An engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of equipment for $60,000 initially and will cost between $0.40 and $0.95 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The pumper can pump 100 metric tons per 8-hour day. If leased, the asset will have a contract period of 5 years. Plan 2 is a rental option that will cost $17,000 per year. In addition, an extra $18.5 per hour labor cost will be incurred for operating the rented equipment per 8-hour day. Which plan should the engineer recommend if the equipment will be needed for 65 days per year? The MARR is 10% per year. The annual worth of plan 1 lease optimistic is $ -17828 The annual worth of plan 1 most likely is $ -18328 The annual worth of plan 1 pessimistic is $ The annual worth of plan 2 rental is $ Plan 1 lease optimistic is better than rental of plan 2.

College Algebra (MindTap Course List)
12th Edition
ISBN:9781305652231
Author:R. David Gustafson, Jeff Hughes
Publisher:R. David Gustafson, Jeff Hughes
Chapter6: Linear Systems
Section6.8: Linear Programming
Problem 5SC: If during the following year it is predicted that each comedy skit will generate 30 thousand and...
icon
Related questions
Question

How is the AOC calculated and what are the solutions with steps?     Fast solution 

An engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of
equipment for $60,000 initially and will cost between $0.40 and $0.95 per metric ton to operate, with a most likely cost of $0.50 per
metric ton. The pumper can pump 100 metric tons per 8-hour day. If leased, the asset will have a contract period of 5 years. Plan 2 is a
rental option that will cost $17,000 per year. In addition, an extra $18.5 per hour labor cost will be incurred for operating the rented
equipment per 8-hour day. Which plan should the engineer recommend if the equipment will be needed for 65 days per year? The
MARR is 10% per year.
The annual worth of plan 1 lease optimistic is $-17828
The annual worth of plan 1 most likely is $ -18328
The annual worth of plan 1 pessimistic is $
The annual worth of plan 2 rental is $
Plan 1 lease optimistic is better than rental of plan 2.
Plan 1 most likely is better than rental of plan 2.
Plan 1 lease pessimistic is better than rental of plan 2.
Transcribed Image Text:An engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of equipment for $60,000 initially and will cost between $0.40 and $0.95 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The pumper can pump 100 metric tons per 8-hour day. If leased, the asset will have a contract period of 5 years. Plan 2 is a rental option that will cost $17,000 per year. In addition, an extra $18.5 per hour labor cost will be incurred for operating the rented equipment per 8-hour day. Which plan should the engineer recommend if the equipment will be needed for 65 days per year? The MARR is 10% per year. The annual worth of plan 1 lease optimistic is $-17828 The annual worth of plan 1 most likely is $ -18328 The annual worth of plan 1 pessimistic is $ The annual worth of plan 2 rental is $ Plan 1 lease optimistic is better than rental of plan 2. Plan 1 most likely is better than rental of plan 2. Plan 1 lease pessimistic is better than rental of plan 2.
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
College Algebra (MindTap Course List)
College Algebra (MindTap Course List)
Algebra
ISBN:
9781305652231
Author:
R. David Gustafson, Jeff Hughes
Publisher:
Cengage Learning