ABC has opened a small printing shop 12 months ago. ABC give good printing services and the business is growing steadily,except for February which is a slack month due to long holiday. Its manager, Mr adam has been studying the overhead cost and its relationship with machine hours.

Holt Mcdougal Larson Pre-algebra: Student Edition 2012
1st Edition
ISBN:9780547587776
Author:HOLT MCDOUGAL
Publisher:HOLT MCDOUGAL
Chapter11: Data Analysis And Probability
Section: Chapter Questions
Problem 8CR
icon
Related questions
Question

ABC has opened a small printing shop 12 months ago. ABC give good printing services and the business is growing steadily,except for February which is a slack month due to long holiday. Its manager, Mr adam has been studying the overhead cost and its relationship with machine hours.

Data from the most recent 12 months follow.
February
1,600
June
6,520
Month
April
4,560
May
6,880
January
March
Overhead 5,030
7,210
costs
(RM)
Machine
2,730
600
3403
2,200
3,411
2,586
hours
September October
November December
6,010
Month
July
August
5,570
7,728
5,810
Overhead 6,230
4,580
costs
(RM)
Machine
hours
3,364
2,411
3,960
2,897
2,207
| 2,864
In order to better understand the relationship between machine hours and overhead costs,
Adam has carried out regression analysis on the above data and the following regression
analysis have been obtained.
Constarit
R2
b coefficient
428
0.99
1.86
The number of machine hours for next month is expected to be 3,000.
Required:
a) Using the results of the regression analysis, calculate an estimate of overhead costs
for next month.
b) Do you share Adam's confidence that the above estimate of next month's costs is
likely to be accurate? Explain why or why not.
c) Identify the outlier and develop an alternative estimate of next month's costs using
the high-low method, and explain why this method is generally less reliable than
regression analysis as a basis for cost estimation.
Transcribed Image Text:Data from the most recent 12 months follow. February 1,600 June 6,520 Month April 4,560 May 6,880 January March Overhead 5,030 7,210 costs (RM) Machine 2,730 600 3403 2,200 3,411 2,586 hours September October November December 6,010 Month July August 5,570 7,728 5,810 Overhead 6,230 4,580 costs (RM) Machine hours 3,364 2,411 3,960 2,897 2,207 | 2,864 In order to better understand the relationship between machine hours and overhead costs, Adam has carried out regression analysis on the above data and the following regression analysis have been obtained. Constarit R2 b coefficient 428 0.99 1.86 The number of machine hours for next month is expected to be 3,000. Required: a) Using the results of the regression analysis, calculate an estimate of overhead costs for next month. b) Do you share Adam's confidence that the above estimate of next month's costs is likely to be accurate? Explain why or why not. c) Identify the outlier and develop an alternative estimate of next month's costs using the high-low method, and explain why this method is generally less reliable than regression analysis as a basis for cost estimation.
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Recommended textbooks for you
Holt Mcdougal Larson Pre-algebra: Student Edition…
Holt Mcdougal Larson Pre-algebra: Student Edition…
Algebra
ISBN:
9780547587776
Author:
HOLT MCDOUGAL
Publisher:
HOLT MCDOUGAL
Algebra & Trigonometry with Analytic Geometry
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:
9781133382119
Author:
Swokowski
Publisher:
Cengage
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill