DM. Inc. worked on a P10,500,000 contract in 2016 to construct an office building. During 2016, DM. INc. uses the cost-to-cost method of computing percentage of completion. At December 31, 2016, the balance in certain accounts were as follows. How much is the realized gross profit in 2016? * • Construction in progress - P3,780,000 • Accounts receivable - P360,000 • Progress billings - P1.800,000 Contract retention - P180,000 Mobilization fee - P140,000 • At December 31, 2016, the estimated cost at completion is P7,350,000. O P1,102,500 O P1,062,500 O P1,242,500 O P1,134,000
Q: Puff and Stuff Construction began a construction project in 2016. The contract price was…
A: Percentage of completion = Cumulative cost incurred at end of year / Total estimated cost Revenue…
Q: On February 1, 2014, Marsh Contractors agreed to construct a building at a contract price of…
A:
Q: Ramos, Inc. began work in 2017 on contract #3814. The contract price is $7,200,000. The contract is…
A: when there is percentage of completions is applied in order to calculate the profit till date. the…
Q: Redline Publishers, Inc. produces various manuals ranging from computer software instructional…
A: Capital expenditure: It refers to the amount spent on acquiring, maintaining, and improving the…
Q: Last year, Stone Builders, Inc. started work on a P10,600,000 construction contract which was…
A: As posted multiple independent questions we are answering only first question kindly repost the…
Q: Nucor Corporation produces steel and steel products at its eight mills and is a major recycler of…
A: Return on assets represents the percentage of how profitable a company's assets are in generating…
Q: 2016 2017 2018 $ 1.000.000.000,00 $ 2.916.000.000,00 $4.050.000.000,00 $ 3.000.000.000,00…
A: Contract Costing - A contract is a big job generally requiring an executing period of more than one…
Q: On January 1, 2016, AVIDA was contracted to construct a townhouse for SM Corp. for a total contract…
A: Using percentage method, the gross profit is recognized on the basis of percentage of costs incurred…
Q: PAPASA Co. has consistently used the percentage of completion to account for its construction…
A: In terms of accountancy, percentage of completion method is a way of recognizing revenue of a…
Q: Ahmed construction began work on a $10,000,000 contracts in 2016 to construct a bridge. During 2016,…
A: COST RECOVERY METHOD Contract price $10,000,000 Cost incurred during Current year (2016)…
Q: On January 1, 2016, the Marjlee Company began construction of an office building to be used as its…
A: Interest Capitalization:Interest capitalization refers to the interest amount that is added to the…
Q: On January 1, 2016, Randolf Company signed a contract to have Rory Associates construct a…
A: Interest to be capitalized = Lower of actual interest or avoidable interest
Q: Ahmed construction began work on a OMR 10,000,000 contracts in 2016 to construct a bridge. During…
A: Information given in question Contract price 10,000,000 Cost incurred during the year…
Q: The ETHAN Construction company was the lowest bidder on a specialized equipment contract. The…
A:
Q: Blue construction Co. has two projects for which it reported, as of December 31, 2012, the following…
A: Solution 1: Gross profit on Project A in 2011= Revenue recognized - Cost incurred = (P4,800,000*75%)…
Q: Sunland, Inc. began work on a $2,060,000 contract in 2017 to construct a warehouse. During 2017,…
A: Journal is a place where accounting transactions are listed in the book keeping system before ledger…
Q: The ETHAN Construction company was the lowest bidder on a specialized equipment contract. The…
A: Computation of Gross profit 2017 Particular Cost already incurred 6,562,500 Cost to…
Q: How much is the Gross Profit/Loss Realized in 2018? PAPASA Co. has consistently used the percentage…
A: Accounting is essential to operating a company since it allows businesses to track income and…
Q: The Skyline Corporation began constructing a building with a contract price of P43,800,000 in 2009.…
A: Amount of collection in 2009 = Progress billings to date - Accounts Receivable
Q: (Analysis of Percentage-of-Completion Financial Statements) In 2017, Steinrotter Construction Corp.…
A: Workings: Given values: The contract price was $ 1000000
Q: (Recognition of Profit on Long-Term Contracts) During 2017, Nilsen Company started a construction…
A: Given, Nilsen Company started a construction job with a contract price of $1,600,000 2017…
Q: DM, Inc. works on a P10,500,000 contract in 2015 to construct an office building. During 2015, DM,…
A: Introduction: Whenever a company employs the installments sales strategy to record its sales…
Q: PAPASA Co. has consistently used the percentage of completion to account for its construction…
A: Total cost = Cost incurred to date + Estimated cost to complete = 2,700,000 + 900,000 = P3,600,000
Q: Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete…
A: Classification of borrowings as general borrowings / specific borrowings:
Q: During 2009, Mason Construction, Inc. started work on a P 5,200,000 fixed-price construction…
A: Solution: % completion during 2009 = Cost incurred / Total estimated costs = 2,650,000 / (2,650,000…
Q: Heart, Inc. consistently uses the percentage of completion method of recognizing income. During…
A: The percentage of method recognise the cost on the basis of percentage of the work completed during…
Q: The Skyline Corporation began constructing a building with a contract price of P 43,800,000 in 2009.…
A: The question is based on the concept of Accounting Standard on Construction Contracts.
Q: During 2017 Apple Corporation built a new warehouse at a cost of $1,500,000 on land costing…
A: Cost of Warehouse=$15,00,000 Cost of land= $100,000 Outstanding Debt during 2017 = $1300,000…
Q: Meberick Company has consistently used the percentage-of-completion method of recognizing income. In…
A: Given that Contract price = €49,000,000 Costs incurred =…
Q: Constructing and Assessing Income Statements Using Cost-to-Cost Method On March 15, 2012, Frankel…
A: Contract costing is one of the costing method being used by the company for recording and accounting…
Q: Ramos, Inc. began work in 2017 on contract #3814. The contract price is $7,200,000. The contract is…
A: The gross profit and revenue are recognised on the basis of percentage of the work completed during…
Q: Blue Construction Company began work on a $979,000 construction contract in 2017, During 2017, Blue…
A:
Q: Archer Construction Company began work on a $420,000 construction contract in 2017. During 2017,…
A: a.
Q: During 2017, Reticulated Company constructed a new manufacturing facility at a cost of P30,000,000.…
A: Weighted average interest rate for general borrowings =12% * P30,000,000 / P40,000,000 + 8% *…
Q: In 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000.…
A: The percentage of completion method is a revenue recognition accounting concept that evaluates how…
Q: JC Construction, Inc. has consistently used the percentage of completion method of recognizing…
A: Revenue is recognized on the basis of percentage of work completed. Percentage of work completed is…
Q: Haft Construction Company has consistently applied the percentage-of-completion method. On January…
A: Contract costing is like job costing where costing constitutes a unit of cost. It is used to measure…
Q: Moon View Desert Homes constructed a subdivision of upscale homes north of Cave Creek, Arizona,…
A: Since, you have asked for a specific question. So, we will answer that question for you.
Q: During 2009, Mason Construction, Inc. started work on a P 5,200,000 fixed-price construction…
A: "Since you have asked multiple questions, we will solve the first question for you". If you want any…
Q: Shumpert, Inc. entered into a contract that was to take two years to complete, with an estimated…
A: Contract: This is an agreement made by two parties in between them which will create mutual legal…
Q: during 2017 totaled P7,800,000. The entity borrowed P4,000,000 at 7% on January 1, 2017. Funds not…
A: As per IAS 23, Borrowing costs on specific borrowing can be capitalized net of investment income…
Q: On January 1, 2017, SJT Corp. made an initial investment of $1,000,000 and construction began on a…
A: Borrowing Costs: It is the cost incurred in connection with borrowing of funds for construction…
Q: 14. Calypso Inc. employs the cost-to-cost method in determining the percentage of completion for…
A: Using percentage method, the revenue is recognised on the basis of percentage of the work completed…
Q: Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete…
A: Accumulated Depreciation Accumulated depreciation refers to the total depreciation of a fixed asset…
Q: The XYZ Construction Company was awarded a contract for $3,150,000 to build a new building XYZ…
A: Compute percentage of completion for construction as shown below:
Q: The Kirby Construction Company was the low bidder on a specialized equipment contract. The contract…
A: A Bidder is basically that persons who bids (in simple words who desires so makes an demand through…
Step by step
Solved in 2 steps
- During 2016, Green Love Company started a construction work with a contract price of $4,500,000,000. The work was completed in 2018. The following information is available on picture below. (a) Compute the application of the percentage of completion method on a cost to cost basis. (b) Calculate the amount of revenue and gross profit to be recognized annually using the percentage of completion and cost-recovery methods.DM, Inc. works on a P10,500,000 contract in 2015 to construct an office building. During 2015, DM, Inc. uses thecost to cost method. At December 31, 2015, the balances in certain accounts were: Construction in Progress – P3,780,000;Accounts Receivable – P360,000; and Billings on Construction in process – P1,800,000; contract retention – P180,000;Mobilization fee – P140,000. At December 31, 2015, the estimated cost at completion is P7,350,000. Determine the realizedgross profit in 2015PAPASA Co. has consistently used the percentage of completion to account for its construction projects. On January 31, 2017, the company began work on a P4,500,000 construction contract. At the inception date, the estimated cost of the construction was P3,375,000. The following relates to the project Gross profit – 2017 450,000 Cost incurred to date – 2018 2,700,000 Estimated cost to complete – 2018 900,000 Progress billings 2018 3,500,000 How much is the Gross Profit/Loss Realized in 2018? Kindly show your good accounting form for the solution. Thank you!
- Heart, Inc. consistently uses the percentage of completion method of recognizing income. During 2018, Heart started work on a P3,000,000 fixed price project. The accounting records disclosed the following data for the year ended December 31, 2018: Costs incurred, P930,000; Estimated cost to complete, P2,170,000; Progress billings, P1,100,000; Collections, P700,000. How much is the balance of Construction in Progress account in 2018?Archer Construction Company began work on a $420,000 construction contract in 2017. During 2017, Archer incurred costs of $278,000, billed its customer for $215,000, and collected $175,000. At December 31, 2017, the estimated additional costs to complete the project total $162,000. Prepare Archer’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.During 2017, Egyptian Mau Company construct building costing P18,500,000. The weighted average accumulated expenditures on the building during 2017 totaled P7,800,000. The entity borrowed P4,000,000 at 7% on January 1, 2017. Funds not needed for construction were temporarily invested in short-term securities, and earned P120,000 interest revenue. In addition to the construction loan, the entity had two other notes outstanding during the year, P3,000,000, 10-year, 10% note payable dated October 1, 2015, and a 5-year P2,000,000, 8% note payable dated November 2, 2015. What amount of interest should be capitalized on December 31, 2017? A. 574,000 B. 620,000 C. 509,600 D. 629,600
- Shumpert, Inc. entered into a contract that was to take two years to complete, with an estimated cost of $2,257,600. The contract price was $3,160,640. Costs of the contract for 2014, the first year, totaled $1,693,200. a. What was the gross profit reported by the percentage of completion method for 2014?The Skyline Corporation began constructing a building with a contract price of P 43,800,000 in 2009. The ledgers of Skyline for 2010 shows the following accounts: Construction in Progress P 10,400,000 Accounts Receivable 3,200,000 Gross Profit earned 3,952,000 Progress billings to date 6,500,000. What was the amount of collection in 2009?During 2017, Reticulated Company constructed a new manufacturing facility at a cost of P30,000,000. The expenditures for this building, which was finished late in 2017, were incurred evenly during the year. The entity had the following loans outstanding at December 31, 2017. 10% note to finance specifically construction of the manufacturing facility, dated January 1, 2017, P10,000,000. Unpaid as of December 31, 2017. Investments were made on the proceeds from this loan and income of P100,000 was realized in 2017. 12%, 20-years bonds payable issued at face value on April 30, 2016, P30,000,000. 8%, 5-years payable, dated March 1, 2016, P10,000,000. What amount of interest is capitalized as cost of the new building? A. 1,550,000 B. 1,450,000 C. 1,400,000 D. 1,500,000
- Last year, Stone Builders, Inc. started work on a P10,600,000 construction contract which was completed this year. It has consistently used the percentage of completion method of recognizing income. Accounting data provided last year were as follows: Debit: Progress Billings P4,300,000; Credits: Cost incurred 3,450,000 Collections 3,900,000 Estimated cost to complete 3,630,000 What amount of this contract was recognized last year? Brave Corporation authorized Heart on January 1, 2010 to operate as a franchisee for an initial franchise fee of P2,500,000. Of this amount, P1,500,000 was received upon signing of the contract and the balance is due in two equal annual payments beginning January 1, 2011. The contract provides that the nonrefundable downpayment represents fair measure of the services already performed, however, substantial performance is still required of Brave. Collectibility of the note is reasonably certain. If the present value of the two annual payments is P895,000,…During 2009, Mason Construction, Inc. started work on a P 5,200,000 fixed-price construction contract to be completed in two years. The accounting records disclosed the following data for the year ended December 31, 2009: Cost incurred P 2,650,000Estimated cost to complete 2,720,000Progress billings 2,500,000Collections 2,000,000What amount of net income or loss should have been recognized in 2009? On May 1, 2010, Jollibee Inc., a franchisor, entered into a franchise agreement with Session Delights, a franchisee. The total franchise fees agreed upon is P11,900,000 of which P5,000,000 is payable upon signing and the balance payable in three annual payments. It was agreed that the down-payment is nonrefundable, not withstanding the lack of substantial performance of services by franchisor. What amount of deferred revenue should be reported in the May 1, 2010 financial statements of Jollibee Inc.?Virginia Corp. has estimated that total depreciation expense for the year ending December 31, 2017 will amount to $1,280,000, total amortization expense for that period will be $420,000, and employee bonuses for the period will total $320,000. In Virginia’s interim income statement for the six months ended June 30, 2017, what is the total amount of expense relating to these three items that should be reported? $1,010,000 $0 $850,000 $505,000