Determine the total number of days the team can complete the installation of the 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture. 07 8 Determine the total cost of labor and equipment for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices. 281,296.28 280,296.28 279,296.28 288,296.28
Determine the total number of days the team can complete the installation of the 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture. 07 8 Determine the total cost of labor and equipment for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices. 281,296.28 280,296.28 279,296.28 288,296.28
Construction Materials, Methods and Techniques (MindTap Course List)
4th Edition
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:William P. Spence, Eva Kultermann
Chapter8: Cast-in-place Concrete
Section: Chapter Questions
Problem 21RQ
Related questions
Question
Derive the labor and equipment cost for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices.
1. Team and Daily Rates
1- Project Engineer (P 2000/day)
1 - Construction Foreman (P 1000/day)
6 - Mason (P800/day)
12 - Laborer (P500/day)
2. Output of team is 13.5 cu.m per day.
3. Equipment (minor tools) is 10% of the labor cost.
AI-Generated Solution
AI-generated content may present inaccurate or offensive content that does not represent bartleby’s views.
Unlock instant AI solutions
Tap the button
to generate a solution
Recommended textbooks for you
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning