Job 75 incurred the following costs for the manufacture of 200 units of motors: Original cost accumulation Direct materials Direct labor P 13,200 16,000 24,000 Factory overhead (150% of direct labor) Direct costs of reworked 10 units Direct materials Direct labor The total rework costs were attributable to exacting specifications of Job 75 and the full rework costs were charged to the specific job. 5. The cost of Job 75 was 2,000 3,200 а. Р316 b. P 266 с. Р 280 d. P 292
Q: The charges to Work in Process-As production. Bal., 9,000 units, 60% completed Direct materials,…
A: The question is based on the concept of Cost Accounting. As per Bartleby guidelines we are allowed…
Q: Fuller Manufacturing Co. Ltd. makes a product by way of three consecutive processes. The following…
A: Journal Entries are represented as below:
Q: Samar Company’s Job 888 manufactured 13,750 units that were completed in February at unit costs…
A: A unit cost refers to the total expense which is incurred by the company to manufacture, store and…
Q: Department S had no work in process at the beginning of the period. It added 12,000 units of direct…
A: The calculation of conversion cost has been made as follows: Conversion cost=Direct labor+Factory…
Q: Condotti Company's Job 205 for the manufacture of 6,600 units coats completed during August 20x8 at…
A: Manufacturing cost means the cost incurred to produce the finished goods in factory. Fixed…
Q: Jenny Company's Job No. 520 for the manufacture of 6,600 coats was completed December at the…
A: Job order costing: Job order costing is one of the methods of cost accounting under which cost is…
Q: Blue Co.'s Job 405 for the manufacture of 2,200 wagons was completed during August at the unit costs…
A: Here in this question, we are required to calculate unit cost of goods. When spoilage loss…
Q: Fuller Manufacturing Co. Ltd. makes a product by way of three consecutive processes. The following…
A: 1 (a) Compute total cost of units completed and transferred to Process 3: Compute the cost of…
Q: 2. GondolaB Company's Job No. 205 (for the manufacture of 6,600 coats) was completed August, 20M at…
A: The total cost of 6000 units manufactured needs to include the loss from defective material sale.
Q: Thventcay End Job 75 incurred the following costs for the manufacture of 200 units of motors:…
A: Since the rework costs were completely related to the Job 75, the total rework costs should be…
Q: Simar Company’s Job 888 manufactured 13,750 units that were completed in February at unit costs…
A: Unit cost of good units = (Total cost incurred - Realizable value of spoiled units) / No. of good…
Q: The following data refers to a process: Material input from previous process: 4,000 litres at a cost…
A: Given data: Material input transferred from previous process = 4,000 liters at the cost of 5,400…
Q: Costs incurred are summarized as follows: WIP - Polishing Process A/C January 1 Bal.…
A:
Q: The total cost assigned to job 777C is P24,000 which includes direct materials cost of P6,000. The…
A: Total cost = P24,000 Conversion cost applied = Total cost - Direct material cost = P24,000 -…
Q: Department S had no work in process at the beginning of the period. It added 10,000 units of direct…
A:
Q: Breeze Company started and completed Job 9, produced 10,000 units, during previous month. Cost…
A: The full absorption costing is an account for all cost Direct Labour, Direct material, variable…
Q: Original cost accumulation: Direct materials…
A: Units produced for job 75 = 10 units To calculate cost per unit , we need to include all cost…
Q: Muller Manufacturing Co. Ltd. makes a product by way of three consecutive processes. The following…
A: Completed Units = Total Input - Scrap Units - Closing WIP units=1,500-200-400=900 Units
Q: Muller Manufacturing Co. Ltd. makes a product by way of three consecutive processes. The following…
A: Journal Entries are represented as below:
Q: The total cost of units completed during the period was a.$88,000 b.$171,600 c.$240,240…
A: Given information is: Department S had no work in process at the beginning of the period. It added…
Q: The following cost data relates to Job 2A32: Direct material RO 10,000, Direct labor cost RO 4,500…
A: Total Manufacturing overhead cost = no. of machine hours x cost per machine hour = 140 machine hours…
Q: Elmer Company’s Job #040335 for the manufacture of 6,600 coats was completed during March at the…
A: No. of good coats = Total coats produced - no. of coats spoiled = 6600 - 600 = 6000
Q: The following information is available for Integrity Co. for the current year: Beginning Work in…
A: Equivalent units means where the some opening and closing work in progress are not fully completed…
Q: Job #2365 incurred the following during production: Direct Materials: $25,000 Manufacturing Labor:…
A: Job costing is a method of costing that involves calculating the cost of individual jobs.
Q: Direct labor-hours required to support estimated production Machine-hours required to support…
A: Manufacturing cost indicates the total amount incurred by the corporation in its operations to make…
Q: The following information is available for Integrity Co. for the current year: Beginning Work in…
A: In a manufacturing process, a product passes through the different stages of production. In such a…
Q: John Manufacturing Co. Ltd. makes a product by way of three consecutive processes. The following…
A: Units completed=Input-Closing WIP-Loss=1500-400-200=900 units
Q: Department S had no work in process at the beginning of the period. It added 13,400 units of direct…
A: Answer for first question:
Q: The cost of materials transferred into the Rolling Department of Keystone Steel Company is $590,700…
A: Cost: In accounting, the term cost is the monetary value spend by the company for material, services…
Q: During March, Mark Company incurred the following costs on Job 209 for the 200 motors: Original cost…
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: Muller Manufacturing Co. Ltd. makes a product by way of three consecutive processes. The following…
A: a) Completed Units =Total Input - Scrap Units -Closing WIP Units=1,500-200-400=900 Units
Q: When Job 117 was completed, direct materials totaled $4.400: direct labor, 55,600; and factory…
A: Given the following information: Direct materials: $4,400 Direct labor: $55,600 Factory overhead:…
Q: 18. During March, Sky Company incurred the following costs on Job 109 for the manufacture of 200…
A: Cost per finished unit of job109=Original cost +Rework cost200 motors=P2,660+P260200 motors=P14.60…
Q: John Manufacturing Co. Ltd. makes a product by way of three consecutive processes. The following…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: Job 75 incurred the following costs for the manufacture of 200 units of motors: Original cost…
A: Dear student, we can answer the first question (question no 5), if the student posts multiple…
Q: Direct Labor 180 Factory overhead, included P10 allowance for spoilage 180 Final inspection…
A: Cost of production(COP) refers to material, labours and overheads incurred during production.
Q: During August of the current year, Job 067 for 2,000 handsaws was completed at the following cost…
A: Cost per unit means the cost incurred to produce one unit. Any expenses incurred to rectified the…
Q: A product passes through two process A and B in the manufacturing process. The information related…
A: Process Manufacturing: Process manufacturing refers to the process of creating goods by mixing…
Q: During August of the current year, Job 067 for 2,000 handsaws was completed at the following cost…
A: Internal failure costs : Internal failure costs are costs that are caused by products or services…
Q: Costs incurred are summarized as follows: WIP - Polishing Process A/C January 1 Bal.…
A: Direct Materials refers to the raw materials used to manufacture a product. Normally all the direct…
Q: Items 17 and 18 are based on the following information: During March, SOFIA COMPANY incurred the…
A: Job costing is a method or technique of costing, in which all costs related to particular job are…
Q: ABC Company’s Job 123 for the manufacture of 2,000 bags was completed during June 2022 at the…
A: Total manufacturing costs of a job includes direct material costs, direct labour costs and factory…
Q: Elmer Company’s Job #040335 for the manufacture of 6,600 coats was completed during March at the…
A: There is no cost assigned to Scrap and hence there will be no distinction is made between normal and…
Q: Assume that the defective goods were charged to all jobs, what is the cost transferred to finish…
A: Job costing is a method of costing in which the cost will be allocated to each job to find out the…
Q: Lopez Company started and completed Job 9, produced 10,000 units, during previous month. Cost…
A: Solution: Computation of Total Cost of Job 9 Particulars Dept A Dept B Dept. C Total Direct…
Q: During March, Mark Company incurred the following costs on Job 209 for the 200 motors: Original cost…
A: Factory overhead for reworked units=Direct labor×Factory overhead's original costDirect labor…
Q: CS Company started work on three job sites during the current year. Any costs incurred are expected…
A: Given : Site Contract price Cost incurred Estimated cost to incomplete Billing on contract…
Q: Costs incurred are summarized as follows: WIP - Polishing Process A/C January 1 Bal.…
A: Normal losses are those losses of the firm that are inherent in the operations of the processes,…
Step by step
Solved in 2 steps
- A machine shop manufactures a stainless steel part that is used in an assembled product. Materials charged to a particular jobamounted to 600. At the point of final inspection, it was discoveredthat the material used was inferior to the specifications required bythe engineering department; therefore, all units had to be scrapped. Record the entries required for scrap under each of the following conditions: a. The revenue received for scrap is to be treated as a reductionin manufacturing cost but cannot be identified with a specificjob. The value of stainless steel scrap is stable and estimatedto be 125 for this job. The scrap is sold two months later forcash at the estimated value of 125. b. Revenue received for scrap is to be treated as a reduction inmanufacturing cost but cannot be identified with a specificjob. A firm price is not determinable for the scrap until it issold. It is sold eventually for 75 cash. c. The production job is a special job, and the 85 received onaccount for the scrap is to be treated as a reduction inmanufacturing cost. (A firm price is not determinable for thescrap until it is sold.) d. Only 40 cash was received for the scrap when it was sold inthe following fiscal period. (A firm price is not determinablefor the scrap until it is sold, and the amount to be received forthe scrap is to be treated as other income.)Original cost accumulation: Direct materials P13,200 Direct labor 16,000 Factory overhead (150% of direct labor) 24,000 Direct costs of reworked 10 units Direct materials 2,000 Direct labor 3,200 The total rework costs were attributable to exacting specifications of Job 75 and the full rework costs were charged to the specific job. The cost per unit of Job 75 wasSimar Company’s Job 888 manufactured 13,750 units that were completed in February at unit costs presented as follows: Direct materials P300 Direct labor 270 Factory overhead (includes an allowance of P15 Spoiled work) 270Final inspection of Job 888 disclosed 1,250 spoiled units, which were sold for P225,000.What would be the unit cost of good units if the spoilage loss is attributable to exacting specifications of Job 004?
- Elmer Company’s Job #040335 for the manufacture of 6,600 coats was completed during Marchat the following unit costs:Direct materials P1,500Direct labor 1,000Manufacturing overhead (includes allowances of P50 for spoiled work) 5003,000Final inspection of job #040335 disclosed 600 spoiled coats, which were sold to a jobber forP600,000.29. What would be the unit cost of the good coats produced on job #040335 assuming thatspoilage loss is charged to all production? Attributable to exacting specifications of job#040335?a. 2,950 b. 3,000 c. 3,145 d. 3,200Elmer Company’s Job #040335 for the manufacture of 6,600 coats was completed during Marchat the following unit costs:Direct materials P1,500Direct labor 1,000Manufacturing overhead (includes allowances of P50 for spoiled work) 5003,000Final inspection of job #040335 disclosed 600 spoiled coats, which were sold to a jobber forP600,000.29. What would be the unit cost of the good coats produced on job #040335 assuming thatspoilage loss is charged to all production? Attributable to exacting specifications of job#040335?a. 2,950 b. 3,000 c. 3,145 d. 3,20030. Using the information in item 29, what is the journal entry to record the disposal of thespoiled coats?a. Cash 600,000Manufacturing overhead 1,200,000Work in process -Job #040335 1,800,000b. Cash 600,000Work in process -Job #040335 600,000c. Cash 600,000Abnormal loss 1,200,000Work in process -Job #040335 1,800,000d. Cash 600,000Manufacturing overhead 1,170,000Work in process -Job #040335 1,170,000Integrity Company’s Job 1088 manufactured 13,750 units that were completed in February at unit costs presented as follows:Direct materials- P300Direct labor- 270Factory overhead (includes an allowance of P15 spoiled work)- P270Final inspection of Job 1088 disclosed 1,250 spoiled units, which were sold for P225,000.What would be the unit selling price if the spoilage is attributable to exacting specifications of Job 1088 and the entity maintain a gross profit of 50%?
- Samar Company’s Job 888 manufactured 13,750 units that were completed in February at unit costs presented as follows: Direct materials P300 Direct labor 270 Factory overhead (includes an allowance of P15 Spoiled work) 270Final inspection of Job 888 disclosed 1,250 spoiled units, which were sold for P225,000.What would be the unit cost of good units if the spoilage loss is attributable to exacting specifications of Job 004? a. 840 b. 889.50 c. 825 d. 862.50Zea Company’s Job 888 manufactured 13,750 units that were completed in February at unit costs presented as follows: Direct materials $300 Direct labor 270 Factory overhead (includes an allowance of P15 Spoiled work) 270Final inspection of Job 888 disclosed 1,250 spoiled units, which were sold for $225,000.What would be the unit cost of good units if the spoilage loss is attributable to exacting specifications of Job 004?2. GondolaB Company's Job No. 205 (for the manufacture of 6,600 coats) was completed August, 20M at the following unit costs: Direct materials - P1,500, Direct labor - 1,000, Factory overhead (including allowance of P50 for spoiled work) - 500. Total = P3,000. Final inspection of Job No. 205 disclosed 600 spoiled costs. These were subsequently sold to a jobber for P600,000. Assuming that spoilage loss is chargeable to the particular job, the unit cost of the good coats produced per Job No. 205 must be: P3,145 P2,950 P3,000 P3,150
- Nadia Company's Job No. 310 (for the manufacture of 6,600 coats) was completed on September 20 at the following unit costs: Direct materials - $1,500, Direct labor - 1,000, Factory overhead (including allowance of$P50 for spoiled work) - 500. Total = $3,000. Final inspection of Job No. 310 disclosed 600 spoiled costs. These were subsequently sold to a jobber for P600,000. Assuming that spoilage loss is chargeable to the particular job, the unit cost of the good coats produced per Job No. 310 must be:Martin Company received an order for 25 automatic mixing machines. Because of the order's exacting specifications, it is anticipated that defective and spoiled work will exceed the normal rate. The materials cost per unit is P80; labor cost, P194; and manufacturing overhead for this order is to be applied at 100% of the labor cost. During production, 5 units were found to be defective and required the following total additional costs: materials, P97, labor, P125, and manufacturing overhead at the 100% rate. On final inspection, 2 units were classified as seconds and sold for P400 each, the proceeds being credited to the order. The purchaser has agreed to accept the 23 machines, although the acceptable units are fewer than the number ordered. What is the unit cost of the completed units? (Round-off to the nearest peso) IN A GOOD ACCOUNTING FORM WILL BE GREAT ALSO!Martin Company received an order for 25 automatic mixing machines. Because of the order's exacting specifications, it is anticipated that defective and spoiled work will exceed the normal rate. The materials cost per unit is P80; labor cost, P194; and manufacturing overhead for this order is to be applied at 100% of the labor cost. During production, 5 units were found to be defective and required the following total additional costs: materials, P97, labor, P125, and manufacturing overhead at the 100% rate. On final inspection, 2 units were classified as seconds and sold for P400 each, the proceeds being credited to the order. The purchaser has agreed to accept the 23 machines, although the acceptable units are fewer than the number ordered. What is the unit cost of the completed units? (Round-off to the nearest peso) ANSWER IN GOOD ACCOUNTING FORM. THANK YOU :)