Create a residential construction Gantt Chart using the details for each items of work below. You can create in an excel file OR through sketching in your bond paper. 1. Grading and Building Permits (4 days) (7 days) 2. Site Work 3. Foundation a. Layout Footings b. Installation of Rebars (1 day) (2 days) (5 days) c. Footing Concreting 4. Rough Carpentry (1 day) (7 days) c. Windows/Doors Installation (2 days) (7 days) (14 days) (25 days) (35 days) (30 days) (40 days) (37 days) (5 days) (1 day) a. Set Steel b. Framing 5. Concrete Slab 6. HVAC 7.Facilities Rough-in 8. Roofing 9. Finish Exterior Work 10. Floor Finishing 11. Paint Works 12. Final Punch-Out 13. Construction close-out

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter16: Budget Estimating
Section: Chapter Questions
Problem 4RQ: Prepare a typical bay estimate based on the following information: a. Bay size of 350 feet and a...
icon
Related questions
Question
Gantt Chart
RESIDENTIAL CONSTRUCTION GANTT CHART
Create a residential construction Gantt Chart using the details for each items of work below.
You can create in an excel file OR through sketching in your bond paper.
1. Grading and Building Permits
(4 days)
(7 days)
2. Site Work
3. Foundation
a. Layout Footings
b. Installation of Rebars
(1 day)
(2 days)
(5 days)
c. Footing Concreting
4. Rough Carpentry
a. Set Steel
(1 day)
(7 days)
c. Windows/Doors Installation (2 days)
(7 days)
(14 days)
(25 days)
(35 days)
(30 days)
(40 days)
(37 days)
(5 days)
(1 day)
b. Framing
5. Concrete Slab
6. HVAC
7.Facilities Rough-in
8. Roofing
9. Finish Exterior Work
10. Floor Finishing
11. Paint Works
12. Final Punch-Out
13. Construction close-out
*Notes:
1. It is not necessary that one activity should finish before proceeding to the next one.
2. Some activities may be performed with other activities at the same time. Some activities may
happen at the same time with others. (For example: after 5 days of floor finishing, some may start
painting works outside the building.
3. Put dates in your Gantt Chart
4. No work to be done on Sundays.
5. No work to be done on Saturdays.
Transcribed Image Text:RESIDENTIAL CONSTRUCTION GANTT CHART Create a residential construction Gantt Chart using the details for each items of work below. You can create in an excel file OR through sketching in your bond paper. 1. Grading and Building Permits (4 days) (7 days) 2. Site Work 3. Foundation a. Layout Footings b. Installation of Rebars (1 day) (2 days) (5 days) c. Footing Concreting 4. Rough Carpentry a. Set Steel (1 day) (7 days) c. Windows/Doors Installation (2 days) (7 days) (14 days) (25 days) (35 days) (30 days) (40 days) (37 days) (5 days) (1 day) b. Framing 5. Concrete Slab 6. HVAC 7.Facilities Rough-in 8. Roofing 9. Finish Exterior Work 10. Floor Finishing 11. Paint Works 12. Final Punch-Out 13. Construction close-out *Notes: 1. It is not necessary that one activity should finish before proceeding to the next one. 2. Some activities may be performed with other activities at the same time. Some activities may happen at the same time with others. (For example: after 5 days of floor finishing, some may start painting works outside the building. 3. Put dates in your Gantt Chart 4. No work to be done on Sundays. 5. No work to be done on Saturdays.
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Sectioning basics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning