Consider the following product structure: Each A consists of one B and three Cs. Each B consists of one D, 2 Es, and 5 Fs. Each C consists of one E and one F. How many Es are necessary to produce a single finished good A?
Q: The product structure tree for end item E follows: The manager wants to know the material…
A: Every business draws the material requirement planning to maintain the production process and…
Q: What does process planning entail? How would processplanning differ for batch and continuous…
A: The product-flow process is vital in any operations and production system. It is the prime duty of…
Q: Part A T V W Y On-hand Inventory 30 40 20 30 250 25 80
A: a) The Product BOM tree is as follows:
Q: Montague Composite makes a unit A, which consists of two units of B, three units of C, and four…
A: Net requirements = Gross requirements - (Beginnning inventory + current period Scheduled receipts)…
Q: Assume you are the manager of Assembly Inc., you have just received an order for 40 units of an…
A: Net requirements = Gross requirements - (Beginnning inventory + current period Scheduled receipts)…
Q: Consider the bill of material for a product, A, and the data given in the table that follows. The…
A: To be determined: solve the last 2 MCQ's with the help of given infomation. Answer to last 2 parts:…
Q: Assembly of End Item A requires 3 units of B and 2 Units of C. The scrap allowance for part B is…
A: Given details , Assembly of end item A requires 3 units of B and 2 units of C. Also The scarp…
Q: Product A consists of subassemblies B and C. Subassembly B requires two parts of D and one part of…
A: Product Structure Tree In manufacturing, a hierarchical grouping of the objects that form a product…
Q: For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31? For the Toy…
A: Instructions and formula used: Net requirements = Gross requirements - previous period…
Q: As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material…
A: Answer a. Option D is the right answer since Handle has lead time of 2 weeks and housing has lead…
Q: Assume that Product Z is made of two units of A and four units of B. A is made of three units of C…
A: Formula to be used ; Units needed = Requirements * Usage rate
Q: Given the table below, select the statement that best fits the box with the Asterix (*) Project…
A: Batch production is a method of production is manufacturing facility which facilitate the group…
Q: The MRP Department has a problem. Its computer “died” just as it spit out the following information:…
A:
Q: A table is assembled using three components, as shown in the accompanying product structure tree.The…
A:
Q: Develop a material requirements plan for end item P and its components, given the tree below. Assume…
A:
Q: The product structure tree for end item E follows: The manager wants to know the material…
A: The material requirements planning (MRP) is an effective inventory planning system that helps in…
Q: An end item’s demand forecasts for the next 6 weeks are 30 units, followed by forecasts of 25 units…
A:
Q: Ajay wanted to produce 20 percent of one product (A), 50 percent of another (B), and 30 percent of a…
A: The development of different versions (variants) of a product in batches, one after the other in a…
Q: One area to which aggregate planning decisions relate is: O a. layout O b. customer order quantities…
A: Aggregate planning can be defined as the concept of matching the demand and supply output over 12…
Q: Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule…
A: Product structure diagram: The product structure presents the material, segment parts…
Q: Given the following Product Structure Diagram The number of E’s required for each A is…
A: Gross requirements can be defined as the total requirements of a product to manufacture the final…
Q: Prepare a master production schedule for industrial pumps in the manner of the following table. Use…
A: Criteria: If POH becomes less than 10 then MPS of lot size 70 is scheduled. Calculate the…
Q: One unit of Part C is used in item A and in item B. Currently, we have 10 As, 20 Bs, and 100 Cs in…
A: Supply chain management is managing the flow of goods and services, involving the storage of raw…
Q: Determine the gross quantities needed of each item if you are to assemble 75 brackets compute…
A: no. of base required for 1 bracket = 1no. of base required for 75 brackets = 75
Q: Given the following MRP matrix for Item D: The planned order release for period 3 is
A:
Q: Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of…
A: a) MRP for component J is prepared as below Steps to create MRP Enter the gross requirement as…
Q: Product A consists of two units of Subassembly B, three units of C, and one unit of D. B is composed…
A: Product Structure Tree In production, the hierarchical classification of the items that make up the…
Q: As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material…
A: PART B number of base required for 1 bracket = 1number of base required for 75 brackets = 751)Base =…
Q: What term is used to identify the difference between the number of units of an item listed on the…
A: Lean manufacturing is described as a process through which wastes can be minimized and the…
Q: snip
A: Please thoroughly answer all parts of this question given in step 2
Q: Using the information in(You need to schedule I0 units of product Alpha fordelivery in 6 weeks.…
A: A Small Introduction about Product Structure Product structure is a progressive disintegration of a…
Q: snip
A: If a product structure diagram has five levels, Level 4 is the lowest.
Q: a. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material…
A:
Q: The following product structure tree indicates the components needed to assemble one unit of product…
A:
Q: Product A consists of subassemblies B and C. Subassembly B requires two parts of D and one part of…
A: Solution a) The product structure tree (BOM) is as shown in the figure-
Q: The following product structure tree indicates the components needed to assemble one unit of product…
A: To build a single unit of Product W, A=1, B=2, and C=4 are required. Therefore, for 100 units of W,…
Q: You need to schedule I 0 units of product Alpha fordelivery in 6 weeks. Three units of D and 2 units…
A: A Small Introduction about Product Structure Product structure is a progressive disintegration of a…
Q: In a make-to-order setting, what is the general procedure for creating a level development plan?
A: Produced to order is a production strategy in which a manufacturer does not begin producing a…
Q: Given the following Product Structure Record, the number of G's required for each A is A B D E (2)…
A: A product structure record is described as the classification of items in a hierarchical manner,…
Q: snip
A: A = B + 3C B= 1D+2E+5F 3C=1E+1F
Q: Each A (finished product) requires 1 of component B and 2 of component C. Each B requires 2 of part…
A: Following is the Product A BOM:
Q: Which of the following are the inputs for the material requirements planning? Master production…
A: 1. Master production scheduling, bill of materials and inventory records.
Q: Product M is made of 2 units of N and 3 unit of P. N is made of 2 units of R and 4 units of S. R is…
A: BOM or Bills of material or Product structure tree lists the components and sub-components and their…
Q: Describe a production environment in which MRP wouldbe useful. Describe a production environment in…
A: Material Requirement Planning is software-based inventory control for production planning and…
Q: Given the following Product Structure Diagram The number of G’s required for each A is…
A: The gross requirements of a product is the total requirements of different sub-products to make one…
snip
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- Given the following Product Structure Diagram The number of E’s required for each A is _________.Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?A product (A) consists of a base (B) and a casting (C). The base consists of a plate(P) and three fasteners (F). The lead time, current on-hand inventory and scheduledreceipts are given in the table below. All components are lot for lot. The MasterSchedule requires 100 units of product A be available in week 4 and 150 in week 6. Part Lead time On - Hand inventory Scheduled receipts A 1 20 None B 1 100 50 in Week 1 C 3 30 20 in Week 1, 30 in Week 2 P 2 0 50 in Week 1 F 3 0 30 in Week 1, 40 in Week 3 Required:A. Draw the product structure tree. B. Develop the MRP for Parts A, B, C, P, and F in order to meet the demand. Therows for MRP tables are Gross Requirement (GR), Scheduled Receipt (SR),On-Hand Inventory (OHI), Net Requirement (NR), and Planned Production (PP).
- A table is assembled using three components, as shown in the accompanying product structure tree.The company that makes the table wants to ship 100 units at the beginning of day 4, 150 units atthe beginning of day 5, and 200 units at the beginning of day 7. Receipts of 100 wood sections arescheduled at the beginning of day 2. There are 120 legs on hand. There are 60 braces on hand. Leadtimes (in days) for all items are shown in the following table. Prepare a material requirements planusing lot-for-lot ordering.Given the following Product Structure Diagram The number of G’s required for each A is _________.Product A consists of subassemblies B and C. Subassembly B requires two parts of D and one part of E. Subassembly C requires one part of D and one part of F.a. Draw a product structure tree (BOM) for this product.b. How many parts are needed to make 300 units of finishedproduct?
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. This exercise contains only parts b and c. Part 2 The product structure is as follows: Bracket Base(1) Clamp(1) Handle(1) Casting(1) Spring(2) Housing(1) Shaft(1) Clamp(4) Bearing(2) Handle(1) Casting(1) Part 3 b) Determine the gross quantities needed of each item if you are to assemble 100 brackets. Base: enter your response here units (enter your response as a whole number). Spring: enter your response here units (enter your response as a whole number). Clamp: enter your response here units (enter your response as a whole number). Housing: enter your response here units (enter your…As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 1 spring, and 3 clamps. The base is assembled from 2 clamps and 2 housings. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. This exercise contains only parts b and c. The product structure is as follows: Bracket Base(1) Clamp(2) Handle(1) Casting(2) Spring(1) Housing(2) Shaft(2) Clamp(3) Bearing(1) Handle(1) Casting(2) b) Determine the gross quantities needed of each item if you are to assemble 50 brackets. Base: ? Spring: ? Clamp: ? Housing: ? Handle: ? Casting: ? Bearing: ? Shaft: ?Product A consists of subassemblies B and C. Subassembly B requires two parts of D and one part of E.Subassembly C requires one part of D and one part of F. a. Draw a product structure tree (BOM) for this product. b. How many parts are needed to make 300 units of finished product?
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 3 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 2 shafts. There is no inventory on hand. This exercise contains only parts b and c. Part 2 The product structure is as follows: Bracket Base(1) Clamp(1) Handle(1) Casting(1) Spring(2) Housing(2) Shaft(2) Clamp(3) Bearing(2) Handle(1) Casting(1) Part 3 b) Determine the gross quantities needed of each item if you are to assemble 125 brackets. Base: 33 units (enter your response as a whole number). Spring: enter your response here units (enter your response as a whole number). Clamp: enter your response here units (enter your response as a whole number). Housing: enter your response here units (enter your response as a whole…A partially completed inventory record for the motor sub-assembly is shown in Figure 11.39.a. Complete the last three rows of the record by using theL4L rule.b. Complete the last three rows of the record by using thePOQ rule with P = 2. c. Complete the last three rows of the record by using thePOQ rule with P = 2.d. If it costs the company $1 to hold a unit in inventory fromone week to the next, and the cost to release an order is$50, which of the lot sizing rules used above will providethe lowest inventory holding + order release cost?Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day toassemble, subassemblies take two days and components take three days. When should an order be released for C3 if the 100 A’s are needed by day 7?