Economics 2. A bridge connecting two towns costs $15,000,000, has an average annual operating cost of $450,000 and a life of 50 years. It requires a onetime major overhaul in 25 years at a cost of $1,800,000. The sponsors of the project can collect an average toll of $2.50 for each passing vehicle. There will be also $3,000, 000 annual benefits to the communities due to time savings and accident reduction from shorter trips. The total (two-way) annual traffic rate is 1,000,000 vehicles. Determine if this public project is justified (i=5%). The project is justified O The project is not justified

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 10E
icon
Related questions
Question
Economics
2. A bridge connecting two towns costs $15,000,000, has an
average annual operating cost of $450,000 and a life of 50 years. It
requires a onetime major overhaul in 25 years at a cost of
$1,800,000. The sponsors of the project can collect an average toll
of $2.50 for each passing vehicle. There will be also $3,000, 000
annual benefits to the communities due to time savings and accident
reduction from shorter trips. The total (two-way) annual traffic rate is
1,000,000 vehicles. Determine if this public project is justified
(i=5%).
The project is justified
O The project is not justified
Transcribed Image Text:Economics 2. A bridge connecting two towns costs $15,000,000, has an average annual operating cost of $450,000 and a life of 50 years. It requires a onetime major overhaul in 25 years at a cost of $1,800,000. The sponsors of the project can collect an average toll of $2.50 for each passing vehicle. There will be also $3,000, 000 annual benefits to the communities due to time savings and accident reduction from shorter trips. The total (two-way) annual traffic rate is 1,000,000 vehicles. Determine if this public project is justified (i=5%). The project is justified O The project is not justified
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Property Damage
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning