2. A project has the following description:
Activity Description Precedence
Duration (Weeks)
A
16
B
20
30
D
B
15
E
В
10
G
H
D
16
А
15
K
E, G, J
12
i) Draw a work-breakdown structure (WBS) for the project.
Answer:
Answer here..
ii) Draw a Gantt Chart for the project.
Answer:
Answer here .
iii) Using the activity-on-node precedence diagram, determine the critical path.
Transcribed Image Text:2. A project has the following description: Activity Description Precedence Duration (Weeks) A 16 B 20 30 D B 15 E В 10 G H D 16 А 15 K E, G, J 12 i) Draw a work-breakdown structure (WBS) for the project. Answer: Answer here.. ii) Draw a Gantt Chart for the project. Answer: Answer here . iii) Using the activity-on-node precedence diagram, determine the critical path.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials Health Info Management Principles/Prac…
Essentials Health Info Management Principles/Prac…
Health & Nutrition
ISBN:
9780357191651
Author:
Bowie
Publisher:
Cengage
Comprehensive Medical Assisting: Administrative a…
Comprehensive Medical Assisting: Administrative a…
Nursing
ISBN:
9781305964792
Author:
Wilburta Q. Lindh, Carol D. Tamparo, Barbara M. Dahl, Julie Morris, Cindy Correa
Publisher:
Cengage Learning