 26004 What is the Cost Performance Index (CPI) value for Ceramic tile Select one: О а. 0.38 O b. 1.67 O C. 1.54 Od. 0.56 1242 AM ENG
If TF of terminal activity is 5 days then TF of activities on critical path is
Select one:
a. none
O b. 3 days
C. zero day
d. 5 days
Transcribed Image Text:If TF of terminal activity is 5 days then TF of activities on critical path is Select one: a. none O b. 3 days C. zero day d. 5 days
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Alloys
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,