An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial outlay of $209.71 million, and the expected cash Inflows would be $70 million per year for 5 years. If the firm does Invest in mitigation, the annual inflows would be $75.66 million. Unemployment in the area where the plant would be built is high, and the plant would provide about 350 good jobs. The risk adjusted WACC is 18%. a. Calculate the NPV and IRR with mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ IRR: -7.87 million 18.25 % Calculate the NPV and IRR without mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ 7.79 million IRR: 18.25 % b. How should the environmental effects be dealt with when evaluating this project? I. The environmental effects should be ignored since the plant is legal without mitigation. II. The environmental effects should be treated as a sunk cost and therefore ignored. III. If the utility mitigates for the environmental effects, the project is not acceptable. However, before the company chooses to do the project without mitigation, it needs to make sure that any costs of "ill will" for not mitigating for the environmental effects have been considered in the original analysis. IV. The environmental effects should be treated as a remote possibility and should only be considered at the time in which they actually occur. V. The environmental effects if not mitigated would result in additional cash flows. Therefore, since the plant is legal without mitigation, there are no benefits to performing a "no mitigation" analysis. -Select- ▼ c. Should this project be undertaken? 1. The project should be undertaken only under the "mitigation" assumption. II. The project should be undertaken since the IRR is positive under both the "mitigation" and "no mitigation" assumptions. III. The project should be undertaken since the NPV is positive under both the "mitigation" and "no mitigation" assumptions. -Select- IV. Even when no mitigation is considered the project has a negative NPV, so it should not be undertaken. V. The project should be undertaken only if they do not mitigate for the environmental effects. However, they have to make sure that they've done the analysis properly to avoid any "ill will" and additional "costs" that might result from undertaking the project without concern for the environmental impacts. v

Intermediate Financial Management (MindTap Course List)
13th Edition
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Eugene F. Brigham, Phillip R. Daves
Chapter12: Capital Budgeting: Decision Criteria
Section: Chapter Questions
Problem 20P: The Aubey Coffee Company is evaluating the within-plant distribution system for its new roasting,...
Question

Are the answers to A & B correct? Could I get some help on the multiple choice (B&C)?

An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air
pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial outlay of $209.71 million, and the expected cash
Inflows would be $70 million per year for 5 years. If the firm does Invest in mitigation, the annual inflows would be $75.66 million. Unemployment in the area where the plant would be built is high, and the plant would provide about 350 good jobs. The risk
adjusted WACC is 18%.
a. Calculate the NPV and IRR with mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate
calculations. Round your answers to two decimal places.
NPV: $
IRR:
-7.87 million
18.25 %
Calculate the NPV and IRR without mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate
calculations. Round your answers to two decimal places.
NPV: $
7.79 million
IRR:
18.25 %
b. How should the environmental effects be dealt with when evaluating this project?
I. The environmental effects should be ignored since the plant is legal without mitigation.
II. The environmental effects should be treated as a sunk cost and therefore ignored.
III. If the utility mitigates for the environmental effects, the project is not acceptable. However, before the company chooses to do the project without mitigation, it needs to make sure that any costs of "ill will" for not mitigating for the
environmental effects have been considered in the original analysis.
IV. The environmental effects should be treated as a remote possibility and should only be considered at the time in which they actually occur.
V. The environmental effects if not mitigated would result in additional cash flows. Therefore, since the plant is legal without mitigation, there are no benefits to performing a "no mitigation" analysis.
-Select- ▼
c. Should this project be undertaken?
1. The project should be undertaken only under the "mitigation" assumption.
II. The project should be undertaken since the IRR is positive under both the "mitigation" and "no mitigation" assumptions.
III. The project should be undertaken since the NPV is positive under both the "mitigation" and "no mitigation" assumptions.
-Select-
IV. Even when no mitigation is considered the project has a negative NPV, so it should not be undertaken.
V. The project should be undertaken only if they do not mitigate for the environmental effects. However, they have to make sure that they've done the analysis properly to avoid any "ill will" and additional "costs" that might result from
undertaking the project without concern for the environmental impacts.
v
Transcribed Image Text:An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial outlay of $209.71 million, and the expected cash Inflows would be $70 million per year for 5 years. If the firm does Invest in mitigation, the annual inflows would be $75.66 million. Unemployment in the area where the plant would be built is high, and the plant would provide about 350 good jobs. The risk adjusted WACC is 18%. a. Calculate the NPV and IRR with mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ IRR: -7.87 million 18.25 % Calculate the NPV and IRR without mitigation. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to two decimal places. NPV: $ 7.79 million IRR: 18.25 % b. How should the environmental effects be dealt with when evaluating this project? I. The environmental effects should be ignored since the plant is legal without mitigation. II. The environmental effects should be treated as a sunk cost and therefore ignored. III. If the utility mitigates for the environmental effects, the project is not acceptable. However, before the company chooses to do the project without mitigation, it needs to make sure that any costs of "ill will" for not mitigating for the environmental effects have been considered in the original analysis. IV. The environmental effects should be treated as a remote possibility and should only be considered at the time in which they actually occur. V. The environmental effects if not mitigated would result in additional cash flows. Therefore, since the plant is legal without mitigation, there are no benefits to performing a "no mitigation" analysis. -Select- ▼ c. Should this project be undertaken? 1. The project should be undertaken only under the "mitigation" assumption. II. The project should be undertaken since the IRR is positive under both the "mitigation" and "no mitigation" assumptions. III. The project should be undertaken since the NPV is positive under both the "mitigation" and "no mitigation" assumptions. -Select- IV. Even when no mitigation is considered the project has a negative NPV, so it should not be undertaken. V. The project should be undertaken only if they do not mitigate for the environmental effects. However, they have to make sure that they've done the analysis properly to avoid any "ill will" and additional "costs" that might result from undertaking the project without concern for the environmental impacts. v
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Essentials of Business Analytics (MindTap Course …
Essentials of Business Analytics (MindTap Course …
Statistics
ISBN:
9781305627734
Author:
Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning