The following table lists the components needed to assemble an end item, lead times, and quantities on hand.                     Item End B C D E F G H LT (wk) 1 2 3 3 1 2 1 2 Amount on hand 0 10 10 25 12 30 5 0           a. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)   Additional units               b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
 

                 
Item End B C D E F G H
LT (wk) 1 2 3 3 1 2 1 2
Amount on hand 0 10 10 25 12 30 5 0
 

 

 

 

 

a. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)
 
Additional units            
 
b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)
 
The latest week            

 
 
 
 
 
The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
Item
End
C
D
E
G
LT (wk)
1
2
1
Amount on hand
10
10
25
12
30
End Item
B (2)
D (3)
E (2)
F (3)
G (2)
E (2)
H (4)
E (2)
a. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP
plan to determine this.)
Additional units
b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started
and still be ready to ship on time? (Hint. You don't need to develop an MRP plan for this part either.)
The latest week
IN O
Transcribed Image Text:The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End C D E G LT (wk) 1 2 1 Amount on hand 10 10 25 12 30 End Item B (2) D (3) E (2) F (3) G (2) E (2) H (4) E (2) a. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and still be ready to ship on time? (Hint. You don't need to develop an MRP plan for this part either.) The latest week IN O
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 6 images

Blurred answer
Knowledge Booster
Facility layout
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.