McDonalds has a drive-through window and, during peak lunch times, can handle a maximum of 85 cars per hour with one person taking orders, assembling them, and acting as cashier. The average sale per order is $12.00.    A proposal has been made to add two additional workers and divide the tasks among the three. One will take orders, the second will assemble them, and the third will act as a cashier. With this system, it is estimated that 120 cars per hour can be serviced. Use productivity arguments to recommend whether or not to change the current system.   Hint: Productivity = revenue/labor dollar

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

McDonalds has a drive-through window and, during peak lunch times, can handle a maximum of 85 cars per hour with one person taking orders, assembling them, and acting as cashier. The average sale per order is $12.00. 

 

A proposal has been made to add two additional workers and divide the tasks among the three. One will take orders, the second will assemble them, and the third will act as a cashier. With this system, it is estimated that 120 cars per hour can be serviced. Use productivity arguments to recommend whether or not to change the current system.

 

Hint: Productivity = revenue/labor dollar 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,