A plant is acquiring new production machinery. Before the machinery can be fully functional, a number of activities must be perfo
Q: 2) Explain 2 examples of the subsidiary legislation. |
A: The objective of this question is to provide two examples of subsidiary legislation. Subsidiary…
Q: Create a table including when during the employee's employment, each specific activity should occur,…
A: Human resource management is the aspect of management that is concerned with managing, supporting,…
Q: (a) the maximum possible profit. (b) the best combination of barrels of pruned and regular olives.…
A: This issue requires assessing the quantity of pruned olive barrels and conventional olive barrels to…
Q: What types of training and support do organizations provide to employees participating in job…
A: Job rotation programs have become increasingly popular in organizations as a strategic approach to…
Q: For a feasible mathematical programming problem, which of the following is always true (select all…
A: In this question we have to answer about the properties of feasible mathematical programming…
Q: Charles Lackey operates a bakery in Idaho Falls, Idaho. Because of its excellent product and…
A: The objective of the question is to calculate the percentage increase in productivity after…
Q: A project manager is faced with a situation where they have no tolerance for scope creep and have…
A: Option 1: With the deadline (Incorrect Answer)Explanation: Deadlines cannot be flexible when the…
Q: While Lewis Fabrication has decided to begin operations on a global scale, it realizes there is…
A: Business Expansion is about increasing the growth of business in the market It includes determining…
Q: An entrepreneur is planning to market a new brand of bottled unsweetened, organic iced tea. The…
A: Decision analysis is a structured approach to decision making Decision Making With Probabilities –…
Q: h ow is master production schedule created and how it is used ?
A: A key component of production planning in the industrial industry is the Master Production Schedule…
Q: Provide examples of make-to-stock, assemble-to-order, and make-to-order products. What advantages…
A: Production management is the aspect that deals with all the activities and functions of the…
Q: Actual demand for a product for the past three months was: Three months ago 400 units Two months…
A: Month Actual demand3 months ago4002 months ago350Last month325
Q: . Describe ways that cultural influences shape your morals and values 2. Explain how cultural or…
A: “Since you have posted multiple questions, we will provide the solution only to the first question…
Q: s position tests material that has a defective content on the averag ems, the inspector is able to…
A: Production is a process that turns raw materials into finished products while utilizing a variety of…
Q: Develop Xbar and R charts for the 1st 10 days of monitoring. Plot the data for the 1st 10 days on…
A:
Q: The average proportion defective is known to be 1%. What should the upper and lower control limits…
A: Let me state the given data, From the given input data, I will determine the upper control limit and…
Q: A company has seven products that are processed through 13 types of machines. The table below gives…
A: Find the given details below:
Q: a. Goods have to be transported from sources S1, S2 and S3, to destinations D1, D2 and D3. The…
A: SourceDestinationD1D2D3SupplyS1856120S215101280S4391080Demand 1508050
Q: Southland Corporation's decision to produce a new line of recreational products has resulted in the…
A: Long-Run DemandDecisionLowMediumHighVendor A$230$300$300Vendor B$140$300$650
Q: The sketch of a feasible region is given below, which point is not a point consistent with a…
A: The sketch of a feasible region is shown in the graph, A coordinate point coming from that sketch,…
Q: Activity AB AC AD DC CB DE CF BF IJ CE EF FG FH EH GH EJ GI HJ ΤΕ a. Draw the AOA diagram. b. Find…
A: Find the given details below:Note that, the first 5 (a to e) questions are not relevant to the given…
Q: What are the organization’s leadership that can contribute to the non-profit organization?
A: The objective of the question is to identify the types of leadership within an organization that can…
Q: 1.5. What is quality of conformance from the producer's perspective and how can it be achieved? 1.6.…
A: A learning curve is a graphical representation that shows how an increase in learning (measured on…
Q: Mr. R. wishes to determine the number of daily servings of steak and potatoes that will meet the…
A: First, I would formulate the LP, this formulation is shown below, Decision variables:The total…
Q: Refer to Table S6.1 - Factors for Computing Control Chart Limits (3 sigma) for this problem. Sample…
A: Find the Given details below:
Q: Select two CAATs and explain how they are useful in auditing. Suggest a method that someone with…
A: The objective of this question is to understand the functionality and usefulness of two Computer…
Q: Provide two types of legal issues that may arise when you are providing services to a person.
A: Law plays an integral role in making the judgements related to complex situations. It helps in…
Q: Compare and contrast taxonomies of IT project Management
A: Taxonomies in IT project management provide frameworks for categorizing and organizing project…
Q: Classify each of the following costs into a Cost of Quality (COQ) category (prevention, appraisal,…
A: Find the given details below:
Q: The following information is known about a project to upgrade a point-of-sale system at Kids and…
A: Critical path method(CPM) is a project management tool (others e.g WBS, PERT). It uses flow chart…
Q: Criterion LPA L 1 3 P312 1 A 4 11 Criterion 1 4 Leadership Personal Administrative Candidate Jacobs…
A: Find the given details below: Given details:CriterionLPAL10.330.25P312A40.51
Q: The following tabulations are actual sales of units for 6 months and a starting forecast in January.…
A: Find the given details below:
Q: Let A, B, and C be the amounts invested in companies A, B, and C. If no more than 40% of the total…
A: Given that no more than 40% of the total investment can be in company B, this statement will be…
Q: Enumerate , What are the challenges of forecasting in volatile or uncertain environments?
A: Forecasting is a strategy that uses historical data to make educated projections about the future…
Q: What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D…
A: 1. Take the ES of the initial activity as 0. 2. Add duration to this to get EF. 3. This EF will…
Q: Mark Gershon, owner of a musical instrument distributorship, thinks that demand for guitars may be…
A: Find the given details below:
Q: How should the $1.3 million be allocated to each of the loan/investment alternatives to maximize…
A: Here, the total annual return is to be maximized, First, I will set the LP formulation, and then, I…
Q: benefit of employee involvement is: A) Employees are not able to spot and pinpoint areas for…
A: Employee involvement plays a crucial role in organizational success by fostering a collaborative and…
Q: Tanaka Machine Shop is considering a four-year project to improve its production efficiency. Buying…
A: Net Present Value is the sum of the present value of all the cash inflows and outflows. A project…
Q: For the Session Long Project you will be choosing a company whose product you personally use and…
A: A product specifies the goods, a service, or an object that is offered by the company or business in…
Q: The seasonal demand for a particular product is given below: Period 1 2 3 4 5 6 Demand 300 450 100…
A: Inventory management is the part of production or operation management of an organization including…
Q: Develop Xbar and R charts for the 1st 10 days of monitoring. Plot the data for the 1st 10 days on…
A:
Q: Visiting an applicant's social media pages can be used to screen a candidate. True or False?
A: Social media has become an integral part of modern life, with platforms like Facebook, Twitter,…
Q: Cutlery Corner sells specialty knives to knife enthusiasts. They have a generous advertising budget…
A: T = dollars spent on a TV campaignN = dollars spent on newspaper advertisementsRF = dollars spent on…
Q: The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $ whole number).…
A: Project crashing is a process that helps to reduce the total duration using additional costs and…
Q: Lewins Change Management model
A: Lewin's Change Management Model: Lewin's…
Q: The maintenance department of RDB Company has devised the following set of tasks to replace a major…
A: TaskPredecessorNormal time (days)Max. Possible compression daysExpediting cost/days…
Q: An express bus system is to be set up between Kaneshie and AIT Campus at a distance of 6km. The…
A: To design the express bus service during the peak period, we need to determine several parameters…
Q: Given the project activity table below: Activity A B C D E F G H I J K Duration (weeks) 8 4 3 3 1 7…
A: Here, for each activity, I am given the dependency data and the duration data in weeks, Let me show…
Q: Write a one-page letter to your office manager on the following issue. Please be succinct in your…
A: Business Communication is an aspect of the business or organization that focuses on the sharing of…
A plant is acquiring new production machinery. Before the machinery can be fully functional, a number of activities must be performed. The activities, their precedence relationships, and their durations are shown in the following table.
|
Days |
|
||
Activity |
a |
m |
b |
Immediate Predecessors |
A |
6 |
8 |
10 |
- |
B |
4 |
5 |
6 |
- |
C |
1 |
2 |
3 |
- |
D |
8 |
18 |
28 |
A |
E |
4 |
5 |
6 |
C |
F |
7 |
8 |
9 |
B, D, E |
G |
4 |
5 |
9 |
B, D, E |
H |
12 |
13 |
14 |
F |
I |
8 |
9 |
10 |
F |
J |
4 |
5 |
6 |
G, H |
K |
2 |
5 |
8 |
I, J |
L |
1 |
2 |
6 |
G, H |
Use excel to answer the following;
d) What is the critical path and project completion time?
e) What is the probability that the job will finish in 59 days or less?
f) What is the probability that the job will finish in 54 days or more?
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 9 images
- A regional conglomerate is about to upgrade its customised accounting software System 2000(S2K)across the region. The directors of the group are eager to have the software upgraded to improve thequality of data from the information system. The new software requires reliable internet access andcan be accessed from anywhere using a Virtual Private network (VPN) connection. The followingactivities with times in weeks are under consideration.Activity ImmediatepredecessorsOptimistictimeMost likelytimeMostpessimistictimeVarianceA - 4 6 8 .4444B - 1 4.5 5 .4444C A 4.5 6.5 7 .1736D A 4 5 6 .1111E B,C 4.5 5.5 8 .3403F D 3 4 5 .1111G E,F 1 1.5 5 .4444H F,G 5 6 7 .1111You must use two decimal places at all times for expected times when they are not integer (you arenot permitted to round off to integers).(a) Draw the activity network for this problem (b) Determine the Expected Times. (c) Determine the activity schedule (ES, EF, LS, and LF) as well as slack.(d) Determine and state the critical path…Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: Time (days) Immediate Time (days) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 4 7 8 — H 3 3 6 E, F B 1 2 3 — I 3 7 9 G, H C 7 7 7 A J 2 6 9 I D 6 9 13 A K 8 9…The ideal outcome of the planning process group is to complete a project successfully by delivering the agreed-upon project scope within time, cost, and quality constraints Select one: True False Initiating involves developing a project charter, which is part of the project ______ management knowledge area. Select one: a. scope b. risk c. communications d. integration Estimate activity resources output Select one: a. Activity list, activity attributes, milestone list, project management plan updates b. Project schedule network diagrams, project documents updates c. Activity resource requirements, resource breakdown structure, project documents updates d. Schedule management plan As time progresses, the scope of a project should become ... Select one: a. more clear and specific b. more vague c. more ambiguous d. more difficult
- Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (A) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)Answer all the following questions based on Table 2 (a) Feasibility studies for a project is an early study before the project begins. List and briefly explain the feasibility processes. (b) Walkers Corporation is analyzing three capital projects with expected cash flows given in the Table 2 below. Each cash flow with an estimated of five years life and four year life. Interest rate of the cash flows is 10 % per annum. The Walkers Corporation uses investment appraisal techniques which is Payback Method. Analyze the appropriate calculations under the investment techniques stated above and give reasons for your investment advice. Table 2 Year Projects / Cash Flow (RM) Delta Gamma Beta 0 (250,000) (450,000) (650,000) 1 60,000 110,000 150,000 2 60,000 130,000 150,000 3 60,000 160,000 150,000 4 60,000 190,000 150,000 5 60,000 - 150,000The project described in the following table has just begun. It is scheduled to be completed in 11 weeks.Use Table B1 and Table B2. Activity Estimated Time(weeks) Standard Deviation(wks.) 1-2 4 0.70 2-4 6 0.90 1-3 3 0.62 3-4 9 1.90 a. If you were the manager of this project, would you be concerned? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) because the probability of finishing on schedule is only about . b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability Have worked this with various formulas and all come back wrong. Where am I making a mistake
- Hi, I need help answering the last question. Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed. Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 5 3 $800 $1,200 - B 6 5 $300 $450 - C 6 5 $550 $775 - D 3 2 $750 $950 A E 6 3 $1,350 $2,250 C F 5 3 $675 $875 B What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)Jaronda is a member of a dance team. As a fundraiser, she and the other members of the team decide that she will use the team's money to buy flowers in bulk, sell the flowers individually to students with her school's permission, and return the team's money plus any profits she makes, What is the MOST accurate name for aronda's role? O A. project manager © B. network facilitator O C data manager O D. systems operatorDave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managers
- Simplifying the ABC System: DBC Electan Company produces two types of printers. The company uses ABC, and all activity drivers are duration drivers. Electan Company is considering using DBC and has gathered the following data to help with its decision. A. Activities with duration drivers: Activities Products Changeover Assembly Testing Rework Total Hours Printer A 1,000 12,000 8,000 8,000 25,000 Printer B 4,000 8,000 12,000 12,000 25,000 Total hours 5,000 20,000 20,000 20,000 50,000 B. Activities with consumption ratios and costs: Activities Products Changeover Assembly Testing Rework CostAssignment Printer A 0.20 0.60 0.40 0.80 $155,000 Printer B 0.80 0.40 0.60 0.20 $155,000 Activity costs $75,000 $120,000 $60,000 $55,000 $310,000 C. Products with cycle time and practical capacity: Products Cycle Time PracticalCapacity…Limbo Technologies has embarked on another project that has an estimated completion time of 40 weeks and a standard deviation of 5 weeks. It is estimated that the project completion time is normally distributed. i)What is the probability of finishing the project in 38 weeks or less? ii)The due date for the project is set so that there is a 90% chance that it will finish by this date. What is the due duration? ACTIVITY PREDECESSOR NORMAL TIME (WEEKS) CRASH TIME (WEEKS) NORMAL COST ($) CRASH COST ($) A - 4 2 1000 1600 B - 6 3 3000 3500 C A 3 1 2500 3000 D A,B 6 5 1500 1850 E D 4 2 3500 4200 F C 4 3 2250 3000 G D 3 2 1900 2500 H F,G,E 2 1 400 5002. Joe and Noël have just gotten engaged. As they are both business students, they thought they'd try to plan their wedding preparation as a project. Here's the WBS they've determined is necessary for a simple but elegant wedding. Assume all durations are deterministic. Although perhaps not realistic to real wedding planning, by using the standard calendar in Project Libre (use default working days in software). Task ID Task Name Duration Predecessor 1 Begin Wedding Planning (milestone) 0 days --- 2 Select Site&Date 3 wks 1 3 Hire Officiant 1 wk 2 4 Hire Caterers 2 wks 1 5 Pick Menu 4 days 4 6 Order Invitations 2 wks 2,5 7 Sent Invitations to Guests 1 wk 6 8 Collect RSVPs 6 wks 7 9 Tell Caterer headcount & Order food 1 wk 8 10 Shop for Wedding Gown 4 wks 1 11 Select Bridesmaids Dresses 4 wks 10 12 Bride goes on Diet 6 wks 10 13 Get Wedding Gown altered 2 wks 12 14 Get Bridemaids' Dresses altered 4 wks 11 15 Order Flowers 2 wks 11 16…