A project has a PV at status of $55000 at the status date and a BAC of $180000 at the end of the project. the project schedule is 14 months and at the status date AC is equal to 121000 and EV has been calculated to be 31000. project sponsor wants to know what the VACdur forecast is in months if a new eac$ is used for revised funding? sponsor assuming the project will continue the way it is currently going.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter9: Decision Making Under Uncertainty
Section: Chapter Questions
Problem 46P
icon
Related questions
Question

A project has a PV at status of $55000 at the status date and a BAC of $180000 at the end of the project. the project schedule is 14 months and at the status date AC is equal to 121000 and EV has been calculated to be 31000.

project sponsor wants to know what the VACdur forecast is in months if a new eac$ is used for revised funding? sponsor assuming the project will continue the way it is currently going.

Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,