company that produces golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times and quantities on hand is shown in the following table. Parts list for golf cart Lead time Quantity on hand Golf cart Top Base 1 1 1 0 40 20 Top Supports(4) Cover 1 1 200 0 Base Motor Body Seats (2) 2 3 2 300 50 120 Body Frame Controls Wheel assemblies(4) 1 1 1 35 0 240 You are required to: a) Construct a product tree.
Q: Activities Predecessor Duration (days) A Initial plan B Requirement Enginearing cRequirement…
A: A Gantt Chart is a kind of bar chart that displays the project's activity schedule and is mainly…
Q: Discuss what are the problems face in implementing MRP system?
A: PROBLEMS IN THE IMPLEMENTATION OF MRPSYSTEMS Even though an MRP system's fundamental assumption is…
Q: QUESTION 1 A master production schedule shows the following information MPS Week Week Week Week…
A: Find the Given details below: Weeks 1 2 3 4 Forecasted Demand 1000 1200 1300 1200 Actual…
Q: Q2: The activities involved in the construction of a certain project are given in the table below.…
A: Based on the given activities and dependency, the following diagram can be prepared. Possible paths…
Q: 17 To minimize the effects of uncertainty due to lead times, MRP systems incorporate ______. a…
A: Note: - Since the exact question to be answered is not specified we will answer only the first…
Q: 2. Use the following MPS, BOM, and inventory record to answer the MRP questions. a) Master…
A: The production schedule used to draft the plan for the final item is known as the master production…
Q: A factory has just received an order for 95 units of an end item, which are to be shipped at the…
A: Planned Order Release of Component D = 762 Formula Used : Projected available Balance =…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A:
Q: Chuck's Custom Boats (CCB) customizes speedboats to each customer's order. CCB has landed a contract…
A: Given- Activity ImmediatePredecessor Normal Time (weeks) CRASHING COSTS 1st Week 2nd Week…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: A time based production chart and Product structure chart are helps to identify the correct…
Q: 1) Table below is for a product with 150 unit lot size. The current on-hand inventory is 110 units.…
A: given,
Q: 3. The large parts of a playground A-frame (from which to hang a swing or glider) consist of a ridge…
A: In assembling and production, the product/item structure tree gives a various leveled…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: A product chart helps to identify the parental relationship between each materials based on the…
Q: (4-c) Fill the following MRP record and determine the planned order releases for item X225 for each…
A: Given data is Lead time = 2 weeks Lot size = Multiple of 50
Q: Assume that Product Z is made of two units of A and three units of B. A is made of four units of C…
A:
Q: What is the lead time (in weeks) to respond to a customer order for product A, based on the BOM…
A: Solution From the given bill of material - To manufacture product A, one B and one E is required.…
Q: a) How many units should be the safety stock? b) What’s the product’s inventory status? c) How many…
A: Safety stock is the inventory that an organization stores in the warehouse to use later for selling…
Q: calculate the MRP schedule sheet for the hospital cup (body, cap, straw, lid) hind (use the lid as…
A: Following is the BOM of thr cup :
Q: b) Samuel, production manager for an exercise equipment manufacturer, needs to schedule an order for…
A: Product structure representing the bill of materials in a hierarchical decomposition which helps to…
Q: An end item’s demand forecasts for the next 6 weeks are 30 units, followed by forecasts of 25 units…
A:
Q: Table B shows a partially completed MPS record for ball Develop the MPS for ball Four customer…
A: Following is the MPS of ball: Formulas used:
Q: a. Write the product structure diagram as an indented bill-of-materials list.
A: Indented bill-of-materials list is following:
Q: Product X is made of two units of Y and three of Z. Y is made of one unit of A and two units of B. Z…
A: A Small Introduction about MRP Material necessities arranging (MRP) is a PC based stock…
Q: Explain what functions of the business affect an MRP system ?
A: A chart is a graphical representation of the data that is delivered and shown. It is a technique for…
Q: The following table lists the components needed to assemble an end item, lead times, and quantities…
A: Given data
Q: The following table lists the components needed to assemble an end item, lead times, and quantities…
A: a. Net Requirement of End Item = 18-0 = 18 Net Requirement of B = 18*2 - 10 = 36-10 = 26 Net…
Q: he following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: Answer: Below is the given data in a tabular and diagrammatical form (Note: We simply have shown…
Q: 6-63
A:
Q: The BOM for product A is given below:Assume the master schedule calls for 200 units of product A in…
A: The cumulative requirements for each cycle are called the Gross Requirements. Scheduled receipts are…
Q: Given the product structure, master productionschedule, and inventory status in Figure 14.13, and…
A: given,
Q: The following table lists the components needed to assemble an end item, lead times (in weeks),and…
A: Material Requirement Planning refers to the quantification of the basic components that are required…
Q: In the following MRP planning schedule for Item J, indicate the correct net requirements, planned…
A: Given Information: Lead time = 1 weeks Beginning Inventory = 42 units Gross Requirements: Week 2: 65…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: Based on the given table, we prepare a product tree structure as shown below: Answer: 392
Q: Departmental Cost Allocation Logan Products has two production departments—assembly andfinishing.…
A: Direct Method Ratio of apportionment of sourcing departments cost to assembly and finishing = 40000…
Q: The following table lists the components needed to assemble an end item, the manufacturing or…
A: Operation manager must make sure that the inventory is up to date. An updated inventory helps to…
Q: d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales…
A: The estimated level of inventory that a manufacturer has in stock which can be readily sold is…
Q: The gross requirements for item A are specified for the beginning of weeks 1 through 12 in the table…
A: Given data is Ordering cost = $45 per order Holding cost = $4/unit/week
Q: The following table lists the components needed to assemble an end item, lead times, and quantities…
A: (a): Units of end item required = 17. Thus 17*2 = 34 units of B, 17 units of C and 17*3 = 51 units…
Q: What information is contained in a bill of material?
A: A Bill of Materials (BOM) is the finished rundown of the multitude of things that are needed to…
Q: In the following MRP planning schedule for Item J, indicate the correct net requirements,…
A: Projected available balance = projected available balance of previous week + scheduled receipts if…
Q: Sheet 9: Q8 Planning model Q8. Use below table to to find the profit of the company, (production…
A: In the linear regression model, two variables are taken into considerations. X is the independent…
Q: What is the lead time (in weeks) to respond to a customer order for product A, based on the BOM…
A: Solution 1. From the given figure, assembling of product A requires 1 unit of B and 1 unit of E.…
Q: Amelia Ltd. makes a plastic tricycle that is composed of three major components: a handlebar-front…
A: Let; FM be the number of fronts made SM be the number of seats made WM be the number of wheels made…
Q: Qty Standard Labor Hour Raw Material В Standard Labor 2 Hours Raw Material INDEPENDENT DEMAND Period…
A: Determine the ratio of workers:
Q: a) Develop the time-phased product structure. b) Produce the MRP for fulfilling the order.
A: The following steps have time phased structure and MRP for fulfilling the order
Q: An end item’s demand forecasts for the next 10 weeks are 30, 30, 30, 30, 20, 20, 30, 30, 30, and 30…
A: A Master Production Schedule can be referred to as a plan where the commodities can be scheduled as…
Q: What functions of the firm affect an MRP system? How?
A: Operations is an important base for every organization, whether in manufacturing, service, or…
Q: Mr. R is working from7:30 AM to 3:30PM including lunch break for 5 days every week in jewelry design…
A: Piece rate pay: The worker is paid per unit of creation in a piece-rate pay system. A person is…
Step by step
Solved in 2 steps with 1 images
- Table B shows a partially completed MPS record for ball Develop the MPS for ball Four customer orders arrived in the following sequences (Table B). Table A Order Quantity Week desired 1 500 4 2 400 5 3 300 1 4 300 7 Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept? Table B Item: Ball bearings Quantity on hand: 400 Order policy: 500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer order booked 300 350 250 250 200 150 100 100 100 100 Projected on-hand inventory MPS quantity 500 MPS start Available to promise (ATP)1. A company that produces golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times and quantities on hand is shown in the following table. Parts list for golf cart Lead time Quantity on hand Golf cart Top Base 1 1 1 0 40 20 Top Supports(4) Cover 1 1 200 0 Base Motor Body Seats (2) 2 3 2 300 50 120 Body Frame Controls Wheel assemblies(4) 1 1 1 35 0 240 You are required to: a) Construct a product tree. b) Determine the low level codes for all the components. c) Develop a material requirements plan that will provide 200 golf carts by week 8 assuming lot for lot ordering.3) Amelia Ltd. makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. The company has orders for 48,000 of these trikes. Current schedules yield the following information. Requirements Cost to Cost to Component Plastic Time Space Manufacture Purchase Front 12 40 8 16 24 Seat/Frame 16 24 8 12 18 Rear wheel (each) .20 8 .4 2 6 Available 100000 320000 60000 The company obviously does not have the resources available to manufacture everything needed for the completion of 24000 tricycles so has gathered purchase information for each component. Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 24000 fully completed tricycles at the minimum cost.
- The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amounton Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 17 G(2), B(2) K 4 22 H(4), B(2) B 3 30 J 4 29 G 4 3 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)Additional units b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.) The latest weekPROBLEM-3) The Sales&Operations (S&OP) process is designed to produce a plan that all departmentswithin the organization, as well as suppliers to the organization, can work. The process is also sometimes referred toas sales, inventory, and operations planning (SIOP) to emphasize the important role that inventory can play as abuffer between sales planning and operations planning. The S&OP department of the XYZ company, that producesKLM products, estimates the sales over the next six years in thousands of packages will be as follows: Assume that each worker stays on the job for at least one year and XYZ currently has eight workers. XYZ estimatesthat they will have 600000 packages on hand at the end of the current year. Assume that, on average, eachworker is paid TL 60000 per year and is responsible for producing 80000 packages. Inventory costs have beenestimated to be 20 KRS per package per year, and shortages are not allowed. XYZ estimates that it costs TL 2500for each…The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amounton Hand Direct Components End 1 0 L(2), C(1), K(3) L 2 11 B(2), J(3) C 3 17 G(2), B(2) K 4 23 H(4), B(2) B 3 34 J 3 25 G 3 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.) b.An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)
- 2-The company is developing a new product that will incorporate subassemblyC. As part of the development process, a manufacturing testrunwill be conducted, requiring an extra 500 subassembly C’s per week.What is the earliest week this extra production can be added while stillmaintaining the inventory requirements of all components?As the production planner for Xiangling HuProducts, Inc., you have been given a bill of material fora bracket that is made up of a base, two springs, and fourclamps. The base is assembled from one clamp and twohousings. Each clamp has one handle and one casting. Eachhousing has two bearings and one shaft. There is no inventoryon hand. a) Design a product structure noting the quantities for eachitem and show the low-level coding.b) Determine the gross quantities needed of each item if youare to assemble 50 brackets.c) Compute the net quantities needed if there are 25 of thebase and 100 of the clamp in stock.1. In an assemble-to-order company, at which level should master scheduling take place? a. The end item level b. The raw material/component level c. None of the above levels d. It does not matter, any level will do e. The component/subassembly level 2. The final assembly schedule (FAS) a. Schedules customer orders as they are received based on components planned in the MPS b. None of the above c. Is used with make-to-stock products d. Is used with make-to-order products e. A and b above 3. The functions of a master production schedule are to: I. Plan material components. II. Plan capacity requirements. III. Keep priorities valid a. II, III and not I b. None of the above is a function of the MPS c. I, II and III d. I, II and III e. I, III and not II 4.The information needed to develop a master production schedule will be got from a. Inventory levels for individual end items b. None of the above c. The production plan d. The forecast of individual end…
- The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount Direct Components on Hand End 1 0 L(2), C(1), K(3) L 1 10 B(2), J(3) C 2 14 G(2), B(2) K 2 19 H(4), B(2) B 1 34 J 2 25 G 2 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? b. An order for the end item is scheduled to be shipped at the start of week 9. What is the latest week that the order can be started and still be ready to ship on time?2.1 Explain how the quality and timing of information received from the design consultants would influence the type of bill of quantities and the in-house planning in the quantity surveyor’s office.Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 9. Subscripts indicate quantity required for each parent. Assumelot-for-lot ordering. c) Develop a net material requirements plan for F (enter your responses as whole numbers). Week Lead Time Item 2 3 4 5 6 7 8 9 (weeks) F Gross req Insert answer insert answer 2 On hand insert answer insert answer Net req insert answer insert answer Order receipt insert answer insert answer Order release insert answer insert answer