Determine the efficiency of each departmental operation if only one shift is operated between 7:30 am-4:30 pm, with a 40 minute lunchbreak and two 10 minute coffee breaks.

Precision Machining Technology (MindTap Course List)
2nd Edition
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Chapter2: Measurement, Materials, And Safety
Section2.5: Quality Assurance, Process Planning, And Quality Control
Problem 10RQ: If an X-bar chart graph falls below the LCL or rises above the UCL, a machining process is said to...
icon
Related questions
Question

A toy factory is planning to make an additional item, which would be processed in 4 departments. The company is proposing to produce 600,000 units per year, working 250 days per year. The estimates of times made by an industrial engineer are in the table:

                                 Departments
Times   1   2   3    4
Average processing time (second/part) 8  13 10 50
Average maintenance, time/day (minutes) 20 30 20 15
Average daily setup, time (minutes) 20 15 30 20
Average bookkeeping, time/day (minutes) 10 8 12 5
Machine adjustment, time/day (minutes) 15 10 15 15
Defective items, (% of production) 5  6   4   4

The parts are produced within the departments in a sequential manner (from department 1 to 2 to 3 to 4). 

 

Determine the efficiency of each departmental operation if only one shift is operated between 7:30 am-4:30 pm, with a 40 minute lunchbreak and two 10 minute coffee breaks. 

Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Precision Machining Technology (MindTap Course Li…
Precision Machining Technology (MindTap Course Li…
Mechanical Engineering
ISBN:
9781285444543
Author:
Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:
Cengage Learning