A schedule for two processors has been created for the following project which has a finishing time of 30. A(6) B(11) Start C(1) D(9) E(8) End F(5) G(4) H(5) Which is the following statements is applicable to the schedule? OA. The schedule is optimal because the finishing time is equal to the critical time. B. The schedule is optimal because the finishing time is equal to the average time. C. The schedule is not optimal because the finishing time is greater than the critical time. D. The schedule is not optimal because the finishing time is greater than the average time. E. The schedule is not optimal because the finishing time is greater than both the average time and the critical time. F. The schedule is optimal because the finishing time is less than the critical time. G. The schedule is optimal because the finishing time is less than the average time. H. The schedule is not optimal because the finishing time is less than the critical time. 1. The schedule is not optimal because the finishing time is less than the average time. J. The schedule cannot be determined as optimal using the critical time and average time. OK. This schedule must be invalid since the finishing time cannot be less than the critical time. OL. This schedule must be invalid since the finishing time cannot be less than the average time.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
QUESTION 5
A schedule for two processors has been created for the following project which has a finishing time of 30.
A(6)
B(11)
Start
C(1)
F(5)
G(4)
D(9)
FO
●
H(5)
E(8)
●
Which is the following statements is applicable to the schedule?
O A. The schedule is optimal because the finishing time is equal to the critical time.
O B. The schedule is optimal because the finishing time is equal to the average time.
End
●
O C. The schedule is not optimal because the finishing time is greater than the critical time.
O D. The schedule is not optimal because the finishing time is greater than the average time.
O E. The schedule is not optimal because the finishing time is greater than both the average time and the critical time.
O F. The schedule is optimal because the finishing time is less than the critical time.
O G. The schedule is optimal because the finishing time is less than the average time.
OH. The schedule is not optimal because the finishing time is less than the critical time.
OI. The schedule is not optimal because the finishing time is less than the average time.
O J. The schedule cannot be determined as optimal using the critical time and average time.
OK. This schedule must be invalid since the finishing time cannot be less than the critical time.
OL. This schedule must be invalid since the finishing time cannot be less than the average time.
Transcribed Image Text:QUESTION 5 A schedule for two processors has been created for the following project which has a finishing time of 30. A(6) B(11) Start C(1) F(5) G(4) D(9) FO ● H(5) E(8) ● Which is the following statements is applicable to the schedule? O A. The schedule is optimal because the finishing time is equal to the critical time. O B. The schedule is optimal because the finishing time is equal to the average time. End ● O C. The schedule is not optimal because the finishing time is greater than the critical time. O D. The schedule is not optimal because the finishing time is greater than the average time. O E. The schedule is not optimal because the finishing time is greater than both the average time and the critical time. O F. The schedule is optimal because the finishing time is less than the critical time. O G. The schedule is optimal because the finishing time is less than the average time. OH. The schedule is not optimal because the finishing time is less than the critical time. OI. The schedule is not optimal because the finishing time is less than the average time. O J. The schedule cannot be determined as optimal using the critical time and average time. OK. This schedule must be invalid since the finishing time cannot be less than the critical time. OL. This schedule must be invalid since the finishing time cannot be less than the average time.
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.