A proposed building is to have three levels of underground parking, as shown in the figure below. To construct this building, it will be necessary to make a 10.0 m excavation, which will need to be temporarily dewatered. The natural and dewatered groundwater tables are shown, and the medium clay is normally consolidated. The dewatering of the area under the existing building caused an increase in vertical effective stress. 5 m | B y=19.5 kN/m -28 m- Existing building Natural Dewatered y dz Sand- (assume imcompressible) Medium clay 42m A Proposed 1.5 m building 8.5 m 2.5 m C/(1+eo)= 0.26 y = 16.5 kN/m³ Stiff soils (assume imcompressible) 10 m V 1.7 12.5 m- z 1.5 m Y=20.0 kN/m³. 10.3 m Unit weight of SAND above the water table is 19.5 KN/cum while that below the water table is 20 KN/cum. The unit weight of CLAY is 16.5 KN/cu.m. The chief engineer is concerned that this dewatering operation may cause excessive settlement in the adjacent building and has asked you to: Compute for the anticipated differential settlement across the width of this building (between A and B) (in mm). Compute the primary consolidation settlement of the clay layer below point A due to the dewatering process (in mm). Compute for the primary consolidation settlement of the clay layer below point B due to the dewatering process (in mm).

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
icon
Concept explainers
Question
A proposed building is to have three levels of underground parking, as shown in the figure below. To
construct this building, it will be necessary to make a 10.0 m excavation, which will need to be
temporarily dewatered. The natural and dewatered groundwater tables are shown, and the medium
clay is normally consolidated. The dewatering of the area under the existing building caused an increase
in vertical effective stress.
- 28 m -
Existing building
A
B
Proposed
1.5 m building
Natural y.
Dewatered
y = 19.5 kN/mª
5 m
1.51
8.5 m
10 m
12.5 m
Sand-
(assume imcompressible)
2.5 m
Fy= 20:0 kN/m.
Medium clay C(1+ eo) = 0.26
y = 16.5 kN/m³
10.3 m
Stiff soils (assume imcompressible)
Unit weight of SAND above the water table is 19.5 KN/cum while that below the water table is 20
KN/cuM. The unit weight of CLAY is 16.5 KN/cyM.
The chief engineer is concerned that this dewatering operation may cause excessive settlement in the
adjacent building and has asked you to:
Compute for the anticipated differential settlement across the width of this building (between A and B)
(in mm).
Compute the primary consolidation settlement of the clay layer below point A due to the dewatering
process (in mm).
Compute for the primary consolidation settlement of the clay layer below point B due to the dewatering
process (in mm).
Transcribed Image Text:A proposed building is to have three levels of underground parking, as shown in the figure below. To construct this building, it will be necessary to make a 10.0 m excavation, which will need to be temporarily dewatered. The natural and dewatered groundwater tables are shown, and the medium clay is normally consolidated. The dewatering of the area under the existing building caused an increase in vertical effective stress. - 28 m - Existing building A B Proposed 1.5 m building Natural y. Dewatered y = 19.5 kN/mª 5 m 1.51 8.5 m 10 m 12.5 m Sand- (assume imcompressible) 2.5 m Fy= 20:0 kN/m. Medium clay C(1+ eo) = 0.26 y = 16.5 kN/m³ 10.3 m Stiff soils (assume imcompressible) Unit weight of SAND above the water table is 19.5 KN/cum while that below the water table is 20 KN/cuM. The unit weight of CLAY is 16.5 KN/cyM. The chief engineer is concerned that this dewatering operation may cause excessive settlement in the adjacent building and has asked you to: Compute for the anticipated differential settlement across the width of this building (between A and B) (in mm). Compute the primary consolidation settlement of the clay layer below point A due to the dewatering process (in mm). Compute for the primary consolidation settlement of the clay layer below point B due to the dewatering process (in mm).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Sediment transport
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning