Consider a production system composed of 1 station at which arriving jobs are processed. The mean time between arrivals equals 5 minutes with a standard deviation of 2 minutes. The mean processing time of a job is 4 minutes, with standard deviation of 2 minutes. It is assumed that the queue has infinite capacity. a) Estimate the expected waiting time in queue. b) Estimate the expected number of jobs waiting in queue.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section12.5: Analytic Steady-state Queueing Models
Problem 27P
icon
Related questions
Question
Consider a production system composed of 1 station at which arriving jobs are
processed. The mean time between arrivals equals 5 minutes with a standard
deviation of 2 minutes. The mean processing time of a job is 4 minutes, with
standard deviation of 2 minutes. It is assumed that the queue has infinite capacity.
a) Estimate the expected waiting time in queue.
b) Estimate the expected number of jobs waiting in queue.
Transcribed Image Text:Consider a production system composed of 1 station at which arriving jobs are processed. The mean time between arrivals equals 5 minutes with a standard deviation of 2 minutes. The mean processing time of a job is 4 minutes, with standard deviation of 2 minutes. It is assumed that the queue has infinite capacity. a) Estimate the expected waiting time in queue. b) Estimate the expected number of jobs waiting in queue.
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,