A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?
Q: Old Pueblo Engineering Contractors creates six-month “rolling” schedules, which are recomputed…
A:
Q: Kofi Abebrese runs a small industrial company that specialize in the production of high standard…
A: The cost-benefit analysis of the two options are given below: The variable overheads include the…
Q: Calculate the average time required to produce one piece per hour if there are five machines with…
A: Given data is Number of machines = 5 Machining time per piece = 0.6 hours Servicing time per piece =…
Q: A single model manual assembly line produces a product whose work content time = 47.8 min. The line…
A: Efficiency is the ability to reduce the wastage of resources, materials, and money in the production…
Q: The company must produce 2000 units of A weekly. The company can purchase up to 1 ton of the raw…
A: A Small Introduction about LPP The linear approach is a technique for selecting the best solution…
Q: Georgia Cabinets manufactures kitchen cabinets that are sold to local dealers throughout the…
A: Given Information: Cabinet Maker 1 Cabinet Maker 2 Cabinet Maker 3 Hours required to…
Q: Compute the takt time for a system where the total time per shift is 480 minutes, there is one…
A: Takt time is described as the time or the rate at which products are needed to be manufactured in…
Q: Apples are prepared in a process with two resources. The first resource has a capacity of 2.1 apples…
A: The concept used here is cycle times and bottleneck resource identification.
Q: The Academic Computer Center has five trainers available in its computer labs to provide training…
A: Operational efficiency is described as the organizational ability to focus on the reduction of…
Q: A restaurant has a maximum capacity to serve 60 customers at any given point of time. However, over…
A: Given- Restaurant Max capacity = 60 customers Output (Customer Serving) = 70 customers
Q: A company makes two products X and Y, using a single resource pool. The resource is available for 8…
A: Availability of resources for production of X and Y = 8 hrs. (480 minutes) Unit load of X = 15…
Q: A product line manufacturing shoes has five stations in series whose individual capacities per shift…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: What cycle time would match capacity and demand if demand is 120 units a day, there are twoshifts of…
A:
Q: Yost-Perry Industries (YPI) manufactures a mix of affordable guitars (A, B, C) that are fabricated…
A: Given Product A demand is 60 units per week Product B demand is 80 units per week Product C demand…
Q: A. If three machines are assigned to an operator, what will be the cost per unit produced? B. If…
A: A) With the help of the data given the following points can be ascertained: Total time of work per…
Q: A production system is as shown below. Station 1 could produce 60 per hour if the rest of the line…
A: The following information is given: The system runs at a rate of 45 per hour (actual output)…
Q: The school cafeteria can make pizza for approximately$0.30 a slice. The cost of kitchen use and…
A: Formula:
Q: The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at…
A: A capacity of a system indicating the total expected output if the stations runs the available time…
Q: Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the…
A: Theoretical Capability = 253,000 units Theoretical Capability = 253,000 units Actual Production=…
Q: Compute the takt time for a system where the total time per shift is 420 minutes, there is one…
A: The answer is as below:
Q: Two machines A and B produce items at the rate of 50 units per hour and 40 units per hour…
A: The answer is as below:
Q: The manager of a car wash must decide whether to have one or two wash lines. One line will mean a…
A: Particulars One line Two lines Fixed cost per month 6000 11000…
Q: Given the following information, compute the takt time: Total time per shift is 480 minutes per day,…
A: Takt Time = Net time available per day/ Daily demand Daily demand = 80
Q: Consider a production line with five stations. Station 1 can produce a unit in 9 minutes. Station 2…
A: Given data is
Q: A newly opened bed-and-breakfast projects the following: Monthly fixed costs Variable cost per…
A: Break-even analysis helps in determining the minimum levels of sales which is required to cover the…
Q: Mack’s guitar fabrication shop produces low cost, highly durable guitars for beginners. Typically,…
A: Multifactor productivity (MFP), otherwise called complete factor productivity (TFP), is a proportion…
Q: The manager of a car wash must decide whether to have one or two wash lines. One line will mean a…
A:
Q: A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit…
A: Given Number of machines = 2 Production capacity of machine = 4 units/hour.
Q: If the firm operates 10 hours per day, 5 days per week, what is the weekly capacity of this work…
A: Weekly available time = 600 Minutes (10 hours) * 5 days = 3000…
Q: The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at…
A: The bottleneck is a term used in manufacturing industries where it often happens that a particular…
Q: c) If the firm operates 8 hours per day, 6 days per week, the weekly capacity of the work cell with…
A: Capacity is the ability to manufacture maximum output from the available resources and materials.
Q: The manager of a car wash must decide whether to have one or two wash lines. One line will mean a…
A:
Q: 30,000-seat college football stadium is used 18 times for games, concerts, and graduation…
A: It is given that the stadium has been used 18 times. So, the Resource used = 18 times
Q: Compute the takt time for a system where the total time per shift is 480 minutes, there is one…
A: Formula:
Q: RideShare offers short-term rentals of vehicles that are kept in small lots in urbanneighborhoods…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: A plant runs in two shifts, one shift of 8 hours and during each shift there is 2 hours of planned…
A: efficiency is the ratio of output to the input
Q: Purple Swift manufactures birdhouses in lots of 10. Eachbirdhouse takes 45 minutes to paint. After…
A: Utilization = Average Output Rate / Maximum Capacity Utilization = [(Number of lots x Setup Time) +…
Q: Alpha Taxi and Hauling also plans to have cabs at a new rail station. The expected arrivalrate is…
A: Formula:
Q: FOR THIS QUESTION, WOULD STORAGE TIME BE INCLUDED IN THE SUM FOR THROUGHPUT TIME? ALSO COULD YOU…
A: For the above question throughout put time is calculated as below:
Q: An airline company must plan its fleet capacity and itslong-term schedule of aircraft usage. For one…
A: The average number of customers per day = 70 Utilization rate = 65% The expected increase in demand…
Q: 7. Compute the takt time for a system where the total time per shift is 480 minutes, there is one…
A: Given data; Total time per shift 480 min No. of shifts 1 shift Rest break 30 min Lunch…
Q: A copy center in an office building prepares bound reports for two clients. The center makes…
A: Given information, Client X Annual Demand = 2000 Standard processing time = 0.5 Average lot size…
Q: T F For a food-processing plant such as Kraft Foods,capacity refers to the number of…
A: Capacity can be defined as the capability or the ability of the system that produce the output in a…
Q: A company operates 8 hours per shift, two shifts per day, five days a week with 12 hours maintenance…
A: Operating hour(h) = 8 Number of per day shift(s) = 2 Days per week (d) = 5 Maintenance hour(M) = 12…
Q: When a patient enters the Valley Health Clinical Laboratory to have his blood drawn and a Chemistry…
A: Given information:Number of techs (N) = 3Operating time per day (H) = 8 hours…
Q: At Susie's Dress Manufacturing, the company's garment production lines produces 600 dresses in a…
A: There is really a limit to how much can be produced in a given day and in industrial and…
Q: Apples are prepared in a process with two resources. The first resource has a capacity of 2.1 apples…
A: Process cycle time indicating the average time required to complete a unit of item. Here, we can…
A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- A business company has the following capacity per month based on the following: 30 working days per month; 1 shift operation at 8 hours per shift; 30 minutes break per shift per employee ABC company produces bicycles and has the following Capacities per process. Frame Welding: 60 bikes per hour per machine Painting: 20 bikes per hour per worker Assembly: 50 bikes per hour per worker Inspection: 100 bikes per hour per worker What can be observed from the system if the demand for the month is 5,000 bikes?A work center consists of 4 machines working 8 hours a day for a 5-day week. If theutilization is 80% and the efficiency is 90%, what is the rated capacity of the workcenter?Under ideal conditions, a picture frame manufacturing facility can produce 480 frames per day. Under normal conditions, the company schedules 434 frames per day. If the production manager sets the output rate to 382 frames per day, what is the resulting capacity cushion?
- The first station can process a unit in 10 minutes First Station capacity = 60/10 = 6 units per hour As the second station has 2 identical machines in parallel, each of which can process a unit in 12 minutes. Each unit needs to be processed on one of the two machines. Second Station Capacity = 60 x 2/12 = 10 units per hour The third station can process a unit in 8 minutes Third Station capacity = 60/8 = 7.5 units per hour What is the hourly capacity of this production line?A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit producedat the station needs to be processed by both of the machines.(The same unit cannot be worked on by both machines simultaneously.) Each machine has a production capacity of 4units per hour. What is the throughput time of the work cell?In order to produce 1000 units of X in a week? units X is scheduled weekly for Operation B (due to 5% scrap ratio)? units X is scheduled weekly for Operation A (due to 2% scrap ratio) Based on your answer in part a, find the number of machines required to produce 1000units of X per week.? The total time required to perform Operation B = ? minutes per week? The total time required to perform Operation A = ? minutes per weekH= Available Time in a week = minutes /weekThusFA = ?FB = ?Since both of the operations A and B are performed on the same machine? machines are required
- Georgetown Pizza makes favorite pan pizzas every day with three working shifts around the clock. The current completely cooked pizza making process has a fixed cost of $24,000, and a variable cost of $2.75 per pizza. The owner is considering a different process that can make pizzas in two ways: completely cooked and selling at $13.98 per unit, or partially cooked with a selling price of $12.98 per unit. This alternate process has a fixed cost of $28,000, but a lower variable cost (because much less energy is used in baking) of $2.25 per pizzac. If the owner expects to get $390,000 as a half year profit, how many units of completely cook pizzas, should Georgetown sell a year using the current pizza making process? d. Determine the annual design capacity for Georgetown’s production if the completely cook pizzas can be produced at 120 units per hour.A work cell at Chris Ellis Commercial Laundry hasa workstation with two machines, and each unit produced at thestation needs to be processed by both of the machines. (The sameunit cannot be worked on by both machines simultaneously.)Each machine has a production capacity of 4 un its per hour.What is the throughput time of the work cell?A copy center in an office building prepares bound reports for two clients. The center makes multiple copies (the lot size) of each report. The processing time to run, collate, and bind each copy depends on, among other factors, the number of pages. The center operates 250 days per year, with one 8-hour shift. Management believes that a capacity cushion of 15 percent (beyond the allowance built into time standards) is best. It currently has three copy machines. Based on the following table of information, determine how many machines are needed at the copy center. Item Client X Client Y Annual demand forecast (copies) 2,000 6,000 Standard processing time (hour/copy) 0.5 0.7 Average lot size (copies per report) 20 30 Standard setup time (hours) 0.25 0.40
- A restaurant has a maximum capacity to serve 60 customers at any given point of time. However, over extended periods in a day, all tables are occupied and the restaurant staff are able to reconfigure the layout to regularly serve 70 customers with many customers still queuing up to get inside the restaurant. What is the utilization of the restaurant?A single model manual assembly line produces a product whose work content time = 47.8 min. The line has 24 workstations with a manning level =1.25. Available shift time per day = 8 hr, but downtime during the shift reduces actual production time to 7.6 hr on average. This results in an average daily production of 256 units/day. Repositioning time per worker is 8% of cycle time. Determine (a) line efficiency, (b) balancing efficiency,and (c) repositioning time.Baby World Inc. has 31 operators and work 7 hours a day, 5 days a week. They specialize in making organic cotton baby onesies. The standard minute value to finish one onesie = 10 minutes. Assume that their actual capacity = max capacity. They just received an order for 6300 of these onesies. How many days will it take to complete this order? Round your answer to the nearest whole number, but do not round until your final answer. Group of answer choices 5 days 6 days 7 days 4 days