Identify: BAC PV AC EV ETC Calculate: CPI SPI CV SV VAC EAC TCPI

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter11: Simulation Models
Section: Chapter Questions
Problem 68P
icon
Related questions
icon
Concept explainers
Topic Video
Question

You are managing a software project with an initial budget estimate of 5 million USD. During interim cost and schedule performance analysis, you figured out that:

  • You should have spent $650,000 till now based on your initial plans and 1,500 man/days of scheduled activities
  • You spent $425,000 till now and completed 600 man/days of scheduled activities which should have cost $525,000 based on your initial plans.
  • You re-estimated the budget required for the remaining work to be done as $4,500,000.

Identify:

  1. BAC
  2. PV
  3. AC
  4. EV
  5. ETC

Calculate:

  1. CPI
  2. SPI
  3. CV
  4. SV
  5. VAC
  6. EAC
  7. TCPI

Once you've calculated this, what does it mean for your project and your stakeholders?

Note: You won't be able to view anyone else's response until you've posted yours.  Also, feel free to use Google, if needed to help give you further clarity on the formulas being used.  Be sure to submit an initial, substantive post by Friday at 11:59 p.m. CST.  

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 7 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,