“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.”   Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year:     Department     Fabricating Machining Assembly Total Plant Manufacturing overhead $ 362,250 $ 414,000 $ 93,150 $ 869,400 Direct labor $ 207,000 $ 103,500 $ 310,500 $ 621,000     Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows:     Department     Fabricating Machining Assembly Total Plant Direct materials $ 3,700   $ 200   $ 2,100   $ 6,000   Direct labor $ 4,200   $ 500   $ 6,900   $ 11,600   Manufacturing overhead   ?     ?     ?     ?       Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.   2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.   4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a. What was the company’s bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 2EB: Salley is developing material and labor standards for her company. She finds that it costs $0.55 per...
icon
Related questions
Question

“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $4,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.”

 

Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year:

 

  Department  
  Fabricating Machining Assembly Total Plant
Manufacturing overhead $ 362,250 $ 414,000 $ 93,150 $ 869,400
Direct labor $ 207,000 $ 103,500 $ 310,500 $ 621,000
 

 

Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows:

 

  Department  
  Fabricating Machining Assembly Total Plant
Direct materials $ 3,700   $ 200   $ 2,100   $ 6,000  
Direct labor $ 4,200   $ 500   $ 6,900   $ 11,600  
Manufacturing overhead   ?     ?     ?     ?  
 

 

Required:

1. Using the company's plantwide approach:

a. Compute the plantwide predetermined rate for the current year.

b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

 

2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions:

a. Compute the predetermined overhead rate for each department for the current year.

b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

 

4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead).

a. What was the company’s bid price on the Koopers job using a plantwide predetermined overhead rate?

b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

Using the company's plant wide approach. Compute the plant wide predetermined rate for the current year.

 
 
 
 
Predetermined overhead rate   % of direct labor cost

Using the company's plant wide approach. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

 
 
 
 
Manufacturing overhead cost applied  
 
  • Suppose that instead of using a plant wide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Compute the predetermined overhead rate for each department for the current year.

     
     
     
     
    Predetermined Overhead Rate  
    Fabricating department   % of direct labor cost
    Machining department   % of direct labor cost
    Assembly department   % of direct labor cost
 
  • Suppose that instead of using a plant wide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

     
     
     
     
    Manufacturing overhead cost applied  

    Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What was the company’s bid price on the Koopers job using a plant wide predetermined overhead rate?

     
     
     
     
    Company's bid price  
    • Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

       
       
       
       
      Manufacturing overhead cost applied  
Expert Solution
Step 1 Formula used :

Predetermined overhead rate =Estimated overhead /estimated direct labor cost

Overhead Applied =Actual labor cost *predetermined overhead rate

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Cost allocation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Excel Applications for Accounting Principles
Excel Applications for Accounting Principles
Accounting
ISBN:
9781111581565
Author:
Gaylord N. Smith
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning