Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table O Total Cost with Normal Time Crash Time (weeks) Activity (weeks) Normal Cost $2,000 $2,300 A 3 B 2 1 с 3 3 $750 Immediate Crashing Predecessor(s) $2,650 $3,100 $750 $2,580 $1,300 $4,400 $2,000 D $2,300 E $1,000 A B C F $3,000 G $1,600 D, E weeks a) Based on the given information regarding the activities for the project, the project length = b) The total cost required for completing this project on normal time = $ ▼ c) For reducing the duration of the project by one week, the activity that should be crashed first is activity The cost of the project based on the first activity selected for crashing will increase by $ weeks d) The maximum weeks by which the project can be reduced by crashing= Total cost of crashing the project to minimum (or maximum weeks possible) = $ 8 6 3 4 4 3 2 2

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question

Answer part D only

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table
D
Total Cost
with
Normal Time Crash Time Normal
Immediate
Activity (weeks)
(weeks) Cost
Crashing Predecessor(s)
A
4
3
$2,000 $2,650
B
2
1
$2,300 $3,100
TTTT
C
3
3
$750
$750
D
8
4
$2,300 $2,580
A
E
6
3
$1,000 $1,300
B
F
3
2
$3,000 $4,400
C
G
4
2
$1,600 $2,000
D, E
a) Based on the given information regarding the activities for the project, the project length =
weeks.
b) The total cost required for completing this project on normal time = $
▼
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
The cost of the project based on the first activity selected for crashing will increase by $
weeks.
d) The maximum weeks by which the project can be reduced by crashing =
Total cost of crashing the project to minimum (or maximum weeks possible) = $
Transcribed Image Text:Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table D Total Cost with Normal Time Crash Time Normal Immediate Activity (weeks) (weeks) Cost Crashing Predecessor(s) A 4 3 $2,000 $2,650 B 2 1 $2,300 $3,100 TTTT C 3 3 $750 $750 D 8 4 $2,300 $2,580 A E 6 3 $1,000 $1,300 B F 3 2 $3,000 $4,400 C G 4 2 $1,600 $2,000 D, E a) Based on the given information regarding the activities for the project, the project length = weeks. b) The total cost required for completing this project on normal time = $ ▼ c) For reducing the duration of the project by one week, the activity that should be crashed first is activity The cost of the project based on the first activity selected for crashing will increase by $ weeks. d) The maximum weeks by which the project can be reduced by crashing = Total cost of crashing the project to minimum (or maximum weeks possible) = $
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,