Charlie is planning to open a Chinese food restaurant “Dragon Express” in Montana. The following table lists all of the activities involved in the opening of the restaurant. Charlie is able to provide his three best estimates for each activity and he wants to know when his restaurant can be open. Use POM-QM to analyze the project and answer the following questions.  Activity # Activity name Predecessors Time estimates in weeks (a,m,b) 1 Select location and obtain financing - 2,4,8 2 Rent negotiation and sign paper work 1 1,2,2 3 Cleaning and renovation of the resturant 2 4,6,8 4 Design resutrant menu - 1,1,1 5 Order and recieve equipment and other necessities 2,4 4,8,12 6 Install equipment 3,5 1,1,1 7 Hire employees 6 1,2,2 8 Final examination 7 1,2,3   Based on the result of POM-QM, the expected completion time of the project is (type number only, no text, no decimals) Based on the result of POM-QM, the standard deviation of the project completion time is (type number only, two decimals, no text)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

Charlie is planning to open a Chinese food restaurant “Dragon Express” in Montana. The following table lists all of the activities involved in the opening of the restaurant. Charlie is able to provide his three best estimates for each activity and he wants to know when his restaurant can be open. Use POM-QM to analyze the project and answer the following questions. 

Activity # Activity name Predecessors Time estimates in weeks (a,m,b)
1 Select location and obtain financing - 2,4,8
2 Rent negotiation and sign paper work 1 1,2,2
3 Cleaning and renovation of the resturant 2 4,6,8
4 Design resutrant menu - 1,1,1
5 Order and recieve equipment and other necessities 2,4 4,8,12
6 Install equipment 3,5 1,1,1
7 Hire employees 6 1,2,2
8 Final examination 7 1,2,3

 

Based on the result of POM-QM, the expected completion time of the project is (type number onlyno text, no decimals)

Based on the result of POM-QM, the standard deviation of the project completion time is (type number onlytwo decimalsno text)
 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question
The probability that the project will be completed in 16 weeks or less is
1.74%
4.09%
45.91%
95.91%
 
The probability that the project will be completed in 20 weeks or less is
21.90%
28.1%
58%
71.90%
Solution
Bartleby Expert
SEE SOLUTION
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.