It has been established that completion of construction projects can be delayed because of unfavourable weather conditions. The probabilities are 0.6 that there will be unfavourable weather, and 0.85 that the construction project will be completed on time if the weather is favourable and 0.35 that the construction project will be completed on time if there is unfavourable weather.

Holt Mcdougal Larson Pre-algebra: Student Edition 2012
1st Edition
ISBN:9780547587776
Author:HOLT MCDOUGAL
Publisher:HOLT MCDOUGAL
Chapter11: Data Analysis And Probability
Section11.8: Probabilities Of Disjoint And Overlapping Events
Problem 2C
icon
Related questions
icon
Concept explainers
Topic Video
Question

It has been established that completion of construction projects can be delayed because of unfavourable weather conditions. The probabilities are 0.6 that there will be unfavourable weather, and 0.85 that the construction project will be completed on time if the weather is favourable and 0.35 that the construction project will be completed on time if there is unfavourable weather.

What is the probability that the construction project will not be completed on time?

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Sample space, Events, and Basic Rules of Probability
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Holt Mcdougal Larson Pre-algebra: Student Edition…
Holt Mcdougal Larson Pre-algebra: Student Edition…
Algebra
ISBN:
9780547587776
Author:
HOLT MCDOUGAL
Publisher:
HOLT MCDOUGAL
College Algebra
College Algebra
Algebra
ISBN:
9781337282291
Author:
Ron Larson
Publisher:
Cengage Learning