A project's internal rate of return (IRR) is the  that forces the PV of the expected future cash flows to equal the initial cash flow. The IRR is an estimate of the project's rate of return, and it is comparable to the  on a bond. The equation for calculating the IRR is:   CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal . The IRR calculation assumes that cash flows are reinvested at the . If the IRR is  than the project's cost of capital, then the project should be accepted; however, if the IRR is less than the project's cost of capital, then the project should be . Because of the IRR reinvestment rate assumption, when  projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR:  differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the  method should be used to evaluate projects. Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%.   0 1 2 3 4                       Project A -1,250 730 360 270 315 Project B -1,250 330 295 420 765 What is Project A’s IRR? Do not round intermediate calculations. Round your answer to two decimal places.  % What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places.  % If the projects were independent, which project(s) would be accepted according to the IRR method?  would be accepted. If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method?  would be accepted. Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive?   The reason is the NPV and IRR approaches use  when mutually exclusive projects are considered. Reinvestment at the  is the superior assumption, so when mutually exclusive projects are evaluated the  approach should be used for the capital budgeting decision.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter11: Capital Budgeting Decisions
Section: Chapter Questions
Problem 7PA: There are two projects under consideration by the Rainbow factory. Each of the projects will require...
icon
Related questions
Question

The Basics of Capital Budgeting: Evaluating Cash Flows: IRR

A project's internal rate of return (IRR) is the  that forces the PV of the expected future cash flows to equal the initial cash flow. The IRR is an estimate of the project's rate of return, and it is comparable to the  on a bond. The equation for calculating the IRR is:

 

CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal .

The IRR calculation assumes that cash flows are reinvested at the . If the IRR is  than the project's cost of capital, then the project should be accepted; however, if the IRR is less than the project's cost of capital, then the project should be . Because of the IRR reinvestment rate assumption, when  projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR:  differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the  method should be used to evaluate projects.

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%.
  0 1 2 3 4
                     
Project A -1,250 730 360 270 315
Project B -1,250 330 295 420 765

What is Project A’s IRR? Do not round intermediate calculations. Round your answer to two decimal places.

 %

What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places.

 %

If the projects were independent, which project(s) would be accepted according to the IRR method?

 would be accepted.

If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method?

 would be accepted.

Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive?

 

The reason is the NPV and IRR approaches use  when mutually exclusive projects are considered.

Reinvestment at the  is the superior assumption, so when mutually exclusive projects are evaluated the  approach should be used for the capital budgeting decision.

 

 

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash
flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects
have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%.
0
1
4
%
2
-1,250
Project A
Project B -1,250
730
330
What is Project A's IRR? Do not round intermediate calculations. Round your answer to two decimal places.
%
3
360
295
270
420
315
765
What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places.
Transcribed Image Text:Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%. 0 1 4 % 2 -1,250 Project A Project B -1,250 730 330 What is Project A's IRR? Do not round intermediate calculations. Round your answer to two decimal places. % 3 360 295 270 420 315 765 What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Effect Of Interest Rate
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,