For constructing an embankment, the soil is transported from a borrow area using a truck which can carry 6m- of soil at a time. The details are as follows. Borrow Truck Field Property leose) (compacted)

Principles of Foundation Engineering (MindTap Course List)
9th Edition
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter5: Soil Improvement And Ground Modification
Section: Chapter Questions
Problem 5.5P
icon
Related questions
Question
For constructing an embankment, the soil is transported
from a borrow area using a truck which can carry 6m³
of soil at a time. The details are as follows.
Borrow Truck
Field
Property
area
(loose) (compacted)
Bulk
density
1.66
1.15
1.82oile
(g/cc)
Water
8
14
content (%)
The quantity of soil to be excavated from
the borrow pit, in m3 for a compacted earth fill of
100 m3 is
Transcribed Image Text:For constructing an embankment, the soil is transported from a borrow area using a truck which can carry 6m³ of soil at a time. The details are as follows. Borrow Truck Field Property area (loose) (compacted) Bulk density 1.66 1.15 1.82oile (g/cc) Water 8 14 content (%) The quantity of soil to be excavated from the borrow pit, in m3 for a compacted earth fill of 100 m3 is
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Soil Compaction principles
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning