Given that we are on Day 30 and the following data, what task should receive the highest priority? Job A B C D Due Date Workdays Remaining 35 32 35 45 5 5 10 na
Q: List and describe three time series models, and explain when would you use it? (be specific)
A: Time series models are used to model the evolution of a variable over time. They are used for…
Q: I need help filling out the rest of this chart and the formula ofr multifactor productivity.…
A: Productivity is a measure of how efficiently the inputs are utilized to generate output. Multifactor…
Q: Compute and tabulate the daily demand for each month in the table below (round off to the nearest…
A: Note: We are allowed to do one question only. Daily demand is the demand per day. Daily demand =…
Q: You are the manager of a project to improve a billing process at your firm. The table below contains…
A: The first step here would be to construct a network diagram and find out the critical path and the…
Q: 2) A software developer has four project proposals for new accounting software. This company cannot…
A: Given data is Project Programmers req Capital req ($) Returns ($) 1 7 250,000 650,000 2 9…
Q: What is your forecast for next year's sales? (Do not round intermediate calculations and round your…
A: The least squares method of forecasting is based on the principle that the sum of squared errors…
Q: 1. A company would like to develop an aggregate plan and evaluate its cost using the transportation…
A: Since backorder cost is not given, it is assumed that backorders are not allowed. This means ending…
Q: Webster Chemical’s nominal weight for filling tubes of caulk is 8.00 ounces ± 0.60 ounces. The…
A: Find the Calculations methods below: Given details: Nominal Weight 8 ± 0.6 Ounces Upper…
Q: ending inventory
A: Gross Profit Margin = 55% Beginning Inventory = 142,000 Net Purchases = 202,000 Net Sales = 433,000
Q: What is the shortest path and what is the shortest possible time to travel from A to Z? (Round your…
A: A critical path network diagram is a system-level representation of the tasks or activities that…
Q: 1. Foxie Owl’s Besty Bagel shop makes fresh bagels. She has to buy raw materials fresh every day for…
A: Given data: Daily demand- 200, 225, 250, 275, or 300 bagels. Fill Rate requirement = 96% or 0.96
Q: A hotel has 200 rooms and 2 fares: low fare, which is $250 per night’s stay, and high fare, which is…
A: The protection level refers to the number of rooms in a hotel that are kept reserved for the high…
Q: CRISIS IT In May 2007, Frontier Airlines Holdings hired Gerry Coady as chief information officer…
A: 1. Too many projects and too few resources: The airline had accepted too many projects. As the…
Q: Problem 7: Write the MOST equation for the task: "A worker slides a ruler (within reach) and pushes…
A: MOST (Maynard operation sequence technique) is the time and motion study technique used in…
Q: United Airlines has an agreement to buy jet fuel from Exxon. The goal is to minimize total cost…
A: Given data: Annual demand (D) = 201,000 barrel Order cost (S) = $ 3740 Holding cost (H) = $ 20…
Q: A big box store sells a lawn mower. Annual demand for the lawn mower is 600 units. The ordering…
A: Annual Demand = D = 600 units Ordering cost per order = S = $20 Annual Holding Cost per unit = H =…
Q: Quality is a new competitive weapon" Justify the statement.
A: The quality of a product or service is the degree to which the product or service possesses…
Q: To From A Select one: 6 O 8 a. Unbalanced b. Unbounded 2 Demand 400 200 The solution presented in…
A: A transpiration cost matrix will helps to identify the optimal allocation for costs based on the…
Q: Space Costs Traffic density Neighborhood income Zoning laws 0.25 0.25 0.20 0.15 0.15 65 40 55 45 85…
A: Ans) a) Formula: Solution: Conclusion or Answer: Best Location: Baptist Church Weighted Score =…
Q: The objective of inventory management is to minimize inventory costs while A.having only enough…
A: Ans) Inventory is usually maintained if they are supply shortages or increase in demand. It helps in…
Q: what is the pareto chart and discuss its benefits and application in the project management field.
A: The Pareto Principle, usually referred to/known as the 80/20 rule, argues that 20% of the labor can…
Q: 5. Consider the following project network, consisting of 10 activities (A-J) Activity Predecessor(s)…
A: AOA is a project management tool that used to map and schedule the project activities, events or…
Q: Torrance Refinery produces approximately 23.1 Million barrels of gasoline per year. A California…
A: Given data: Production per year (p)= 23.1 Million barrel Demand per year (D) = 5.3 Million barrels…
Q: Based on available information, lead time demand for PC thumb drives averages 51 units (normally…
A: Given data; d Average Demand 51 units SD Standard deviation 5 units Service level 98%…
Q: Describe the steps used to develop a forecasting system.
A: Forecasting is a method of predicting the unknown. In other words, it is a step forward by looking…
Q: Emerald manufactures large screen televisions. Their best-selling model has annual demand of…
A: Given data: Annual demand = 8,000 units/year Daily production capacity (p) = 200 units/day. Setup…
Q: Scenario 14.1 — Vidalia Onions When Vidalia onions are ready, the entire 13 county (plus parts of…
A: Given data: The safety inventory requires = 30% of lead time demand Holding cost for a bag =15% of…
Q: XYZ Corporation operates two plants, each of which has a capacity of 170 units per day. Each day,…
A: Ans) Formula used in excel sheet: Solver Pic:
Q: a) Explain what a “supply chain” is. b) Explain why practioneers of supply chain management need…
A: Supply chain management is an important part of business strategy. It can be used to improve…
Q: A serial system is assembled in house from 20 parts. To be successful in the marketplace the system…
A: A reliability block diagram (RBD) is a method to depict the contribution of reliability of component…
Q: Briefly describe what happens in each of the five project management process groups (initiating,…
A: Project management is concerned with designing and planning business projects keeping in mind the…
Q: The forecast error in a given time period is obtained by subtracting the actual value of the…
A: Forecasting shows the procedure of taking more instructed projections by utilizing recorded info as…
Q: What information would you need in order to demonstrate to Mr. John how to balance the assembly…
A: Project schedule helps in calculating different values related to the production cycle like the…
Q: A cause -and-effect diagram is used to identify the possible causes of defects. Draw a Cause and…
A: Cause and effect diagram aka fishbone diagram aka Ishikawa diagrams are causal diagrams created by…
Q: Answer the following questions based on the Tornado and Sensitivity graphs given below. Which input…
A: In optimization, it is important to identify a variable that requires effort to evaluate but has the…
Q: The average number of customers waiting. (Round your intermediate calculations to 3 decimal places…
A: Given the data stated below, Here, the arrival rate is 4 per hour whereas the service time is 13…
Q: CRISIS IT In May 2007, Frontier Airlines Holdings hired Gerry Coady as chief information officer…
A: Weighted score model is a mdoel which helps to compare different options based on certain score…
Q: In the following scenario, what will your stockout costs be if you have 200 hammers in stock and you…
A: Arrange the orders in ascending order Order received 80 60 50 30 120 Order…
Q: What is the difference between a progress report and a status report? Give examples of both
A: The main aim of a progress report is to show the tasks accomplished by a project team during a…
Q: L. Houts Plastics is a large manufacturer of injection-molded plastics in North Carolina. An…
A: Ans) Formula: Item is classified A if the cumulative percent is less than or equal to 80% Item is…
Q: Evaluate the effectiveness of a Agile/Scrum approach compared to a plan-based approach based on the…
A: The concepts of agile and scrum are not so different from each other. Agile is a concept that helps…
Q: Problem 20-8 (Algo) Lakeside Bakery bakes fresh pies every morning. The daily demand for its apple…
A: *The question given in the heading is not relevant to the subject, so I have solved the below…
Q: The Ottery Creek Winery produces three kinds of table wine - a blush, a white, and a red. The winery…
A: Let Blush wine, white wine and red wine be represented by B, W and R respectively. Maximize…
Q: a) What percentage improvement is needed in the supply chain strategy for profit to improve to…
A: First to identify the given data, the sales is $100,000, the given cost of material is 45% of sales…
Q: Part 2 Calculation Questions As assistant manager of a soccer specialty store you have been asked to…
A: Given data: Average weekly demand (d) = 18 pairs/week Standard Deviation of demand = 6 pairs Lead…
Q: To meet holiday demand, Alex's Pie Shop requires a production line that is capable of producing 50…
A: Cycle time is the proportion between total available time and total demand. Considering the given…
Q: Chiltern Farms “[T]he beautiful valley of Vyeboom nestled between the majestic Franschhoek Mountains…
A: Supply Chain Management relates to the distribution network that is laid out to move or dispatch…
Q: The table below provides financial information for a hardware retailer. What is the retailer's…
A: Given data; Cost of goods sold 33180 units Average inventory 8000 units No. of days 365…
Q: Safety stock = units (round your response to the nearest whole number).
A: Mean demand = 70 units Standard Deviation of demand = 7 units Service Level = 90%
Q: Tyler Apiaries sells bees and beekeeping supplies. Bees (including a queen) are shipped in special…
A: The capacity of a process to deliver outputs within a customer-generated set of "specification…
Calculate the Critical Ratio and provide the priority order based on your calculations. The data will be provided in the question.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- All projects utilise several different resources to successfully complete the project successfully tothe customer or sponsors requirements.Resources add another dimension to planning and scheduling. This includes people, materials,equipment, tool, facilities and so forth.The quantity and availability of these resources are often limited and cause project to face risks orconstraints which needs to be managed carefully.With the above statements , differentiate between Resource smoothing and resourcelimited scheduling then to substantiate your answer by providing at least two (2) situations whereresource limited scheduling may occur1. Which of the following is generally considered a characteristic of project process? A. Operations and equipment are dedicated to the product B. Work is not fixed but moves through a sequence of operations C. Products or services are standard and are produced in a large volume D. Processes are linear and often continuous but can be stopped E. The product or service will be made to a specific customer order 2. Select those of the following that would normally be considered true of Operations A. Operations is the part of the organisation that is easiest to manage B. Most of the investment in technology is in operations C. Operations can contribute little to making a firm world less competitive D. Operations is the area of the business that most of the people do not workA project has a budget of $300,000 and is expected to last 10 months, with the work results and budget spread evenly across all months. The project just completed its 3rd month, the work is on schedule, and $65,000 has been spent. What is the cost variance? How efficient (in %) must work progress be to complete on time and within budget?
- You will be a Project Manager soon, How can you practice standards for scheduling? Give example or scenario, and apply the key components of proper scheduling.Executing processes exclude coordinating people and other resources to carry out the various plans and create the products, services, or results of the project or phase Select one: True False A ______ is a series of actions directed toward a particular result. Select one: a. project b. process c. plan d. goal A dependency or relationship pertains to the sequencing of project activities or tasks Select one: True False Determine budget output Select one: a. Work performance information, cost forecasts, change requests, project management plan updates, project documents updates, organizational process assets updates b. Activity cost estimates, basis of estimates, project documents updates c. Cost management plan d. Cost baseline, project funding requirements, project documents updatesWhat is a workflow chart and how is it important for business planning purposes?
- College students always have a lot of work to do, but thissemester, Katie Lawrence is overwhelmed. Following arethe assignments she faces, the estimated completion times(in days), and due dates:Help Katie prioritize her work so that she completes asmany assignments on time as possible. Today is November2. How would your sequence of assignments change ifKatie were interested in minimizing the mean tardiness ofher assignments?You are managing a software project with an initial budget estimate of 5 million USD. During interim cost and schedule performance analysis, you figured out that: You should have spent $650,000 till now based on your initial plans and 1,500 man/days of schedule activities You spent $425,000 till now and completed 600 man/days of schedule activities which should have cost $525,000 based on your initial plans. You re-estimated the budget required for the remaining work to be done as $4,500,000. Identify: BAC PV AC EV ETC Calculate: CPI SPI CV SV VAC EAC TCPI(Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?
- (Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 1. Check for over-allocation. Which resources are over allocated? 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?You are managing a software development project. Only 35% of the work has so far been completed, while the planned schedule called for 50% completion by this date. Originally budgeted for $250,000, the team has already spent $150,000 on the project. What is the best way to describe the state of this project? Ahead of schedule, within budget Behind schedule, within budget Ahead of schedule, over budget Behind schedule, over budgetFreed works for a traditional company that expects him to start at 8.30 a.m. and leave at 5.30 p.m. or later every day. Most of his work is done on a project basis and, as a manager, he is responsible for the quality of work that is produced and for meeting deadlines, as the nature of his work involves meeting deadlines, achieving certain objectives, and hitting targets. On most days of the week, there is often extra work to be done on a project, and Freed stays late in the office or brings his work home. Occasionally, his director and colleagues find him missing important information in a meeting because he was thinking about something else.People sometimes think about something other than what they’re doing. Their minds wander, whether they are trying to read important emails, speaking to clients, updating the sales figures, or talking to colleagues, creating barriers in communication not only for themselves but also their receivers. Justify this statement in keeping with the…