e. Compute the percent idle time and percent efficiency for the assignment in part d. Note: if the calculated cycle time and the actual bottleneck station time are different, use the actual bottleneck time in your calculations. (Round your answers to 2 decimal places) Idle percentage Efficiency
Q: Describe ERP
A: Businesses generally utilize or apply the enterprise resource planning (ERP) framework for multiple ...
Q: The chart below shows the initial investment and expected yearly payback for Project A and Project B...
A: A Small Introduction about Investment A venture is basically a resource that is made fully intent...
Q: Draw a basic Risk Matrix (Probability vs. Impact) and plot the following FIVE (5) risks. Loss of p...
A: A risk matrix often called a risk diagram anticipated threats or risks in the diagram. In the contex...
Q: Given the product structure, master productionschedule, and inventory status in Figure 14.13, and as...
A: given,
Q: A manufacturer sells a product in two regions. Weekly demand in each region is Normally distributed ...
A: given, standard deviation = 300 weekly demand = 1000 correlation coefficient = -.35
Q: a. Suppose the overall utility (sum of part-worths) of the current favorite cereal is 75 for each ch...
A: Given Table: Wheat/Corn Sweetener Flavor Bits Child Low High Sugar Honey Artificial Present A...
Q: Daily Subway and Bus Use in Five Major C 0.75 0.5 0.25 gapore ez Kong ondon Tokyo v York
A: 1 b ) are unusually reliant on buses 2 c) it began to rebound after 1990
Q: P(X)U.T0.24/0.304 U.155 0.194 Expected value = A previous analysis of historical records found that ...
A: A Small Introduction about Product Management The fundamental target of product management is the...
Q: There are 3 different fire alarm systems in the store. System A detects fire with a probability of 0...
A: In the question, we could see that there are three different fire alarm systems, these systems are s...
Q: A company has an optimistic time of 92 days with pessimistic time of 141 days and the most likely ti...
A: Given: Optimistic time = 92 days Pessimistic time = 141 days Most likely time = 120 days To be de...
Q: b. In order of greatest positional weight. Tiebreaker: most following tasks. (Use your rounded cycle...
A: REMAINING TIME = CYCLE TIME - TASK TIME
Q: b) The Scott Tractor Company ships tractor parts from Omaha to St. Louis by railroad. However, a con...
A: The objective of the maximal flow network diagram is to find the maximum output the firm can get fro...
Q: Critically evaluate the relationship between corporate governance and enterpriserisk management and ...
A: A Small Introduction about Risk Management "Risk management" assists an association with distingu...
Q: strategles be be Impleme der to achie the objective of optimizing the productivity of retail space a...
A: One way to optimize productivity is to use stores. This allows you to do them fast with a minimum of...
Q: e objectives of research.
A: In many professions, understanding all aspects of the research process is a useful skill that may he...
Q: Tonya Manager is interested in expanding her firm and has determined three areas in which she might ...
A: given, Tonya has = $500,000 for investment expected yield on return = 20% yearly
Q: D. The information related to project crashing is shown in the following table. Normal Duration (hou...
A: Find the Cost slope calculations below:
Q: For a time study of a health insurance claims-adjusting process, the analyst uses the continuous met...
A: A Small Introduction about Performance Tasks administrators are answerable for overseeing exercises...
Q: What are the challenges of Filinnials? How do you respond these challenges?
A: Businesses and major corporations prefer to invest in international markets and extend their operati...
Q: Demand 150 250 200 (i) What will be the decision variable for this transportation problem (ii) Devel...
A: Concept Meaning- A prologue to the Transportation problem has been talked about in the past article,...
Q: Covid-19 is an example of a general environment force. Group of answer choices True False
A: A general environment is a environment in which is beyond the controls of an organisation or it is a...
Q: The two main sources of end item product demand which become inputs to the MPS are: a. Known custom...
A: The master production schedule(MPS) is an arrangement for individual wares to be delivered in each t...
Q: Sarah has been employed for just over two years as a supervisor in a facilities management company, ...
A: Saima ought to direct Sarah on the practical angles regarding creating an unreasonable excusal assu...
Q: Operations Management 1. An Enterprise resource-planning system helps a company? a. Find new low cos...
A: Customer relationship management is described as the management of a company's interactions and rela...
Q: Describe the Easy Jet company through a 4V analysis
A: An overview of EasyJet EasyJet is a successful example of a no-frills airline in Europe. According t...
Q: 4. Quantity Discount Model Unitex, the manufacturer of clear cosmetic boxes in problem (2), consumes...
A:
Q: What is the probability that no cars are in the system? What is the average number of cars waiting f...
A: Service rate is the rate at which the customers are being served by the worker in the organizational...
Q: 150 units with a probability of 50% 250 units with a probability of 35% 350 units with a probability...
A: A Small Introduction about Manufacturing Manufacturing is the method involved with transforming un...
Q: Using an appropriate Fixed Order Quantity system model compute the following: (a) Minimum cost prod...
A: NOTE: WE ARE ALLOWED TO DO THE FIRST THREE SUB-PARTS ONLY.
Q: Q4
A: How does post-earnings-announcement drift function, and what causes it? Despite the fact that corpor...
Q: Your Lego furniture company makes Tables and Chairs. Below, you are given the starting inventory, se...
A: T = Units of Tables to be produced C = Units of chairs to be produced Objective function: Max Z = 75...
Q: Cutey Barber Salon Cutey Barber Salon is a trendy barber salon that is located in a densely popula...
A: Given-
Q: What impact does ignoring carrying cost in the allocation ofstock in a DRP system have on lot sizes?
A: Define distribution resources planning (DRP). All tiers of a distribution network should have a time...
Q: The Company makes TSHIRTS at their facility in chicago and Minnesota. The process involves three dep...
A: Capacity utilization = (Available time hours / used time hours) x 100 %
Q: The higher ending inventory will result in higher net profit. What should you do?
A: Merchandise inventory helps in examining the product value that is available in the stock.
Q: As a production manager for RMC, what do you recommend? Why?
A: The production manager should make a decsion that would help in making tasks of the manager easy to ...
Q: Why are Excel skills important in a workplace?
A: Excel skills remain important at a workplace owing to the following reasons: 1. Business Analysis: ...
Q: Colours Galore buys a standard type of paint in 50 litres containers at a price of R800 per containe...
A: A Small Introduction about Inventory Management Inventory management alludes to the most common w...
Q: 8 October 4:14 PM © 18% 0 Assignment Case - 6.. Case Application Poga Poga 2 Higher and Higher You m...
A: Note: “Since you have posted a question with multiple sub-parts, we will solve the first three sub-p...
Q: List and define the main areas of risk management concern.
A: Risk management is the process of identifying, analyzing, and controlling hazards to an organization...
Q: CinEl is a motor company founded in 1937 with its headquarter in Barbados. CinEl is among the leadin...
A: The controlling process can be stated as the technique that can be utilized to ensure standards or q...
Q: What is the rationale for (a) a phantom bill of material, (b) aplann ing bill of material, and (c) a...
A: In the construction, production, or maintenance of any product or service, a bill of materials (BOM)...
Q: ALB. Fach toy 4 type A requires Pro dutes two A manofacturr 4 ALB. Fach toy d type A requires s enoy...
A:
Q: Discuss the ongoing challenges of recruitment trends with respect to women and minorities in law enf...
A: There are various ongoing challenges of recruitment trends with respect to women and minorities in l...
Q: The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements ove...
A: Given-
Q: Early Start, Early Finish, Late Start, Late Finish, Duration, Float Below is a project listed in a t...
A: Given- Activity Predecessor Duration (Weeks) A None 5 B A 3 C A 8 D C 13 E B 7 F B 9 ...
Q: ompute a three-period moving average and a four-period moving average for weeks 5, 6, and 7. Compute...
A: Moving average method of forecasting takes previous months' data into consideration and finds the fo...
Q: Lenovo uses the ZX-81 chip in some of its laptop computers. The prices for the chip during the last ...
A: Calculation of 2 month moving averages of the data (1)month (2)Sales (3)2 month moving total...
Q: A busness is aunchng a new product. The aunch wil require a number of related actvties as follows h...
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and s...
Q: The Industrial and Systems Engineering Department at Sun University is moving from its old building ...
A: Project management is the management in which different kinds of skills, techniques, processes, and ...
I need help with part E
Idle time is equal to Minimum cycle time - task time
Idle % = (Total idle time * 100) /(cycle time * Number. of stations)
Efficiency of time = 1 - Idle time %
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length(minutes) Immediate(Predecessor) a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g Click here for the Excel Data File a. Do each of the following: (1) Enter the number of following tasks for each of the tasks shown in the table below. (2) Assign tasks to stations in order of greatest number of following tasks. Use greatest positional weight as a tiebreaker rule. (3) Determine the percentage of idle time. (Round your answer to 2 decimal places.) (4) Compute the rate of output in printers per day that could be expected for this line, assuming a 420-minute working day. (Round your answer 2 decimal places.) b. Answer these questions: (1) What is the…As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows: Task Duration(minutes) ImmediatePredecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f Click here for the Excel Data File Do each of the following: a. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.) b. Determine the minimum number of stations needed. (Round your answer to the next whole number.) c. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice. d. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation.…Assume that operations on a work package were expected to cost $1,500 to complete the package. They were originally scheduled to have been finished today. At this point, however, we have actually expended $1,200, and we estimate that we have completed four-fifths of the work. What is the Cost-Schedule Index? (0.5) What does it indicate? (0.5) Show all your work and explain.
- (Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?(Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 1. Check for over-allocation. Which resources are over allocated? 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. Does the solution have the minimum number of stations? Explain. How much idle time is there, summed over all workstations? What is the efficiency of this line? SHOW ALL WORK Work Task Task Time (seconds) Task Predecessor(s) A 70 - B 60 A C 120 B D 60 - E 240 C, D F 100 A G 190 E, F
- The times required to complete each of eight jobs in a two-machine flow shop are shown in thetable that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B.a. Determine a sequence that will minimize makespan time.b. Construct a chart of the resulting sequence, and find machine B’s idle time. c. For the sequence determined in part a, how much would machine B’s idle time be reduced bysplitting the last two jobs in half?TIME (hours)Job Machine A Machine Ba 16 5b 3 13c 9 6d 8 7e 2 14f 12 4g 18 14h 20 11If the cycle time is 65.4 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning task A? Task Task Time (seconds) Tasks That Must Precede Other Tasks Number of Following Tasks A 28 - 7 B 13 - 8 C 35 B 7 D 11 A 6 E 20 C 6 F 6 D, E 5 G 23 F 3 H 25 F 2 I 37 G 1 J 11 G, H 1 K 27 I, J 0 Total 236 a. 26.9 minutes b. 37.4 seconds c. 28.5 seconds d. 31.6 seconds e. 57.6 secondsJamison Day Consultants has been entrusted with thetask of evaluating a business plan that has been divided into foursections—marketing, finance, operations, and human resources.Chris, Steve, Juana, and Rebecca form the evaluation team. Eachof them has expertise in a certain field and tends to finish thatsection faster. The estimated times taken by each team memberfor each section have been outlined in the table below. Furtherinformation states that each of these individuals is paid $60/hour.a) Assign each member to a different section such that JamisonConsultants’s overall cost is minimized.b) What is the total cost of these assignments?Times Taken by Team Members for Different Sections (minutes)MARKETING FINANCE OPERATIONS HRChris 80 120 125 140Steve 20 115 145 160Juana 40 100 85 45Rebecca 65 35 25 75
- The Mowry Machine Shop still has five jobs to be processedas of 8 a.m. today (day 23) at its bottleneck operation. The daywhen the order arrived, processing time, and promised duedates are given in the following table. The jobs are listed inthe order of arrival.a. Develop separate schedules by using the FCFS and EDDrules. Compare the schedules on the basis of averageflow time and average days past due.b. Which rule gives the best schedule, in your judgment?Why?A dress-making operation is being designed as an assemblyline. Table 10-22 shows the tasks that need to be performed, theirtask times, and preceding tasks. If the goal is to produce 30 dressesper hour, answer the questions that follow the table. (a) Compute the cycle time.(b) Which task is the bottleneck?(c) What is the maximum output for this line?(d) Compute the theoretical minimum number of stations.(e) Assign work elements to stations, using the longest tasktime rule.(f) Compute the effi ciency and balance delay of yourassignment.please answer 5 questions below, my deadline is coming in tomorrow Information are all in 2 pictures