Question
In case of total suspension, or suspension of activities along the critical path, which is not due to any fault of the contractor, the
elapsed time between the effective order of suspending operation and the order to resume work shall be allowed the contractor by
adjusting the contract time accordingly
True
False
Transcribed Image Text:In case of total suspension, or suspension of activities along the critical path, which is not due to any fault of the contractor, the elapsed time between the effective order of suspending operation and the order to resume work shall be allowed the contractor by adjusting the contract time accordingly True False
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Coordinate geometry in survey
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning