EQUIRED: a. The PERT Network, identifying the critical path and including slack times.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

4. PERT NETWORK, required A. 

5. New York Bldg. Corp., required A & B. 

these has only 3 questions in total. 

4. PERT NETWORK. All audits have a critical path, but auditors seldom recognize it as such without the aid of
network analysis. In the auditing of liabilities, the following activities and estimated times have been identified:
0-1
Obtain schedule of liabilities
2
1-2
Mail confirmations
12
2-6
Process confirmations
39
Investigate debit balances
Vouch selected liabilities
6-7
5
1-3
3 - 4
64
Test accruals and amortization
4
1-4
Test pension plan
Reconcile interest expense to debt
Verify debt restriction compliance
Review subsequent payments
4
4 - 5
5-7
5
7-8
10
REQUIRED:
a. The PERT Network, identifying the critical path and including slack times
5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is
currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty.
Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal
completion time of 22 weeks. The following activities can be crashed.
Activities
Cost to Crash 2 Weeks
Cost to Crash 1 Week
P 8,000
BC
P15,000
19,600
19,500
DE
10,000
8,800
EF
REQUIRED:
a. New York Building desires to reduce the normal completion time Job #181 and, at the same time, report
the highest possible income for the year. New York Building should crash
a. Activity BC 1 week and activity EF 1 week
b. Activity DE 1 week and activity BC 1 week
c. Activity EF 2 weeks
d. Activity DE 1 week and activity EF 1
week
b. Compute for the cost to crash of the activities.
Transcribed Image Text:4. PERT NETWORK. All audits have a critical path, but auditors seldom recognize it as such without the aid of network analysis. In the auditing of liabilities, the following activities and estimated times have been identified: 0-1 Obtain schedule of liabilities 2 1-2 Mail confirmations 12 2-6 Process confirmations 39 Investigate debit balances Vouch selected liabilities 6-7 5 1-3 3 - 4 64 Test accruals and amortization 4 1-4 Test pension plan Reconcile interest expense to debt Verify debt restriction compliance Review subsequent payments 4 4 - 5 5-7 5 7-8 10 REQUIRED: a. The PERT Network, identifying the critical path and including slack times 5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty. Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed. Activities Cost to Crash 2 Weeks Cost to Crash 1 Week P 8,000 BC P15,000 19,600 19,500 DE 10,000 8,800 EF REQUIRED: a. New York Building desires to reduce the normal completion time Job #181 and, at the same time, report the highest possible income for the year. New York Building should crash a. Activity BC 1 week and activity EF 1 week b. Activity DE 1 week and activity BC 1 week c. Activity EF 2 weeks d. Activity DE 1 week and activity EF 1 week b. Compute for the cost to crash of the activities.
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Types of Scheduling
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.