Marigold Construction Company began operations on January 1, 2020, During the year, Marigold Construction entered into a contract with Luhdquist Corp. to construct a manufacturing facility. At that time, Marigold estimated that it would take 5 years to complete the facility at a total cost of $4,501.00O. The total contract price for construction of the facility is $6.031.000, During the year, Marigold incurred $1,083,200 in construction costs related to the construction project. The estimated cost to complete the contract is $4,332.800. Lundquist Corp. was billed and paid 26% of the contract price. Prepare schedules to compute the amount of gross proft to be recognized for the year ended December 31. 2020, and the amount to be shown as "costs and recognized pront in excess of billings or "billings in excess of costs and recognized pront" at December 31, 2020, under each of the following methods. (Enter negative amounts using elther a negotive sign preceding the number eg 45 or parentheses eg. (45). Iif answer is 0, please enter 0. Do not leave any fields blank.) (a) Completed-contract method. Gross Profit to be recognized

Financial And Managerial Accounting
15th Edition
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:WARREN, Carl S.
Chapter27: Lean Manufacturing And Activity Analysis
Section: Chapter Questions
Problem 18E: Cost of quality and value-added/non-value-added reports for a service company A. Using the...
icon
Related questions
Question
Marigold Construction Company began operations on January 1. 2020. During the year, Marigold Construction entered into a
contract with Lundquist Corp. to construct a manufacturing facility. At that time, Marigold estimated that it would take 5 years to
complete the facility at a total cost of $4,501.000. The total contract price for construction of the facility is $6.031,000, During the
year, Marigold incurred $1.083,200 in construction costs related to the construction project. The estimated cost to complete the
contract is $4,332.800. Lundquist Corp. was billed and paid 26% of the contract price.
Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31. 2020, and the amount to
be shown as "costs and recognized proft in excess of billings" or "billings in excess of costs and recognized proft" at December 31.
2020, under each of the following methods. (Enter negative amounts using elther a negative sign preceding the number eg 45 or
parentheses eg. (45). If answer is 0, please enter 0, Do not leave anry fields blank.)
fa) Compieted-contract method.
Gross Profit to be recognized
Transcribed Image Text:Marigold Construction Company began operations on January 1. 2020. During the year, Marigold Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Marigold estimated that it would take 5 years to complete the facility at a total cost of $4,501.000. The total contract price for construction of the facility is $6.031,000, During the year, Marigold incurred $1.083,200 in construction costs related to the construction project. The estimated cost to complete the contract is $4,332.800. Lundquist Corp. was billed and paid 26% of the contract price. Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31. 2020, and the amount to be shown as "costs and recognized proft in excess of billings" or "billings in excess of costs and recognized proft" at December 31. 2020, under each of the following methods. (Enter negative amounts using elther a negative sign preceding the number eg 45 or parentheses eg. (45). If answer is 0, please enter 0, Do not leave anry fields blank.) fa) Compieted-contract method. Gross Profit to be recognized
Computation of Gross Profit to Be Recognized
under Percentage-of-Completion Method
Total Estimated Cost
Estimated Profit
%24
Percentace-of Completion
Gross Proft
Estimated Profit
Percentage-of-Completion
21
Transcribed Image Text:Computation of Gross Profit to Be Recognized under Percentage-of-Completion Method Total Estimated Cost Estimated Profit %24 Percentace-of Completion Gross Proft Estimated Profit Percentage-of-Completion 21
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub