A planned municipality anticipates a waste collection rate of 60 tons per day, 5 days per week. municipality is trying to decide between a direct haul system and a transfer station operation and would like to know the break-even one-way haul distance (in miles, no decimal places). The city has determined that the use of a direct haul system would require four (4) additional collection vehicles than a transfer operation would need. The Collection Vehicle Information: Collection vehicle capacity = 5 tons Collection Vehicle cost = $125,000 Hauling cost = $32/hr Transfer Station Information: Trailer Size = 21 tons Trailer cost = $35,000 (use 2) Tractor cost = $80,000 (use 1) Facility cost ($/(ton/d of capacity) - based on 5 d/wk operation = $13,000 /(ton/day) Facility operation cost = $35,000/yr Hauling costs = $38/hr Average hauling speed = 35 mph Capital Recovery Factor, CRF (5%, 10 yrs) =0.13 %3D %3D

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 7RQ
icon
Related questions
Question

Using simple calculation method.

2. A planned municipality anticipates a waste collection
rate of 60 tons per day, 5 days per week.
municipality is trying to decide between a direct haul
system and a transfer station operation and would like to
know the break-even one-way haul distance (in miles, no
decimal places). The city has determined that the use of
a direct haul system would require four (4) additional
collection vehicles than a transfer operation would need.
The
Collection Vehicle Information:
Collection vehicle capacity = 5 tons
Collection Vehicle cost = $125,000
Hauling cost =
$32/hr
Transfer Station Information:
Trailer Size = 21 tons
Trailer cost = $35,000 (use 2)
Tractor cost = $80,000 (use 1)
Facility cost (S/(ton/d of capacity) - based on 5
d/wk operation = $13,000 /(ton/day)
Facility operation cost = $35,000/yr
Hauling costs = $38/hr
Average hauling speed = 35 mph
Capital Recovery Factor, CRF (5%, 10 yrs) =0.13
Transcribed Image Text:2. A planned municipality anticipates a waste collection rate of 60 tons per day, 5 days per week. municipality is trying to decide between a direct haul system and a transfer station operation and would like to know the break-even one-way haul distance (in miles, no decimal places). The city has determined that the use of a direct haul system would require four (4) additional collection vehicles than a transfer operation would need. The Collection Vehicle Information: Collection vehicle capacity = 5 tons Collection Vehicle cost = $125,000 Hauling cost = $32/hr Transfer Station Information: Trailer Size = 21 tons Trailer cost = $35,000 (use 2) Tractor cost = $80,000 (use 1) Facility cost (S/(ton/d of capacity) - based on 5 d/wk operation = $13,000 /(ton/day) Facility operation cost = $35,000/yr Hauling costs = $38/hr Average hauling speed = 35 mph Capital Recovery Factor, CRF (5%, 10 yrs) =0.13
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Alloys
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,