contractor agreed that. If his job was not done by a certain date, he  would pay $100 for the 1st day of delay and for each succeeding day $ 5more than the preceding day, How many days after the stipulated date  did he use if his penalty is $1080?

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter9: Pricing Construction Equipment
Section: Chapter Questions
Problem 7RQ
icon
Related questions
Question

A contractor agreed that. If his job was not done by a certain date, he  would pay $100 for the 1st day of delay and for each succeeding day $ 5more than the preceding day, How many days after the stipulated date  did he use if his penalty is $1080?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Pricing subcontractor's work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,